{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 April 22, 2013 Mr. D. R. Madison Vice President  
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 April 22, 2013 Mr. D. R. Madison Vice President Southern Nuclear Operating Company, Inc.
 
Edwin I. Hatch Nuclear Plant 11028 Hatch Parkway North Baxley, GA 31513
Southern Nuclear Operating Company, Inc. Edwin I. Hatch Nuclear Plant 11028 Hatch Parkway North Baxley, GA 31513  


==SUBJECT:==
==SUBJECT:==
Line 23: Line 22:


==SUMMARY==
==SUMMARY==
  - EDWIN I. HATCH NUCLEAR PLANT DOCKET NOS. 50-321 AND 50-366  
  - EDWIN I. HATCH NUCLEAR PLANT DOCKET NOS. 50-321 AND 50-366


==Dear Mr. Madison:==
==Dear Mr. Madison:==


This refers to the meeting conducted on April 17, 2013, in Vidalia, Georgia. The purpose of the meeting/open house session was to provide opportunities to discuss the annual assessment of Edwin I. Hatch Nuclear Plant with the public for the period of January 1, 2012, - December 31, 2012. Enclosed are a list of attendees, copies of the poster boards displayed at the meeting, and the meeting handout.
This refers to the meeting conducted on April 17, 2013, in Vidalia, Georgia. The purpose of the meeting/open house session was to provide opportunities to discuss the annual assessment of Edwin I. Hatch Nuclear Plant with the public for the period of January 1, 2012, - December 31, 2012. Enclosed are a list of attendees, copies of the poster boards displayed at the meeting, and the meeting handout.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be  
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS).
 
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
available electronically for public in spection in the NRC Public Document Room (PDR) or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).  
 
Should you have any questions concerning this meeting, please contact me at (404) 997-4611.
Should you have any questions concerning this meeting, please contact me at (404) 997-4611.
Sincerely,
Sincerely,
/RA By Jannette Worosilo For/  
                                                /RA By Jannette Worosilo For/
 
Frank Ehrhardt, Chief Reactor Projects Branch 2 Division of Reactor Projects Docket Nos.: 50-321 and 50-366 License Nos.: DPR-57 and NPF-5
Frank Ehrhardt, Chief       Reactor Projects Branch 2 Division of Reactor Projects Docket Nos.: 50-321 and 50-366 License Nos.: DPR-57 and NPF-5  


==Enclosures:==
==Enclosures:==
: 1. List of Attendees
: 1. List of Attendees
: 2. Poster Boards
: 2. Poster Boards
: 3. Meeting Handout
: 3. Meeting Handout cc w/encls: (See page 2)


cc w/encls:  (See page 2)
____________              X SUNSI REVIEW COMPLETE G FORM 665 ATTACHED OFFICE            RII:DRP          RII:DRP SIGNATURE        Via email        /RA/
NAME              EMorris          JWorosilo DATE                04/19/2013        4/22/2013 E-MAIL COPY?        YES    NO      YES      NO    YES    NO      YES    NO      YES    NO      YES    NO    YES    NO


