Letter Sequence Meeting |
---|
|
|
MONTHYEARNL-23-0555, Request for Exemption from Physical Barrier Requirement2023-07-0707 July 2023 Request for Exemption from Physical Barrier Requirement Project stage: Request ML23223A0142023-08-10010 August 2023 NRR E-mail Capture - Acceptance Review - SNC Fleet Exemption to 10 CFR 73.2, Physical Barriers Project stage: Acceptance Review ML23311A1302023-11-17017 November 2023 Summary of Nov. 6, 2023, - Closed Meeting Held with Southern Nuclear Operating Company, Inc., Regarding Physical Barriers Exemptions for Hatch Units 1 & 2, Farley Units 1 & 2 and Vogtle Units 1, 2, 3 & 4 (EPID L-2023-LLE-0018 & L-2023-LLE-0 Project stage: Meeting ML23345A1312024-01-0303 January 2024 Withholding Letter - SNC Fleet - Physical Barriers Exemption (L-2023-LLE-0018 and L-2023-LLE-0021) Project stage: Other ML23341A2042024-01-12012 January 2024 Request for Additional Information Exemption Requests for Physical Barriers (EPID L-2023-LLE-0018 & L-2023-LLE-0021) Project stage: RAI 2023-08-10
[Table View] |
Summary of Nov. 6, 2023, - Closed Meeting Held with Southern Nuclear Operating Company, Inc., Regarding Physical Barriers Exemptions for Hatch Units 1 & 2, Farley Units 1 & 2 and Vogtle Units 1, 2, 3 & 4 (EPID L-2023-LLE-0018 & L-2023-LLE-0ML23311A130 |
Person / Time |
---|
Site: |
Hatch, Vogtle, Farley |
---|
Issue date: |
11/17/2023 |
---|
From: |
John Lamb Plant Licensing Branch II |
---|
To: |
Southern Nuclear Operating Co |
---|
Lamb J |
Shared Package |
---|
ML23311A149 |
List: |
---|
References |
---|
EPID L-2023-LLE-0018, EPID L-2023-LLE-0021 |
Download: ML23311A130 (6) |
|
|
---|
Category:Meeting Summary
MONTHYEARML24025A1372024-01-31031 January 2024 Summary of Observation Pre-Submittal Meeting Held with Snc., Regarding a Proposed Alternative Request - Explosively Actuated Valves for Vogtle Electric Generating Plant, Units 3 and 4 ML24012A1592024-01-30030 January 2024 Summary of January 8, 2024, Meeting Held with Southern Nuclear Operating Company, Inc., to Discuss a RAI License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Head Bolts ML24019A1932024-01-30030 January 2024 Summary of January 8, 2024, Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company Regarding a Proposed LAR for Vogtle Electric Generating Plant, Units 1, 2, 3, & 4; Hatch, Units 1 & 2; Farley, Units 1 & 2 ML23356A0282023-12-27027 December 2023 December 11, 2023, Pre-Application Meeting with SNC Regarding a Proposed Fleet LAR to Revise TS 5.3.1 to Relocate Training Qualification Requirements from TS to Their Qatr/Ndqam ML23338A2592023-12-0808 December 2023 Summary of Observation Public Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a License Amendment Request for the Reactor Pressure Vessel Head Closure Bolts for Hatch, Units 1 & 2 (EPID No. L-2022-LLA- 0120) ML23311A1302023-11-17017 November 2023 Summary of Nov. 6, 2023, - Closed Meeting Held with Southern Nuclear Operating Company, Inc., Regarding Physical Barriers Exemptions for Hatch Units 1 & 2, Farley Units 1 & 2 and Vogtle Units 1, 2, 3 & 4 (EPID L-2023-LLE-0018 & L-2023-LLE-0 ML23313A0952023-11-16016 November 2023 Summary of November 7, 2023, Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request for Vogtle Electric Generating Plant, Units 1 and 2 ML23303A2032023-11-0101 November 2023 October 24, 2023, Summary of Comment Gathering Public Meeting on Lessons Learned from the ITAAC Hearing Process for Vogtle Units 3 and 4 ML23275A0882023-10-12012 October 2023 Summary of Meeting with Southern Nuclear Operating Company ML23272A1822023-10-11011 October 2023 Summary of September 28, 2023, Observation Pre Submittal Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request for Vogtle Electric Generating Plant, Units 3 and 4 ML23244A0312023-09-18018 September 2023 MTS - Meeting Summary - Pre-Submittal Meeting on August 02, 2023 - RICT 45-day Extension for TS 3.7.1 & 3.7.2 ML23230A0212023-08-30030 August 2023 