ML24290A079
ML24290A079 | |
Person / Time | |
---|---|
Site: | Hatch |
Issue date: | 10/18/2024 |
From: | Ashley Waldron NRC/NMSS/DREFS/EPMB1 |
To: | Coleman J Southern Nuclear Operating Co |
References | |
Download: ML24290A079 (1) | |
Similar Documents at Hatch | |
---|---|
Category:Letter
MONTHYEARIR 05000321/20240102024-11-0606 November 2024
[Table view]NRC Inspection Report 05000321/2024010 and 05000366/2024010 ML24299A2222024-10-31031 October 2024 Audit Summary for License Amendment Request to Revise Renewed Facility Operating Licenses to Adopt an Alternative Seismic Method for Categorization of Structures, Systems, and Components NL-24-0357, Notification of Deviation from the Inspection Frequency Requirements of the Boiling Water Reactor Vessel and Internals Project (BWRVIP) BWR Jet Pump Assembly Inspection and Flaw Evaluation Guidelines2024-10-30030 October 2024 Notification of Deviation from the Inspection Frequency Requirements of the Boiling Water Reactor Vessel and Internals Project (BWRVIP) BWR Jet Pump Assembly Inspection and Flaw Evaluation Guidelines IR 05000321/20240032024-10-30030 October 2024 Edwin I Hatch, Units 1 and 2 - Integrated Inspection Report 05000321/2024003 and 05000366/2024003 ML24292A1602024-10-22022 October 2024 Request for Withholding Information from Public Disclosure License Amendment Request to Revise Technical Specification Surveillance Requirements to Increase Safety/Relief Valve Setpoints ML24290A0792024-10-18018 October 2024 SLR Environmental Preapplication Meeting Summary ML24303A4102024-10-17017 October 2024 Dir Results Letter to NRC - Hatch - Hurricane Helene IR 05000321/20244012024-10-10010 October 2024 Security Baseline Inspection Report 05000321-2024401 and 05000366-2024401 ML24256A0282024-09-12012 September 2024 2024 Hatch Requal Inspection Corporate Notification Letter NL-23-0930, Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program2024-09-11011 September 2024 Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program NL-24-0337, Interim 10 CFR 21.21(a)(2) Report Regarding Operation Technology, Inc., ETAP Software Error in Transient Stability Program2024-09-0909 September 2024 Interim 10 CFR 21.21(a)(2) Report Regarding Operation Technology, Inc., ETAP Software Error in Transient Stability Program ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 NL-24-0334, 0 to the Updated Final Safety Analysis Report, Technical Specifications Bases Changes, Technical Requirements Manual Changes, License Renewal 10 CFR 54 .37(b) Changes, 10 CFR 50.59 Summary Report & Revised Nrc2024-09-0303 September 2024 0 to the Updated Final Safety Analysis Report, Technical Specifications Bases Changes, Technical Requirements Manual Changes, License Renewal 10 CFR 54 .37(b) Changes, 10 CFR 50.59 Summary Report & Revised Nrc IR 05000321/20240912024-08-27027 August 2024 NRC Investigation Report 2-2023-003 and NOV - NRC Inspection Report 05000321/2024091 and 05000366/2024091 IR 05000321/20240052024-08-26026 August 2024 Updated Inspection Plan for Edwin I. Hatch Nuclear Plant, Units 1 and 2 - Report 05000321/2024005 and 05000366/2024005 NL-24-0313, Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint Response to Request for Additional Information2024-08-23023 August 2024 Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint Response to Request for Additional Information IR 05000321/20240022024-08-0808 August 2024 Edwin I Hatch Nuclear Plants, Units 1 and 2 – Integrated Inspection Report 05000321-2024002 and 05000366-2024002 NL-24-0290, Response to Request for Additional Information Related to Request for Specific Exemption2024-07-26026 July 2024 Response to