____________ X SUNSI REVIEW COMPLETE G FORM 665 ATTACHED OFFICE RII:DRP RII:DRP      SIGNATURE Via email /RA/      NAME EMorris JWorosilo      DATE 04/19/2013 4/22/2013      E-MAIL COPY?    YES NO      YES NO      YES NO      YES NO      YES NO      YES NO      YES NO D. Madison 2 cc w/encls: C. Russ Dedrickson Fleet Support Supervisor  
D. Madison                               2 cc w/encls:
C. Russ Dedrickson                         Dennis R. Madison Fleet Support Supervisor                   Vice President Southern Nuclear Operating Company, Inc. Edwin I. Hatch Nuclear Plant Electronic Mail Distribution              Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution David R. Vineyard Plant Manager                              T. E. Tynan Edwin I. Hatch Nuclear Plant              Site Vice President Southern Nuclear Operating Company, Inc. Vogtle Electric Generating Plant Electronic Mail Distribution              Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution S. Kuczynski Chairman, President and CEO                C. R. Pierce Southern Nuclear Operating Company, Inc. Nuclear Licensing Director Electronic Mail Distribution              Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution Todd L. Youngblood Vice President                            B. D. McKinney, Jr.
Fleet Oversight                            Regulatory Response Manager Southern Nuclear Operating Company, Inc. Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution              Electronic Mail Distribution Leigh Perry                                D. W. Daughhetee SVP & General Counsel-Ops & SNC            Licensing Engineer Southern Nuclear Operating Company, Inc. Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution              Electronic Mail Distribution D. G. Bost                                T. D. Honeycutt Chief Nuclear Officer                      Regulatory Response Supervisor Southern Nuclear Operating Company, Inc. Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution              Electronic Mail Distribution Paula Marino                              Bradley J. Adams Vice President                            Vice President Engineering                                Fleet Operations Support Southern Nuclear Operating Company, Inc. Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution              Electronic Mail Distribution T. A. Lynch                                N. J. Stringfellow Vice President                            Licensing Manager Joseph M. Farley Nuclear Plant            Southern Nuclear Operating Company, Inc.
Southern Nuclear Operating Company, Inc. Electronic Mail Distribution Electronic Mail Distribution (cc w/encls contd - See page 3)


Southern Nuclear Operating Company, Inc.
D. Madison                              3 cc w/encls contd:                        Arthur H. Domby, Esq.
Electronic Mail Distribution  
L. P. Hill                                Troutman Sanders Licensing Supervisor                      Electronic Mail Distribution Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution              James C. Hardeman Environmental Radiation Program Manager L. L. Crumpton                            Environmental Protection Division Administrative Assistant, Sr.              Georgia Department of Natural Resources Southern Nuclear Operating Company, Inc. Electronic Mail Distribution Electronic Mail Distribution Chuck Mueller Steven B. Tipps                            Manager Hatch Principal Engineer - Licensing      Policy and Radiation Program Edwin I. Hatch Nuclear Plant              Georgia Department of Natural Resources Electronic Mail Distribution              Electronic Mail Distribution W. E. Duvall                              Cynthia A. Sanders Site Support Manager                      Radioactive Materials Program Manager Edwin I. Hatch Nuclear Plant              Environmental Protection Division Electronic Mail Distribution              Georgia Department of Natural Resources Electronic Mail Distribution Senior Resident Inspector U.S. Nuclear Regulatory Commission        Mr. Steven M. Jackson Edwin I. Hatch Nuclear Plant              Senior Engineer - Power Supply U.S. NRC                                  Municipal Electric Authority of Georgia 11030 Hatch Parkway N                      Electronic Mail Distribution Baxley, GA 31513 Reece McAlister Mr. Ken Rosanski                          Executive Secretary Resident Manager                          Georgia Public Service Commission Edwin I. Hatch Nuclear Plant              Electronic Mail Distribution Oglethorpe Power Corporation Electronic Mail Distribution              Chairman Appling County Commissioners Mark Williams                              County Courthouse Commissioner                              69 Tippins Street, Suite 201 Georgia Department of Natural Resources    Baxley, GA 31513 Electronic Mail Distribution Amy Whaley Jerry Ranalli                              Resident Manager Municipal Electric Authority of Georgia    Electronic Mail Distribution Power Electronic Mail Distribution Lee Foley Manager of Contracts Generation Oglethorpe Power Corporation Electronic Mail Distribution


David R. Vineyard Plant Manager Edwin I. Hatch Nuclear Plant
D. Madison                                4 Letter to Dennis R. Madison from Frank Ehrhardt dated April 22, 2013


Southern Nuclear Operating Company, Inc.
==SUBJECT:==
Electronic Mail Distribution
PUBLIC MEETING


S. Kuczynski Chairman, President and CEO
==SUMMARY==
 
- EDWIN I. HATCH NUCLEAR PLANT DOCKET NOS. 50-321 AND 50-366 Distribution w/encls:
Southern Nuclear Operating Company, Inc.
C. Evans, RII L. Douglas, RII OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMHatch Resource
Electronic Mail Distribution
 
