MONTHYEARML20350B7092020-12-15015 December 2020 Pre-Submittal Meeting - Hatch Proposed National Fire Protection Association (NFPA)-805 Supplemental License Amendment Request Project stage: Meeting ML21021A2462021-01-21021 January 2021 Slides - SNC Slides - Pre-Submittal Meeting on January 26, 2021 - Hatch NFPA-805 LAR Project stage: Request ML21028A0532021-02-0303 February 2021 Summary of Public Meeting with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request to Supplement National Fire Protection Association (NFPA)-805, Performance-Based Standard for Fire Protection for Project stage: Meeting 2021-01-21
[Table View] |
Similar Documents at Hatch |
---|
Category:Slides and Viewgraphs
MONTHYEARML24313A1052024-11-13013 November 2024 November 13, 2024, Hatch Pre-Submittal Public Meeting Slides (Southern Co.) ML24295A1842024-10-16016 October 2024 SNC Slides - Hatch Public Pre-Submittal Meeting on Oct 30, 2024 - Change EDG SRs 3.8.1.2 & 3.8.1.5 Load Bands ML24278A0012024-09-19019 September 2024 SLR Environmental Pre-Application Meeting - Southern Nuclear Corporation Presentation Slides ML24263A0822024-09-19019 September 2024 SLR Pre-Application Meeting - NRC Presentation Slides ML24123A0502024-05-0202 May 2024 2023 Annual Assessment Public Meeting Summary Meeting Number 20240479 ML23361A0812024-01-0808 January 2024 SNC Slides - Pre-Submittal Public Meeting on January 8, 2024 Related to Fleet QATR ML23361A1092024-01-0808 January 2024 SNC Slides for Public Meeting on 1-8-24 to Discuss Hatch LAR - Revise TS Table 1.1-1 (Modes) to Relax Required No. of Fully Tensioned RPV Head Closure Studs ML23206A0412023-08-0202 August 2023 SNC Slides - Public Pre-Submittal Meeting on Aug 02, 2023 - Request for 45-Day Limited Extension of Risk Informed Completion Time (RICT) Program Backstop for TS 3.7.1 & 3.7.2 ML23088A2362023-03-28028 March 2023 SNC Presentation - Public Meeting - 03-28-2023 - Page from ML22231B055 ML23079A2362023-03-20020 March 2023 Annual Assessment Meeting Presentation Slides ML22209A1872022-07-28028 July 2022 Pre-Submittal Meeting on August 1, 2022 Re Plant Hatch LAR: Relaxation of Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs (EPID L-2022-LRM-0052) (Slides) ML22167A1402022-06-22022 June 2022 Pre-Submittal Public Meeting Slides for Rewrite TS-3.7.2 License Amendment ML22080A0192022-03-18018 March 2022 Annual Assessment Meeting Presentation ML21271A2022021-10-0505 October 2021 Pre-Submittal Meeting on October 5, 2021 - Hatch NFPA 805 Supplement LAR (SNC Slides) ML21225A0312021-08-31031 August 2021 Pre-Submittal Meeting - Request to Eliminate the Requirement for Automatic Main Steam Isolation on High Turbine Building Area Temperature ML21222A0342021-08-16016 August 2021 SNC Slides - Hatch TSTF-505 LAR - Pre-Submittal Meeting - 08-16-2021 ML21083A2872021-03-24024 March 2021 Pre-Submittal Meeting - Quality Assurance Topical Report Revision to Allow Application of Remote Assessment Techniques During Exigent Conditions ML21021A2462021-01-21021 January 2021 Slides - SNC Slides - Pre-Submittal Meeting on January 26, 2021 - Hatch NFPA-805 LAR ML20318A1032020-11-12012 November 2020 SNC ERO Staffing LAR RAI Responses ML20156A0012020-06-0404 June 2020 Slides - SNC Slides - Pre-Submittal Meeting on June 10, 2020 - Hatch EDG AOT Extension ML20101K6582020-04-10010 April 2020 Annual Assessment ML19123A3542019-05-0202 May 2019 Public Meeting Summary - Hatch Nuclear Plant, Docket Nos. 50-321 and 50-366 ML19025A0242019-01-25025 January 2019 SNC License Amendment Request for Proposed Changes to Emergency Response Organization Staffing and Augmentation ML18124A0052018-05-0404 May 2018 Summary of Public Meeting - Hatch Nuclear Plant Docket Nos. 50-321, 50-366 ML18066A0302018-03-0101 March 2018 Slides for March 1, 2018 Public Meeting ML17324A3462017-11-15015 November 2017 Meeting Slides for 11/15/2017, Public Meeting Between NRC and SNC Regarding Hatch License Amendment Request - Application of TSTF-423 to Drywell Spray Function Technical Specification End State ML16174A0272016-06-21021 June 2016 Revised NRC-SNC Hatch NFPA 805 Extension 06212016 ML16169A0612016-06-20020 