Request for Additional Information Related to Request for Specific Exemption NL-24-0276, Post-Audit Supplement to License Amendment Request to Revise Renewed Facility Operating Licenses to Adopt an Alternative Seismic Method for Categorization of Structures, Systems, and Components2024-07-26026 July 2024 Post-Audit Supplement to License Amendment Request to Revise Renewed Facility Operating Licenses to Adopt an Alternative Seismic Method for Categorization of Structures, Systems, and Components NL-24-0261, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 20232024-07-19019 July 2024 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2023 ML24198A1252024-07-16016 July 2024 Edwin I Hatch Nuclear Plant Units 1 - 2 Notification of Conduct of Title 10 of the Code of Federal Regulations 50 NL-24-0260, Inservice Inspection Program Owner’S Activity Report (OAR-1) for Refueling Outage 1R312024-07-0909 July 2024 Inservice Inspection Program Owner’S Activity Report (OAR-1) for Refueling Outage 1R31 05000321/LER-2024-003, Reactor Core Isolation Cooling (RCIC) System Inoperable Due to Mispositioned Link2024-07-0303 July 2024 Reactor Core Isolation Cooling (RCIC) System Inoperable Due to Mispositioned Link 05000321/LER-2024-002-01, Incorrectly Installed Temporary Modification Results in Multiple Conditions Prohibited by Plant Technical Specifications2024-07-0303 July 2024 Incorrectly Installed Temporary Modification Results in Multiple Conditions Prohibited by Plant Technical Specifications NL-24-0143, Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities in2024-06-27027 June 2024 Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities in NL-24-0239, Response to Apparent Violation in NRC Inspection Report 05000321, 366/2024090: EA-23-1392024-06-17017 June 2024 Response to Apparent Violation in NRC Inspection Report 05000321, 366/2024090: EA-23-139 ML24163A0532024-06-14014 June 2024 Audit Plan - Alternative Seismic Method LAR NL-24-0148, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2024-06-0404 June 2024 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis ML24149A0492024-06-0404 June 2024 SNC Fleet - Regulatory Audit in Support of Review of the License Amendment Request to Revise TS 1.1, Use and Application Definitions, and Add New Technical Specification 5.5.21 and 5.5.17, Online Monitoring Program, NL-24-0202, SNC Response to Regulatory Issue Summary 2024-01: Preparation and Scheduling of Operator Licensing Examinations2024-05-24024 May 2024 SNC Response to Regulatory Issue Summary 2024-01: Preparation and Scheduling of Operator Licensing Examinations IR 05000321/20240902024-05-15015 May 2024 NRC Inspection Report 05000321-2024090 and 05000366-2024090, Investigation Report 2-2023-003; and Apparent Violation NL-24-0191, Annual Radiological Environmental Operating Reports for 20232024-05-10010 May 2024 Annual Radiological Environmental Operating Reports for 2023 05000321/LER-2024-002, Manual Reactor Trip Due to Loss of Feedwater2024-05-0909 May 2024 Manual Reactor Trip Due to Loss of Feedwater NL-24-0195, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water.2024-05-0707 May 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water. NL-24-0064, Units 1 & 2 and Hatch Nuclear Plant - Units 1 & 2 License Amendment Request to Revise Technical Specification 1.1 and Add Online Monitoring Program to Technical Specification 5.52024-05-0303 May 2024 Units 1 & 2 and Hatch Nuclear Plant - Units 1 & 2 License Amendment Request to Revise Technical Specification 1.1 and Add Online Monitoring Program to Technical Specification 5.5 IR 05000032/20240112024-04-25025 April 2024 Notification of Edwin I. Hatch