LAR-22-002 Technical Specification 3.8.3 Summary of 08-17-23 Public Meeting ML23187A5742023-08-22022 August 2023 Summary of June 29, 2023, Meeting with Southern Nuclear Operating Company ML23146A1542023-06-0505 June 2023 Summary of May 25, 2023, Meeting with Southern Nuclear Operating Company ML23146A1672023-05-31031 May 2023 Public Meeting Summary2022 Annual Assessment Meeting for Joseph M. Farley, Units 1 and 2 Docket No. 50?348, and 50?364 Meeting Number 20230610 ML23136B2942023-05-19019 May 2023 Summary of May 02, 2023, Observation Public Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a LAR for the Reactor Pressure Vessel Head Closure Bolts for Edwin I. Hatch Nuclear Plant, Units 1 and 2 ML23132A0412023-05-18018 May 2023 Summary of May 11, 2023, Meeting with Southern Nuclear Operating Company ML23121A1692023-05-12012 May 2023 Summary of Meeting with Southern Nuclear Operating Company Vogtle LAR-23-006 U/3&4 More Restrictive Action for TS 3.1.9 Cvs Isolation Valves ML23115A3282023-05-10010 May 2023 Summary of Public Meeting with Southern Nuclear Operating Company to Have a Pre-Submittal Discussion of Draft License Amendment Request (LAR) for Vogtle Electric Generating Plant (VEGP) Unit 3 ML23115A0662023-05-0101 May 2023 Summary of Public Meeting with Southern Nuclear Operating Company to Have Presubmittal Meeting for Vogtle Electric Generating Plant, Unit 4 IR 05000424/20040252023-04-28028 April 2023 Public Meeting Summary - Vogtle Electric Generating Plant, Units 1, 2, 3, & 4 Docket No. 5000424, 5000425, 5200025, 5200026, Meeting Number 20230375 ML23094A1092023-04-14014 April 2023 Summary of Conference Call Held with SNC, Regarding Regulatory Issue Summary 2000-11, Supplement 2, NRC Emergency Telecommunications System, for Joseph M. Farley Nuclear Plant, Units 1 and 2, and SNC Emergency Operations Facility ML23088A3882023-04-0303 April 2023 Summary of March 28, 2023, Observation Public Meeting Held with SNC, Regarding a License Amendment Request Regarding the Reactor Pressure Vessel Head Closure Bolts for Edwin I. Hatch Nuclear Plan, Units 1 and 2 ML23090A1422023-04-0303 April 2023 Summary of Conference Call Regarding the Spring 2022 Steam Generator Tube Inspections ML23088A2362023-03-28028 March 2023 SNC Presentation - Public Meeting - 03-28-2023 - Page from ML22231B055 ML23065A0732023-03-17017 March 2023 March 2, 2023, Summary of Meeting with Southern Nuclear Operating Company - Vogtle Electric Generating Plant, Unit 4 ML23055A0902023-03-14014 March 2023 February 16, 2023, Summary of Meeting with Southern Nuclear Operating Company ML23048A0682023-03-0101 March 2023 Summary of February 13, 2023, Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company, Inc. Regarding a Proposed License Amendment Request for Vogtle Electric Generating Plant, Units 1 and 2 ML23037A0032023-02-0606 February 2023 Summary of February 2, 2023, Public Meeting with Southern Nuclear Operating Company ML23012A0512023-01-17017 January 2023 January 11, 2023, Summary of Public Meeting with Southern Nuclear Operating Company (SNC) Regarding Vogtle Emergency Technical Specification Amendment ML22349A2142023-01-0303 January 2023 Summary of December 8, 2022, Public Meeting with Southern Nuclear Operating Company ML22336A0812022-12-0505 December 2022 Summary of December 1, 2022, Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request for Vogtle Electric Generating Plant, Units 1 and 2 ML22335A4922022-12-0202 December 2022 Summary of Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request for Vogtle Electric Generating Plant, Units 1 and 2 ML22319A0132022-11-30030 November 2022 Summary of a Public Meeting with Southern Nuclear Operating Company on November 10, 2022 ML22322A1672022-11-28028 November 2022 Summary of 11/15/2022 Public Meeting on Lessons Learned ML22271A0182022-10-0404 October 2022 Summary of Public Meeting with SNC on Lessons Learned Final ML22257A2362022-09-19019 September 2022 