Todd L. Youngblood Vice President
 
Fleet Oversight
 
Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution
 
Leigh Perry SVP & General Counsel-Ops & SNC
 
Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution
 
D. G. Bost Chief Nuclear Officer
 
Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution
 
Paula Marino Vice President Engineering
 
Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution
 
T. A. Lynch Vice President
 
Joseph M. Farley Nuclear Plant
 
Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution Dennis R. Madison Vice President Edwin I. Hatch Nuclear Plant
 
Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution  
 
T. E. Tynan Site Vice President Vogtle Electric Generating Plant
 
Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution C. R. Pierce Nuclear Licensing Director
 
Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution B. D. McKinney, Jr.
Regulatory Response Manager
 
Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution
 
D. W. Daughhetee Licensing Engineer
 
Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution
 
T. D. Honeycutt Regulatory Response Supervisor
 
Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution
 
Bradley J. Adams Vice President Fleet Operations Support
 
Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution
 
N. J. Stringfellow Licensing Manager
 
Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution
 
(cc w/encls cont'd - See page 3)
D. Madison  3 cc w/encls cont'd:
L. P. Hill Licensing Supervisor
 
Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution
 
L. L. Crumpton Administrative Assistant, Sr.
Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution
 
Steven B. Tipps Hatch Principal Engineer - Licensing Edwin I. Hatch Nuclear Plant Electronic Mail Distribution


W. E. Duvall Site Support Manager Edwin I. Hatch Nuclear Plant Electronic Mail Distribution
NRC Annual Assessment Summary Edwin I. Hatch Nuclear Plant Southern Nuclear operated the plant safely and in a manner that preserved the public health and safety and protected the environment.
Edwin I. Hatch Nuclear Plant was in the Licensee Response Column of the NRCs ROP Action Matrix for the last quarter of 2012.
Enclosure 2


Senior Resident Inspector U.S. Nuclear Regulatory Commission Edwin I. Hatch Nuclear Plant U.S. NRC 11030 Hatch Parkway N Baxley, GA  31513
2 NRC Inspection Activities Edwin I. Hatch Nuclear Plant for 2012 Two Resident Inspectors on Site Implemented baseline inspection program Inspected in-plant evolutions and activities Compiled and submitted quarterly inspection reports Two Major Team Inspections Component Design Bases Initial License Examination Enclosure 2


Mr. Ken Rosanski Resident Manager Edwin I. Hatch Nuclear Plant Oglethorpe Power Corporation Electronic Mail Distribution
3 NRC Plans for 2013 NRC plans baseline inspections at Edwin I.
Hatch Nuclear Plant for the remainder of 2013 Major Team Inspections Include:
Problem Identification and Resolution Initial License Examination Plant Modifications Inspection Emergency Preparedness Exercise Triennial Fire Protection Inspection License Renewal Phase 2 Enclosure 2


Mark Williams Commissioner
4 Reactor Oversight Process Strategic Performance Areas Safety Cornerstones Baseline Inspection                    Performance Indicator Results                                Results Significance                    Significance Significance Threshold                      Threshold Threshold Action Matrix Regulatory Response Enclosure 2


Georgia Department of Natural Resources Electronic Mail Distribution
5 Reactor Oversight Process Regulatory Framework PUBLIC HEALTH AND NRCs Overall                                            SAFETY AS A RESULT OF CIVILIAN Safety Mission                                    NUCLEAR REACTOR OPERATION Strategic Performance                      REACTOR            RADIATION                  PLANT SAFETY              SAFETY              SECURITY Areas INITIATING MITIGATING  BARRIER    EMERGENCY    PUBLIC    OCCUPATIONAL    PHYSICAL Cornerstones  EVENTS    SYSTEMS  INTEGRITY  PREPAREDNESS RADIATION    RADIATION    PROTECTION SAFETY        SAFETY Human Performance          Safety Conscious Work          Problem Identification Environment                  and Resolution Cross-Cutting Areas Enclosure 2


Jerry Ranalli Municipal Electric Authority of Georgia Power Electronic Mail Distribution
Edwin I. Hatch Nuclear Plant Annual Assessment Meeting 2012 Reactor Oversight Process Nuclear Regulatory Commission - Region II Enclosure 3
 
Lee Foley Manager of Contracts Generation Oglethorpe Power Corporation Electronic Mail Distribution
 