Nuclear Plant - Comprehensive Engineering Team Inspection (CETI) Baseline Inspection Report 0500032/2024011 and 05000366/2024011 NL-24-0165, Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 20232024-04-25025 April 2024 Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 2023 05000366/LER-2024-002, Incorrectly Installed Temporary Modification Results in a Condition Prohibited by Plant Technical Specifications2024-04-24024 April 2024 Incorrectly Installed Temporary Modification Results in a Condition Prohibited by Plant Technical Specifications ML23032A3322024-04-24024 April 2024 Issuance of Amendments Nos. 322 and 267, Regarding LAR to Relax Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in TS Table 1.1-1, Modes IR 05000321/20240012024-04-22022 April 2024 Integrated Inspection Report 05000321/2024001 and 05000366/2024001 NL-24-0026, Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint2024-04-19019 April 2024 Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint 05000321/LER-2024-001, Primary Containment Penetration Exceeded Maximum Allowable Primary Containment Leakage Rate (La)2024-04-0909 April 2024 Primary Containment Penetration Exceeded Maximum Allowable Primary Containment Leakage Rate (La) NL-24-0115, Response to Request for Additional Information Exemption Requests for Physical.2024-04-0404 April 2024 Response to Request for Additional Information Exemption Requests for Physical. NL-24-0116, Nuclear Property Insurance Coverage as of April 1, 2024 and Licensee Guarantees of Payment of Deferred.2024-03-29029 March 2024 Nuclear Property Insurance Coverage as of April 1, 2024 and Licensee Guarantees of Payment of Deferred. ML23275A2402024-03-22022 March 2024 SNC Fleet - Issuance of Environmental Assessment and Finding of No Significant Impact Regarding Exemption from the Requirements of 10 CFR Part 73, Section 73.2, Definitions (EPID Nos. L-2023-LLE-0018 & L-2023-LLE-0021) - Letter NL-24-0062, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2024-03-12012 March 2024 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis ML24069A0012024-03-0909 March 2024 – Correction of Amendment No. 266 Regarding License Amendment Request Regarding Relocation of Specific Surveillance Frequencies to a Licensee-Controlled Program (TSTF-425, Revision 3) NL-24-0089, Correction of Technical Specification Omission2024-03-0909 March 2024 Correction of Technical Specification Omission ML24047A0362024-03-0404 March 2024 Response to Hatch and Vogtle FOF Dates Change Request (2025) NL-24-0061, Cycle 32 Core Operating Limits Report Version 12024-03-0101 March 2024 Cycle 32 Core Operating Limits Report Version 1 2024-09-09 Category:Meeting Summary MONTHYEARML24290A0792024-10-18018 October 2024
[Table view]SLR Environmental Preapplication Meeting Summary ML24213A2462024-08-0505 August 2024 Summary of Closed Meeting SNC Fleet - Physical Barriers Exemption ML24156A1772024-06-11011 June 2024 Summary of June 6, 2024, Closed Meeting Held with Southern Nuclear Operating Company, Inc., Regarding the Physical Barrier Exemptions for Joseph M. Farley Nuclear Plant, Units 1 and 2, Edwin I. Hatch Nuclear Plant, Units 1 and 2, and Vogtle ML24123A0502024-05-0202 May 2024 2023 Annual Assessment Public Meeting Summary Meeting Number 20240479 ML24019A1932024-01-30030 January 2024 Summary of January 8, 2024, Observation Pre-Submittal Meeting Held with Southern Nuclear Operating Company Regarding a Proposed LAR for Vogtle Electric Generating Plant, Units 1, 2, 3, & 4; Hatch, Units 1 & 2; Farley, Units 1 & 2 ML24012A1592024-01-30030 January 2024 Summary of January 8, 2024, Meeting Held with Southern Nuclear Operating