Southern Nuclear Operating Company (SNC) Standard Emergency Plan (SEP)
SNC/Nuclear Regulatory Commission (NRC) Pre-submittal Interaction April, 22, 2015
Agenda
- July 2014 Interaction Recap
- Change in Submittal Scope
- Status of Fleet SEP
- Construction/Testing Schedule Milestones Update
- License Amendment Scope and Schedule
- Key Features of the Submittal
- Licensing Considerations
- Questions/Feedback 2
July 2014 Interaction Recap
- Described current status of and history of Vogtle 3-4 emergency plan
- Discussed options for combining the two Vogtle emergency plans into a single plan
- Agreed that the option of adopting the fleet SEP on a limited basis to include Vogtle only was the option of choice
- Agreed that future interactions would be desirable 3
Change in Submittal Scope
- Initial submittal to include SNC SEP base for all SNC plants, and annexes for Farley, Hatch, Vogtle 1-2 and Vogtle 3-4
- Vogtle 1-2 annex will be submitted using the current Technical Support Center (TSC) and Operations Support Center (OSC)
- When approved and SNC personnel trained on new SNC Fleet SEP then Farley, Hatch, Vogtle 1-2 and Vogtle 3-4 will implement
- Impacts to Emergency Operations Facility (EOF) and EOF staffing require all SNC plants to implement concurrently, with exception of Vogtle 3-4
- A separate License Amendment Request (LAR) will be submitted for Vogtle 1-2 to transition to the common TSC and OSC
- The LAR for use of the common Vogtle TSC and OSC by all Vogtle units will be implemented prior to 10 CFR 52.103(g) 4
Status of Fleet SEP
- Fleet SEP drafted
- Includes all emergency plan information common to SNC plants (Farley, Hatch and Vogtle)
- EOF
- Communication plan
- Annexes for Farley, Hatch, Vogtle 1-2 and Vogtle 3-4 drafted
- Include EP information unique to each site
- Much information for each Vogtle annex identical, but separate information for treatment of Emergency Action Level (EALs) and associated technical bases 5
VEGP 3 and 4 EP Related Construction/Testing Schedule Milestones
- VEGP 3 fuel load
- VEGP 10 CFR 52.103(g) finding - EP required to be followed and effectiveness maintained (10 CFR 50.54(q)(2))
- Final EALs submitted for approval - 180 days before fuel load -
License Condition (Following SCANA approach)
- Staffing assessment submitted - 180 days before fuel load - License Condition (Staffing analysis completed December 2014)
- Implementing procedures submitted - 180 days before fuel load -
ITAAC 6
License Amendment Scope and Schedule
- Submittal planned for June 2015
- Requesting approval by June 2016
- Submit LAR for Vogtle site common TSC and OSC in June 2016 immediately following approval of SNC SEP
Key Features of the Submittal
- Conforms to NUREG 0654 Rev. 1
- Removes unnecessary detail
- Leverages fleet standard procedures and processes
- Requests a 90 minute augmentation time
- Revises EOF organization to include Emergency Director
- 90 minute augmentation time
- Use of tone alert radio as back-up notification method
- SEP refers to implementing procedures as Emergency Plan Implementing Procedure (EPIPs)
- Existing emergency plan uses the term Emergency Implementing Procedure (EIP)
Licensing Considerations Submittal contents
- LAR Considerations
- One letter with separate enclosures for Farley, Hatch, Vogtle 1-2 and Vogtle 3-4
- Separate enclosures with change justification matrices for Farley, Hatch, Vogtle 1-2 and Vogtle 3-4
- Separate enclosures with ERO Augmentation Technical Document for Farley, Hatch, Vogtle 1-2 and Vogtle 3-4
Questions/Feedback 11