Arthur H. Domby, Esq.
Troutman Sanders Electronic Mail Distribution
 
James C. Hardeman Environmental Radiation Program Manager Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution
 
Chuck Mueller
 
Manager Policy and Radiation Program Georgia Department of Natural Resources Electronic Mail Distribution
 
Cynthia A. Sanders Radioactive Materials Program Manager Environmental Protection Division
 
Georgia Department of Natural Resources Electronic Mail Distribution
 
Mr. Steven M. Jackson Senior Engineer - Power  Supply Municipal Electric Authority of Georgia Electronic Mail Distribution
 
Reece McAlister Executive Secretary Georgia Public Service Commission Electronic Mail Distribution
 
Chairman Appling County Commissioners County Courthouse 69 Tippins Street, Suite 201 Baxley, GA  31513
 
Amy Whaley Resident Manager Electronic Mail Distribution
 
D. Madison  4 Letter to Dennis R. Madison from Frank Ehrhardt dated April 22, 2013
 
==SUBJECT:==
PUBLIC MEETING
 
==SUMMARY==
- EDWIN I. HATCH NUCLEAR PLANT DOCKET NOS. 50-321 AND 50-366 Distribution w/encls
: C. Evans, RII L. Douglas, RII  OE Mail  RIDSNRRDIRS PUBLIC RidsNrrPMHatch Resource


Enclosure 1
2 Enclosure 3


Enclosure 2 NRC Annual Assessment SummarySouthern Nuclear operated the plant safely and in a manner that preserved the public health and safety and protected the environment.Edwin I. Hatch Nuclear Plant was in the Licensee Response Column of the NRC's ROP Action Matrix for the last quarter of 2012.Edwin I. Hatch Nuclear Plant 2  Enclosure 2 NRC Inspection ActivitiesTwo Resident Inspectors on SiteImplemented baseline inspection programInspected in-plant evolutions and activitiesCompiled and submitted quarterly inspection reportsTwo Major Team InspectionsComponent Design BasesInitial License ExaminationEdwin I. Hatch Nuclear Plant for 2012
3 Significance Threshold Performance Indicators Green    Baseline Inspection White    Requires additional NRC oversight Yellow  Requires more NRC oversight Red      Requires most NRC oversight Inspection Findings Green    Very low safety issue White  Low to moderate safety issue Yellow  Substantial safety issue Red      High safety issue Enclosure 3


3  Enclosure 2 NRC Plans for 2013NRC plans baseline inspections at Edwin I. Hatch Nuclear Plant for the remainder of 2013 Major Team Inspections Include:Problem Identification and ResolutionInitial License ExaminationPlant Modifications InspectionEmergency Preparedness ExerciseTriennial Fire Protection InspectionLicense Renewal Phase 2 4  Enclosure 2 Reactor Oversight ProcessSafetyCornerstonesBaseline Inspection ResultsSignificance ThresholdAction MatrixSignificance ThresholdPerformance IndicatorResultsStrategicPerformance AreasSafetyCornerstonesBaseline Inspection ResultsSignificance ThresholdAction MatrixSignificance ThresholdPerformance IndicatorResultsRegulatory ResponseStrategicPerformance Areas 5  Enclosure 2 Reactor Oversight Process Regulatory Framework NRC's Overall Safety MissionPUBLIC HEALTH AND SAFETY AS A RESULT OF CIVILIAN NUCLEAR REACTOR OPERATIONREACTOR SAFETY Strategic Performance AreasRADIATION SAFETYPLANT SECURITYCornerstonesINITIATING EVENTSMITIGATING SYSTEMSBARRIER INTEGRITYEMERGENCY PREPAREDNESSPUBLIC RADIATION SAFETYOCCUPATIONAL RADIATION SAFETYPHYSICAL PROTECTIONHuman PerformanceSafety Conscious Work EnvironmentProblem Identification and ResolutionCross-Cutting Areas Enclosure 3 Edwin I. Hatch Nuclear Plant Annual Assessment Meeting2012 Reactor Oversight ProcessNuclear Regulatory Commission -Region II
4 NRC Annual Assessment Summary Edwin I. Hatch Nuclear Plant Southern Nuclear operated the plant safely and in a manner that preserved the public health and safety and protected the environment.
Edwin I. Hatch Nuclear Plant was in the Licensee Response Column of the NRCs ROP Action Matrix for the last quarter of 2012.
Enclosure 3