Company, Inc., to Discuss a RAI License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Head Bolts ML23356A0282023-12-27027 December 2023 December 11, 2023, Pre-Application Meeting with SNC Regarding a Proposed Fleet LAR to Revise TS 5.3.1 to Relocate Training Qualification Requirements from TS to Their Qatr/Ndqam ML23338A2592023-12-0808 December 2023 Summary of Observation Public Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a License Amendment Request for the Reactor Pressure Vessel Head Closure Bolts for Hatch, Units 1 & 2 (EPID No. L-2022-LLA- 0120) ML23311A1302023-11-17017 November 2023 Summary of Nov. 6, 2023, - Closed Meeting Held with Southern Nuclear Operating Company, Inc., Regarding Physical Barriers Exemptions for Hatch Units 1 & 2, Farley Units 1 & 2 and Vogtle Units 1, 2, 3 & 4 (EPID L-2023-LLE-0018 & L-2023-LLE-0 ML23244A0312023-09-18018 September 2023 MTS - Meeting Summary - Pre-Submittal Meeting on August 02, 2023 - RICT 45-day Extension for TS 3.7.1 & 3.7.2 ML23136B2942023-05-19019 May 2023 Summary of May 02, 2023, Observation Public Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a LAR for the Reactor Pressure Vessel Head Closure Bolts for Edwin I. Hatch Nuclear Plant, Units 1 and 2 ML23088A3882023-04-0303 April 2023 Summary of March 28, 2023, Observation Public Meeting Held with SNC, Regarding a License Amendment Request Regarding the Reactor Pressure Vessel Head Closure Bolts for Edwin I. Hatch Nuclear Plan, Units 1 and 2 ML23088A2362023-03-28028 March 2023 SNC Presentation - Public Meeting - 03-28-2023 - Page from ML22231B055 ML22243A1912022-09-0707 September 2022 Public Pre-Submittal Meeting on August 1, 2022 - Revise TS Table 1.1-1 Modes to Relax RPV Head Closure Studs ML22200A0432022-07-22022 July 2022 Summary of June 22, 2022, Pre-Submittal Meeting W/Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request to Re-Write TS 3.7.2, Plant Service Water and Ultimate Heat Sink for Edwin I. Hatch Nuclear ML22108A1382022-04-18018 April 2022 Annual Assessment Public Meeting Summary ML21278A5572021-10-25025 October 2021 Meeting Summary - Pre-Submittal Meeting on October 5, 2021 - Hatch NFPA 805 License Amendment Request ML21251A5372021-09-20020 September 2021 September 7, 2021, Summary of Follow-Up, Public, Pre-Licensing Meeting with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request to Adopt TSTF-505 for Edwin I. Hatch Nuclear Plant, Units 1 and 2 ML21229A0072021-09-10010 September 2021 Summary of Public Meeting with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request to Adopt TSTF-505 ML21232A2622021-09-0101 September 2021 Summary of Public Meeting with Southern Nuclear Operating Company Regarding Proposed LAR to Remove Function 1.f (Main Steam Line Isolation-Turbine Building Area Temperature-High) from TS Table 3.3.6.1A-7 for Hatch Units 1&2 (L-2021-LRM-0081 ML21124A1232021-05-0404 May 2021 April 27, 2021, Public Meeting Summary Joseph M. Farley Nuclear Plant Units 1 and 2, Edwin I. Hatch Nuclear Plant Units 1 and 2, Docket No. 50-348, 50-364, 50-321, 50-366, Meeting Number ML21117A030 ML21102A3112021-04-19019 April 2021 Corrected - 03/31/2021 Summary of Public Meeting with Southern Nuclear Operating Company, Inc., Regarding a Proposed Licensing Action Request to Change the Quality Assurance Topical Report ML21092A0082021-04-0808 April 2021 Summary of March 31, 2021, Public Meeting with Southern Nuclear Operating Company, Inc., Regarding a Proposed Licensing Action Request to Change the Technical Specification Related to Heat Flux Hot Channel Factor ML21028A0532021-02-0303 February 2021 Summary of Public Meeting with Southern Nuclear Operating