Summary of September 13, 2022, Partially Open and Partially Closed Pre-Submittal Meeting Held with SNC, Regarding a Proposed OLM License Amendment Request for Vogtle Electric Generating Plant, Units 1 and 2 ML22243A0302022-09-0909 September 2022 Summary of a Public Meeting with Southern Nuclear Operating Company on August 25, 2022 ML22243A1912022-09-0707 September 2022 Public Pre-Submittal Meeting on August 1, 2022 - Revise TS Table 1.1-1 Modes to Relax RPV Head Closure Studs ML22200A0432022-07-22022 July 2022 Summary of June 22, 2022, Pre-Submittal Meeting W/Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request to Re-Write TS 3.7.2, Plant Service Water and Ultimate Heat Sink for Edwin I. Hatch Nuclear ML22172A2142022-07-11011 July 2022 June 16, 2022, Summary of Public Meeting with Southern Nuclear Operating Company, Inc., a Proposed License Amendment Request to Modify the Technical Specifications Regarding Pressurizer Safety Valve Setpoints at the Joseph M. Farley Nuclear ML22145A6052022-06-0202 June 2022 Summary of May 24, 2022, Public Meeting with SNC, Regarding a Proposed Alternative Request for Performance-Based Leakage Test Frequencies for the Refueling Water Tank Suction Check Valves for Vogtle, Units 1 & 2 ML22145A4492022-05-27027 May 2022 Summary of May 23, 2022, Public Meeting with SNC, Regarding a Proposed License Amendment Request to Change Technical Specification 3.8.1 and Implement TSTF-163 for Vogtle Electric Generating Plant, Units 1 and 2 ML22131A3422022-05-18018 May 2022 Summary of Public Meeting with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Requests to Implement Alternate Source Term, TSTF-51, TSTF-471, and TSTF-490 for Vogtle, Units 1 & 2 (EPID No. L-2022-LRM-0033 ML22132A0102022-05-17017 May 2022 Meeting of Public Meeting with Southern Nuclear Operating Company, Inc., Regarding Proposed Accident Tolerant Fuel License Amendment Request and Exceptions for Vogtle Electric Generating Plant, Units 1 and 2 ML22123A0652022-05-0202 May 2022 Public Meeting Summary Vogtle Electric Generating Plant, Units 1, 2, 3, & 4 Docket No. 50-424, 50-425, 52-025, 52-026, Meeting Number 20220330 ML22098A1292022-04-26026 April 2022 Summary of March 31, 2022 Public Meeting with Southern Nuclear Operating Company ML22108A1382022-04-18018 April 2022 Annual Assessment Public Meeting Summary 2024-01-31
[Table view] |
Text
November 17, 2023 LICENSEE: Southern Nuclear Operating Company, Inc.
FACILITY: Edwin I. Hatch Nuclear Plant, Units 1 and 2 Joseph M. Farley Nuclear Plant, Units 1 and 2 Vogtle Electric Generating Plant, Units 1, 2, 3, and 4
SUBJECT:
SUMMARY
OF NOVEMBER 6, 2023, CLOSED MEETING HELD WITH SOUTHERN NUCLEAR OPERATING COMPANY, INC., REGARDING PHYSICAL BARRIER EXEMPTIONS FOR EDWIN I. HATCH NUCLEAR PLANT, UNITS 1 AND 2, JOSEPH M. FARLEY NUCLEAR PLANTS, UNITS 1 AND 2, AND VOGTLE ELECTRIC GENERATING PLANT, UNITS 1, 2, 3, AND 4 (EPID NO. L-2023-LLE-0018 AND L-2023-LLE-0021)
By letter dated July 7, 2023 (Agencywide Documents and Access Management System (ADAMS) Accession No. ML23188A163), Southern Nuclear Operating Company, Inc. (SNC, the licensee) submitted exemption requests in accordance with Title 10 of the Code of Federal Regulations (10 CFR), Section 73.5, Specific exemptions, to the angled bracket requirement in paragraph (1) of the physical barrier definition in 10 CFR 73.2, Definitions, for specific locations along the protected area perimeter fencing at Edwin I. Hatch Nuclear Plant (Hatch),
Units 1 and 2; Joseph M. Farley Nuclear Plant (Farley), Units 1 and 2; and Vogtle Electric Generating Plant (Vogtle), Units 1, 2, 3, and 4.
On November 6, 2023, the U.S. Nuclear Regulatory Commission (NRC) staff held a closed meeting with representatives from SNC. The purpose of the meeting was to discuss security-related information regarding the physical barrier exemption requests for Hatch, Farley, and Vogtle. A list of attendees is provided in the Enclosure.