June 2016 SNC Slides for 6-21-16 Public Meeting on Hatch NFPA 805 Extension ML16169A0602016-06-17017 June 2016 SNC Draft Letter to NRC Regarding Hatch NFPA 805 Extension ML15191A4872015-07-13013 July 2015 Unit 2: Plant Service Water Piping Replacement Using High Density Polyethylene (Hdpe) Piping Nrc/Snc Meeting July 13, 2015 ML15106A2042015-04-22022 April 2015 April 22, 2015, Meeting with Southern Nuclear Company, Slide Presentation ML14177A0862014-06-26026 June 2014 NRC Presentation Slides for Public Meeting with Southern on Seismic Reevaluation (GMRS) ML14176B2392014-06-26026 June 2014 Southern Nuclear Operating Company Seismic Reevaluation - GMRS NTTF 2.1 Presentation Slides ML13112A2552013-04-22022 April 2013 Summary of Public Meeting to Discuss the Annual Assessment of Edwin I. Hatch Nuclear Plant with the Public for the Period of January 1, 2012, - December 31, 2012 ML12115A2572012-04-24024 April 2012 Summary of with Southern Nuclear Operating Co., Inc., to Discuss the Annual Assessment of Edwin I. Hatch for 2011 ML1111900612011-04-28028 April 2011 Summary of Public Meeting with Southern Nuclear Operating Company, Inc., to Discuss the Nrc'S Reactor Oversight Process and the Nrc'S Annual Assessment of Plant Safety Performance at Hatch for the Period of 01/01/210 - 12/31/2010 ML1011304442010-04-23023 April 2010 Summary of Public Meeting to Discuss the Annual Assessment of Edwin I. Hatch for the Period of January 1, 2009 Through December 31, 2009 ML1020105352009-10-29029 October 2009 Tritium Meeting, Southern Nuclear, Hatch ML0910607322009-04-16016 April 2009 Summary of Meeting with Southern Nuclear Operating Co, Inc., to Provide Opportunities to Discuss Annual Assessment of Edwin I. Hatch for the Period of 01/01/2008 - 12/31/08 ML0810704462008-04-0909 April 2008 Annual Assessment Public Meeting, Slides ML0723505462007-08-23023 August 2007 08/15/2007 Public Meeting Summary - Enclosure 2 ML0717004662007-05-31031 May 2007 05/2007 Generation Planning Overview. ML0632800652006-11-14014 November 2006 Meeting Summary Handouts, Enclosure 2 (Tac Nos. MD2934 and MD2935) ML0622804942006-08-0909 August 2006 Hatch Tritium Public Meeting Power Point Slide Attachment ML0611505512006-04-12012 April 2006 Slides for Annual Assessment Meeting Cy 2005 ML0610704022006-04-12012 April 2006 Edwin I. Hatch Annual Assessment Meeting Cy 2005- Slides ML0535403442005-12-12012 December 2005 Submittal of Power Point Presentation Proposed Solutions to Part 21 on Safety Limit 2.1.1.1, NUREG-1433/34 ML0511501332005-04-13013 April 2005 Annual Assessment Meeting Cy 2004, Edwin I. Hatch Nuclear Plant - NRC Region II, Vidalia, Ga, April 13, 2005 ML0410406802004-04-0606 April 2004 Meeting Presentation for Edwin I. Hatch Annual Assessment Meeting, Reactor Oversight Program - Cy 2003 ML0333003292003-11-19019 November 2003 Summary of Meeting Held on November 3, 2003, Between NOAA Fisheries, U.S.Corps of Engineers, and U.S. Nuclear Regulatory Commission to Discuss Section 7 Consultations Under the Endangered Species Act 2024-09-19
[Table view] |
Text
Hatch Pre-Submittal Meeting NFPA-805 Supplemental LAR January 2021
Meeting Purpose and Agenda
- Meeting purpose: Discuss proposed license amendment request (LAR) to supplement modifications described in Table S-2, Plant Modifications Committed, of SNC letter NL-19-1475, dated December 13, 2019
- LAR will update Transition License Conditions for both units to refer to updated Table S-2
- Updated Table S-2 will be submitted as part of LAR Agenda
Issue Background Issue Background
- June 2020, NRC issued Amendments 304 and 249 to Hatch Units 1 and 2 Renewed Facility Operating License (RFOL) to adopt NFPA-805 performance-based standards
- Amendments contain Transition License Conditions that require SNC to implement modifications described in Table S-2 of December 13, 2019 SNC letter by the startup of the second refueling outage (for each unit) after issuance of NRC Safety Evaluation (SE)
- Unit 2 = by startup of spring 2023 refueling outage 2R27
- Unit 1 = by startup of spring 2024 refueling outage 1R31