Company, Inc., Regarding a Proposed License Amendment Request to Supplement National Fire Protection Association (NFPA)-805, Performance-Based Standard for Fire Protection for ML20318A0752020-11-16016 November 2020 Summary of November 12, 2020, Public Meeting with Southern Nuclear Operating Company, Inc., Regarding a License Amendment Request for the Emergency Plan ML20289A4242020-11-0404 November 2020 Summary of Public Meeting with Southern Nuclear Operating Company, Inc. Regarding Proposed License Amendment Request to Remove Function 1.f from Technical Specification Table 3.3.6.1A-7 for Hatch, Units 1 and 2 ML20217L3692020-08-13013 August 2020 Summary of Meeting Joseph M. Farley Nuclear Plant, Units 1 and 2; Edwin I. Hatch, Units 1 and 2; and Vogtle Electric Generating Plant, Units 1, 2, 3, and 4 a LAR for the Emergency Plan (EPID Nos. L-2020-LLA0150 and L-2020-LLA-015 ML20162A1622020-06-16016 June 2020 June 10, 2020, Summary of Public Mtg with Southern Nuclear Operating Company, Inc., a Proposed License Amendment Request for a One-Time Completion Time for the Emergency Diesel Generator Using a Risk-Informed Approach ML20154K7242020-06-0202 June 2020 EOC Meeting Summary ML19123A3542019-05-0202 May 2019 Public Meeting Summary - Hatch Nuclear Plant, Docket Nos. 50-321 and 50-366 ML19114A0062019-04-30030 April 2019 Summary of July 31, 2018, Pre-Application Meeting with Southern Nuclear to Discuss Proposed Changes to Secondary Containment Technical Specifications (EPID L-2018-LEM-0047 ML19038A3462019-02-15015 February 2019 Summary of Meeting with the Nuclear Regulatory Commission and Southern Nuclear Operating Company, Inc. Regarding Pre-Submittal of a License Amendment Request for Proposed Changes to Emergency Response Organization Staffing and Augmentation ML18284A0222018-10-16016 October 2018 August 23, 2018, Summary of Pre-Application Meeting with Southern Nuclear Operating Company, Inc. to Discuss TSTF-51 and TSTF-471 ML18142B0452018-05-24024 May 2018 Summary of May 21, 2018, Pre-submittal Public Teleconference with Southern Nuclear Operating Company, Inc. to Discuss the Upcoming License Amendment Request to Remove the Dedicated Shift Technical Advisor ML18124A0052018-05-0404 May 2018 Summary of Public Meeting - Hatch Nuclear Plant Docket Nos. 50-321, 50-366 ML17131A1572017-05-11011 May 2017 Summary of Public Meeting Concerning Annual Assessment of Edwin I. Hatch Nuclear Plant, Units 1 and 2 ML17093A9172017-04-21021 April 2017 Summary of 3/23/2017, Pre-Submittal Public Meeting with Southern Nuclear Operating Company, Inc. to Discuss the Proposed License Amendment Requests Regarding TSTF-542, Reactor Pressure Vessel Water Inventory Controls, and SR3.3.1.3 (CAC Nos ML17030A4372017-02-15015 February 2017 Summary of Public Meeting with Southern Nuclear Operating Company, Inc. to Discuss the Degraded Grid Voltage Proposed License Amendment Request ML16179A1862016-06-30030 June 2016 Summary of Public Meeting with Southern Nuclear Operating Company to Discuss Delay of Application Date for NFPA 805 License Amendment Request for Edwin I. Hatch Nuclear Plant, Units Nos. 1 and 2 ML16085A1762016-03-29029 March 2016 Summary of March 24, 2016, Meeting with Southern Nuclear Operating Company Regarding Planned Physical Protection Modifications ML15195A4812015-08-31031 August 2015 July 13, 2015, Summary of Meeting with SNC on High Density Polyethylene Piping for HNP-2 ML15125A0872015-05-26026 May 2015 May 12, 2015 Summary of Meeting with Southern Nuclear Operating Company to Discuss a Future Fleet Standard Emergency Plan Submittal ML15121A0342015-04-30030 April 2015 Summary of Public Meeting to Discuss the 2014 