2  Enclosure 3 3  Enclosure 3 Significance ThresholdGreenBaseline InspectionWhiteRequires additional NRC oversightYellowRequires more NRC oversightRedRequires most NRC oversightPerformance Indicators Inspection FindingsGreenVery low safety issueWhiteLow to moderate safety issueYellowSubstantial safety issueRedHigh safety issue 4  Enclosure 3 NRC Annual Assessment SummarySouthern Nuclear operated the plant safely and in a manner that preserved the public health and safety and protected the environment.Edwin I. Hatch Nuclear Plant was in the Licensee Response Column of the NRC's ROP Action Matrix for the last quarter of 2012.Edwin I. Hatch Nuclear Plant
5 NRC Inspection Activities Edwin I. Hatch Nuclear Plant for 2012 Two Resident Inspectors on Site Implemented baseline inspection program Inspected in-plant evolutions and activities Compiled and submitted quarterly inspection reports Two Major Team Inspections Component Design Bases Initial License Examination Enclosure 3


5  Enclosure 3 NRC Inspection ActivitiesTwo Resident Inspectors on SiteImplemented baseline inspection programInspected in-plant evolutions and activitiesCompiled and submitted quarterly inspection reportsTwo Major Team InspectionsComponent Design BasesInitial License ExaminationEdwin I. Hatch Nuclear Plant for 2012
6 Edwin I. Hatch Nuclear Plant Performance Indicators and Findings January 1 through December 31, 2012 All Green Performance Indicators All Green / Severity Level IV inspection findings Enclosure 3


6  Enclosure 3 Edwin I. Hatch Nuclear Plant Performance Indicators and FindingsAll Green Performance IndicatorsAll Green / Severity Level IV inspection findingsJanuary 1 through December 31, 2012
7 NRC Plans for 2013 NRC plans baseline inspections at Edwin I.
Hatch Nuclear Plant for the remainder of 2013 Additional Major Inspections Include:
Problem Identification and Resolution Initial License Examination Plant Modifications Inspection Emergency Preparedness Exercise Triennial Fire Protection Inspection License Renewal Phase 2 Enclosure 3


Enclosure 3 NRC Plans for 2013NRC plans baseline inspections at Edwin I. Hatch Nuclear Plant for the remainder of 2013Additional Major Inspections Include:Problem Identification and ResolutionInitial License ExaminationPlant Modifications InspectionEmergency Preparedness ExerciseTriennial Fire Protection InspectionLicense Renewal Phase 2
8 Enclosure 3


8  Enclosure 3 9 Enclosure 3}}
9 Enclosure 3}}

Revision as of 19:26, 4 November 2019

04/17/2013 Summary of Public Meeting to Discuss the Annual Assessment of Edwin I. Hatch Nuclear Plant with the Public for the Period of January 1, 2012, - December 31, 2012
ML13112A255
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 04/22/2013
From: Frank Ehrhardt
NRC/RGN-II/DRP/RPB2
To: Madison D
Southern Nuclear Operating Co
References
Download: ML13112A255 (20)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 April 22, 2013 Mr. D. R. Madison Vice President Southern Nuclear Operating Company, Inc.

Edwin I. Hatch Nuclear Plant 11028 Hatch Parkway North Baxley, GA 31513

SUBJECT:

PUBLIC MEETING

SUMMARY

- EDWIN I. HATCH NUCLEAR PLANT DOCKET NOS. 50-321 AND 50-366

Dear Mr. Madison:

This refers to the meeting conducted on April 17, 2013, in Vidalia, Georgia. The purpose of the meeting/open house session was to provide opportunities to discuss the annual assessment of Edwin I. Hatch Nuclear Plant with the public for the period of January 1, 2012, - December 31, 2012. Enclosed are a list of attendees, copies of the poster boards displayed at the meeting, and the meeting handout.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS).

ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Should you have any questions concerning this meeting, please contact me at (404) 997-4611.