The NRC staff opened the meeting with introductory remarks and a roll call of the attendees.
Discussion during the meeting followed the agenda contained in the notice that the NRC staff posted on the NRCs public website on October 25, 2023 (ML23298A054). The NRC staff asked if SNC considered requesting an alternative measure for its vertical brackets in lieu of exemptions, since SNC asserted in its submittal that the use of vertical brackets at its sites provides an equivalent level of protection as the angled brackets required by paragraph (1) of the physical barrier definition in 10 CFR 73.2. SNC stated that its submittal followed the FirstEnergy Nuclear Operating Company exemptions dated September 6, 2018 (ML17200D139), and SNC indicated it would consider whether it wants to pursue a different licensing approach.
The NRC staff informed SNC that if it decides to move forward with the submitted request, and the NRC staff determines the exemptions are justified, the NRC will issue the exemptions on a site-specific basis rather than to the SNC fleet as the licensee requested. To complete its review
of the SNCs exemption request, the NRC staff informed the licensee that the following additional information is needed:
(1) A description or comparison of the types of protected area perimeter fencing used at Farley, Hatch, and Vogtle in sufficient detail to demonstrate which portions of that fencing meet each fence attribute required by paragraph (1) of the definition of physical barrier in 10 CFR 73.2; (2) The time it takes for an individual to climb or otherwise traverse over the licensees alternative fence configuration that uses vertical brackets; and (3) A justification for each alternative fence location that explains why SNC cannot meet the NRCs fence requirement in paragraph (1) of the physical barrier definition.
The NRC staff informed SNC that if it decides to pursue an alternative measure, the NRC staff would still need the additional information listed in items (1) and (2) above; however, SNC would not need to provide the information in item (3) since SNC would be asserting that it meets the NRCs physical barrier requirement.
The NRC staff acknowledged that SNC requested that the NRC staff withhold from the public the Figures Attachment to its submittal dated July 7, 2023. The NRC staff explained that it reviewed the information in the Figures Attachment and noted that the information appears to not meet the withholding justifications in 10 CFR 2.390(a)(1)-(9) or the criteria and guidance in NRCs DG-SGI-1, Designation Guide of Safeguards Information, dated September 30, 2005 (ML062780084, not publicly available). The NRC staff requested that SNC provide specific justification to support its request to withhold the drawings in the Figures Attachment.
The NRC staff made no regulatory decisions during the meeting. The meeting adjourned at 1:43 pm Eastern Standard Time. Public meeting feedback forms were available, but no comments were received.
Please direct any inquiries to me at John.Lamb@nrc.gov or 301-415-3100.
/RA John G. Lamb, Senior Project Manager Plant Licensing Branch, II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-321, 50-366, 50-348, 50-366, 50-424, 50-425,52-025, and 52-026
Enclosure:
List of Attendees cc w/encls: Distribution via Listserv
LIST OF ATTENDEES NOVEMBER 6, 2023, CLOSED MEETING WITH SOUTHERN NUCLEAR COMPANY REGARDING PHYSICAL BARRIER EXEMPTIONS EDWIN I. HATCH NUCLEAR PLANT, UNITS 1 AND 2 JOSEPH M. FARLEY NUCLEAR PLANT, UNITS 1 AND 2 VOGTLE ELECTRIC GENERATING PLANT, UNITS 1, 2, 3, AND 4 ATTENDEE REPRESENTING Tony Bowers U.S. Nuclear Regulatory Commission (NRC)
Lou Cubellis NRC Steven Sarver NRC Mike Markley NRC John G. Lamb NRC Andrea Johnson NRC Ed Miller NRC Zach Turner NRC Dawnmathews Kalathiveettil NRC Jonathan Brown NRC Jeff Bream NRC Randy Patterson NRC Ryan Joyce Southern Nuclear Operating Company (SNC)
Jeanne Johnston SNC Ryan Henderson SNC Ken Lowery SNC Wes Sparkman SNC Dane Dienethal SNC Guye Akins SNC Gerald Durham SNC Steve Shipman SNC
PKG ML23311A149 Meeting Notice ML23298A054 Meeting Summary ML23311A130 NRC-001 OFFICE DORL/LPL2-1/PM DORL/LPL2-1/LA DPCP/RSB/BC DORL/LPL2-1/BC DORL/LPL2-1/PM NAME JLamb KGoldstein ABowers MMarkley JLamb DATE 11/06/2023 11/07/2023 11/15/2023 11/17/2023 11/17/2023