Annual Performance Assessment of the Edwin I. Hatch Nuclear Plant ML15103A0602015-04-30030 April 2015 April 22, 2015, Summary of Meeting with Southern Nuclear Operating Company to Discuss a Future Fleet Standard Emergency Plan Submittal ML14122A0372014-05-0808 May 2014 April 23, 2014 Summary of Meeting with Southern Nuclear Operating Company to Discuss Grid Design Criteria ML14115A4102014-04-25025 April 2014 Summary of Public Meeting to Discuss Annual Assessment of Edwin I. Hatch Nuclear Plant, Units 1 and 2, in Vidalia, Georgia ML13225A2932013-08-12012 August 2013 7/23-24/2013, Summary of Meeting 2013 U.S. Nuclear Regulatory Commission (NRC) Initial Exam Writers' Workshop ML13112A2552013-04-22022 April 2013 Summary of Public Meeting to Discuss the Annual Assessment of Edwin I. Hatch Nuclear Plant with the Public for the Period of January 1, 2012, - December 31, 2012 ML12115A2572012-04-24024 April 2012 Summary of with Southern Nuclear Operating Co., Inc., to Discuss the Annual Assessment of Edwin I. Hatch for 2011 ML11292A1612011-10-20020 October 2011 Summary of Meeting with Beyond Nuclear Regarding Their 10 CFR 2.206 Petition to Suspend Operating Licenses of General Electric Mark I Boiling Water Reactors 2024-08-05 |
Text
Jamie M. Coleman Regulatory Affairs Director Southern Nuclear Operating Co., Inc.
3535 Colonnade Parkway Birmingham, AL 35243
SUBJECT:
EDWIN I. HATCH, UNITS 1 AND 2 SUBSEQUENT LICENSE RENEWAL APPLICATION - PUBLIC MEETING
SUMMARY
OF PRE-SUBMITTAL ENVIRONMENTAL REVIEW MEETING (DOCKET NUMBERS: 50-321 AND 50-366)
Dear Jamie Coleman:
By letter dated November 20, 2023 (Agencywide Documents Access and Management System (ADAMS) ML23324A132), Southern Nuclear Company (Southern, the applicant), submitted a letter of intent to submit a subsequent license renewal (SLR) application for Edwin I. Hatch (Hatch) Units 1 and 2.
On September 19, 2024, the U.S. Nuclear Regulatory Commission (NRC, or the staff) held a public meeting with Southern to discuss the expected content of the upcoming submittal of their SLR application and accompanying environmental report for Hatch. The focus of this meeting was on the environmental review. The slides for the staff presentation are available in ADAMS at ML24263A082. A similar meeting will be held in the future for the safety review.
Southern provided its presentation involving Hatch, which is available in ADAMS under ML24278A001. The staff discussed the NRCs review process and the applicant discussed relevant environmental issues related to their SLR application. No members of the public provided comments or asked questions.
Should you have any questions, please contact me via email at Ashley.Waldron@nrc.gov.
Sincerely, Ashley Waldron Environmental Project Manager Environmental Project Manager Branch 1 Division of Rulemaking, Environment, and Financial Support Office of Nuclear Material Safety and Safeguards Docket Nos. 50-321 and 50-366
Enclosure:
List of Attendees October 18, 2024 Signed by Waldron, Ashley on 10/18/24
ML24290A079 (Ltr)
OFFICE PM:EPMB1 LA:REFS BC:EPMB1 PM:EPMB1 NAME A.Waldron AWalker-Smith S.Koenick A.Waldron DATE 10/16/2024 10/16/2024 10/17/2024 10/18/2024
List of Attendees NRC Attendees Ashley Waldron Brian Harris Steve Koenick Rao Tammara Dawnmathews Kalathiveettil John Lamb Nancy Martinez Other Attendees Peter LeJeune Thomas Casey Paul Guill Jeff Sharkey Hannah Pell Kristin Meek Heather Galloway Southern Amy Aughtman Lindsey Grissom Brad Deen Yasmeen Arafeh Jim DeLano Michael Todd Louis Tony Banks Bradley Creek Brandon Marlow Ernest Bates Adam Wilcher Enercon Stacey Burgess Stephan Franzone Rachel Turney-Work Mary Hoganson Enclosure