Sincerely,

/RA By Jannette Worosilo For/

Frank Ehrhardt, Chief Reactor Projects Branch 2 Division of Reactor Projects Docket Nos.: 50-321 and 50-366 License Nos.: DPR-57 and NPF-5

Enclosures:

1. List of Attendees
2. Poster Boards
3. Meeting Handout cc w/encls: (See page 2)

____________ X SUNSI REVIEW COMPLETE G FORM 665 ATTACHED OFFICE RII:DRP RII:DRP SIGNATURE Via email /RA/

NAME EMorris JWorosilo DATE 04/19/2013 4/22/2013 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO

D. Madison 2 cc w/encls:

C. Russ Dedrickson Dennis R. Madison Fleet Support Supervisor Vice President Southern Nuclear Operating Company, Inc. Edwin I. Hatch Nuclear Plant Electronic Mail Distribution Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution David R. Vineyard Plant Manager T. E. Tynan Edwin I. Hatch Nuclear Plant Site Vice President Southern Nuclear Operating Company, Inc. Vogtle Electric Generating Plant Electronic Mail Distribution Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution S. Kuczynski Chairman, President and CEO C. R. Pierce Southern Nuclear Operating Company, Inc. Nuclear Licensing Director Electronic Mail Distribution Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution Todd L. Youngblood Vice President B. D. McKinney, Jr.

Fleet Oversight Regulatory Response Manager Southern Nuclear Operating Company, Inc. Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution Electronic Mail Distribution Leigh Perry D. W. Daughhetee SVP & General Counsel-Ops & SNC Licensing Engineer Southern Nuclear Operating Company, Inc. Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution Electronic Mail Distribution D. G. Bost T. D. Honeycutt Chief Nuclear Officer Regulatory Response Supervisor Southern Nuclear Operating Company, Inc. Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution Electronic Mail Distribution Paula Marino Bradley J. Adams Vice President Vice President Engineering Fleet Operations Support Southern Nuclear Operating Company, Inc. Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution Electronic Mail Distribution T. A. Lynch N. J. Stringfellow Vice President Licensing Manager Joseph M. Farley Nuclear Plant Southern Nuclear Operating Company, Inc.

Southern Nuclear Operating Company, Inc. Electronic Mail Distribution Electronic Mail Distribution (cc w/encls contd - See page 3)

D. Madison 3 cc w/encls contd: Arthur H. Domby, Esq.

L. P. Hill Troutman Sanders Licensing Supervisor Electronic Mail Distribution Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution James C. Hardeman Environmental Radiation Program Manager L. L. Crumpton Environmental Protection Division Administrative Assistant, Sr. Georgia Department of Natural Resources Southern Nuclear Operating Company, Inc. Electronic Mail Distribution Electronic Mail Distribution Chuck Mueller Steven B. Tipps Manager Hatch Principal Engineer - Licensing Policy and Radiation Program Edwin I. Hatch Nuclear Plant Georgia Department of Natural Resources Electronic Mail Distribution Electronic Mail Distribution W. E. Duvall Cynthia A. Sanders Site Support Manager Radioactive Materials Program Manager Edwin I. Hatch Nuclear Plant Environmental Protection Division Electronic Mail Distribution Georgia Department of Natural Resources Electronic Mail Distribution Senior Resident Inspector U.S. Nuclear Regulatory Commission Mr. Steven M. Jackson Edwin I. Hatch Nuclear Plant Senior Engineer - Power Supply U.S. NRC Municipal Electric Authority of Georgia 11030 Hatch Parkway N Electronic Mail Distribution Baxley, GA 31513 Reece McAlister Mr. Ken Rosanski Executive Secretary Resident Manager Georgia Public Service Commission Edwin I. Hatch Nuclear Plant Electronic Mail Distribution Oglethorpe Power Corporation Electronic Mail Distribution Chairman Appling County Commissioners Mark Williams County Courthouse Commissioner 69 Tippins Street, Suite 201 Georgia Department of Natural Resources Baxley, GA 31513 Electronic Mail Distribution Amy Whaley Jerry Ranalli Resident Manager Municipal Electric Authority of Georgia Electronic Mail Distribution Power Electronic Mail Distribution Lee Foley Manager of Contracts Generation Oglethorpe Power Corporation Electronic Mail Distribution