- Appropriate compensatory measures required until full compliance achieved 4
Issue Background (continued)
- For equipment not affected by fire, NFPA-805 requires that a fire-induced cable failure on a separate load circuit supplied from the same power source would not affect this equipment
- Subsequent to issuance of Hatch NFPA-805 RFOL Amendments, additional breakers were discovered that lacked proper coordination
- SNC currently finalizing extent of condition to ensure all breaker coordination issues are identified 5
Proposed License Amendment Request
Proposed License Amendment Request LAR will generally follow format prescribed in NEI 06-02:
1.0
SUMMARY
DESCRIPTION 2.0 DETAILED DESCRIPTION 2.1 Current Licensing Basis Requirements 2.2 Reason for the Proposed Change 2.3 Description of the Proposed Change
3.0 TECHNICAL EVALUATION
4.0 REGULATORY EVALUATION
4.1 Applicable Regulatory Requirements / Criteria 4.2 No Significant Hazards Consideration Determination Analysis 4.3 Conclusions
5.0 ENVIRONMENTAL CONSIDERATION
6.0 REFERENCES
ATTACHMENTS:
M. License Condition Changes S. Modification Items 7
1.0 Summary Description 2.0 Detailed Description 1.0 Summary Description
- Proposed change will revise Hatch Units 1 and 2 RFOL to reference updated Table S-2 for list of required modifications that must be implemented to achieve full compliance with NFPA-805
- Revised RFOL will specify the modifications are required by the startup of the Unit 2 spring 2023 refueling outage, U2R27, and by the startup of the Unit 1 spring 2024 refueling outage, U1R31 2.0 Detailed Description
- 1. Current Licensing Basis Requirements
- Discuss current RFOL requirements
- 2. Reason for Proposed Change
- Discuss that current Table S-2 referenced in RFOLs does not contain all required modifications to achieve compliance
- 3. Description of Proposed Change
- Describe proposed marked-up changes to RFOLs 8
3.0 Technical Evaluation
- Discuss NRC SE conclusions that the SNC approach, methods, and data are acceptable to establish, implement, and maintain the proposed risk-informed performance based (RI/PB) fire protection plan (FPP) in accordance with 10 CFR 50.48(c), subject to the completion of the modifications identified in Table S-2 and the implementation items identified in Table S-3
- 2001 Edition of NFPA-805 provides a comprehensive RI/PB standard for fire protection, and specifies minimum requirements for light-water reactors during all phases of plant operation
- As discussed in Section C.2.1 of RG 1.205, Revision 1, when the NRC issues an NFPA-805 license amendment it will impose a license condition requiring the use of NFPA-805 along with an implementation schedule
- Items identified in Table S-2 and S-3 were credited in LAR supporting analysis, and were relied upon by NRC staff in its review 9
3.0 Technical Evaluation (continued)
- Discuss NFPA-805 requirements for proper breaker coordination, and assumptions used in Fire PRA model
- Discuss that updated Table S-2 will not affect Fire PRA model
- Discuss that the amendment request will not impact the NFPA-805 modification schedule contained in the current RFOL to achieve full compliance with 10 CFR 50.48(c) 10
4.0 Regulatory Evaluation 5.0 Environmental Considerations 6.0 References
- Will use portions of original Hatch NFPA-805 LAR as appropriate to address these sections 11
Attachment M License Condition Changes The licensee shall implement the modifications described in Attachment S2, Table S-2, Plant Modifications Committed, of SNC letter NL-19-1475 NL-21-XXXX, dated December 13, 2019 Month, Day, 2021, to its facility to complete transition to full compliance with 10 CFR 50.48(c) by the startup of the second refueling outage (for each unit) after the issuance of the NRC SE Unit 2 refueling outage 2R27 (spring 2023) and Unit 1 refueling outage 1R31 (spring 2024). The licensee shall maintain appropriate compensatory measures in place until completion of these modifications.
12
Attachment S Modification Items Will be consistent with Table S-2 referenced in current RFOLs, with the inclusion of the additional required breaker coordination modifications 13
Questions?