D. Madison 4 Letter to Dennis R. Madison from Frank Ehrhardt dated April 22, 2013

SUBJECT:

PUBLIC MEETING

SUMMARY

- EDWIN I. HATCH NUCLEAR PLANT DOCKET NOS. 50-321 AND 50-366 Distribution w/encls:

C. Evans, RII L. Douglas, RII OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMHatch Resource

NRC Annual Assessment Summary Edwin I. Hatch Nuclear Plant Southern Nuclear operated the plant safely and in a manner that preserved the public health and safety and protected the environment.

Edwin I. Hatch Nuclear Plant was in the Licensee Response Column of the NRCs ROP Action Matrix for the last quarter of 2012.

Enclosure 2

2 NRC Inspection Activities Edwin I. Hatch Nuclear Plant for 2012 Two Resident Inspectors on Site Implemented baseline inspection program Inspected in-plant evolutions and activities Compiled and submitted quarterly inspection reports Two Major Team Inspections Component Design Bases Initial License Examination Enclosure 2

3 NRC Plans for 2013 NRC plans baseline inspections at Edwin I.

Hatch Nuclear Plant for the remainder of 2013 Major Team Inspections Include:

Problem Identification and Resolution Initial License Examination Plant Modifications Inspection Emergency Preparedness Exercise Triennial Fire Protection Inspection License Renewal Phase 2 Enclosure 2

4 Reactor Oversight Process Strategic Performance Areas Safety Cornerstones Baseline Inspection Performance Indicator Results Results Significance Significance Significance Threshold Threshold Threshold Action Matrix Regulatory Response Enclosure 2

5 Reactor Oversight Process Regulatory Framework PUBLIC HEALTH AND NRCs Overall SAFETY AS A RESULT OF CIVILIAN Safety Mission NUCLEAR REACTOR OPERATION Strategic Performance REACTOR RADIATION PLANT SAFETY SAFETY SECURITY Areas INITIATING MITIGATING BARRIER EMERGENCY PUBLIC OCCUPATIONAL PHYSICAL Cornerstones EVENTS SYSTEMS INTEGRITY PREPAREDNESS RADIATION RADIATION PROTECTION SAFETY SAFETY Human Performance Safety Conscious Work Problem Identification Environment and Resolution Cross-Cutting Areas Enclosure 2

Edwin I. Hatch Nuclear Plant Annual Assessment Meeting 2012 Reactor Oversight Process Nuclear Regulatory Commission - Region II Enclosure 3

2 Enclosure 3

3 Significance Threshold Performance Indicators Green Baseline Inspection White Requires additional NRC oversight Yellow Requires more NRC oversight Red Requires most NRC oversight Inspection Findings Green Very low safety issue White Low to moderate safety issue Yellow Substantial safety issue Red High safety issue Enclosure 3

4 NRC Annual Assessment Summary Edwin I. Hatch Nuclear Plant Southern Nuclear operated the plant safely and in a manner that preserved the public health and safety and protected the environment.

Edwin I. Hatch Nuclear Plant was in the Licensee Response Column of the NRCs ROP Action Matrix for the last quarter of 2012.

Enclosure 3

5 NRC Inspection Activities Edwin I. Hatch Nuclear Plant for 2012 Two Resident Inspectors on Site Implemented baseline inspection program Inspected in-plant evolutions and activities Compiled and submitted quarterly inspection reports Two Major Team Inspections Component Design Bases Initial License Examination Enclosure 3

6 Edwin I. Hatch Nuclear Plant Performance Indicators and Findings January 1 through December 31, 2012 All Green Performance Indicators All Green / Severity Level IV inspection findings Enclosure 3

7 NRC Plans for 2013 NRC plans baseline inspections at Edwin I.

Hatch Nuclear Plant for the remainder of 2013 Additional Major Inspections Include:

Problem Identification and Resolution Initial License Examination Plant Modifications Inspection Emergency Preparedness Exercise Triennial Fire Protection Inspection License Renewal Phase 2 Enclosure 3