Advises That Fuel Load Date for Unit 1 Remains 830831.Util Budget Includes Provisions for Up to 4-month Delay of Fuel Load Date
ML20072A694
Person / Time
Site: Byron  Constellation icon.png
Issue date: 01/18/1983
From: Mark Miller
COMMONWEALTH EDISON CO., ISHAM, LINCOLN & BEALE
To: Smith I
Atomic Safety and Licensing Board Panel
References
ISSUANCES-OL, NUDOCS 8301240105
Download: ML20072A694 (1)


Text

^

ISHAM, LINCOLN & BEALE COUNSELORS AT LAW THREE FIRST NATIONAL PLAZA CHICAGO. ILUNOIS 40 Bot 9E EEI,,U T .

issoC [EN!,N W -

January 18, 1983 In the Matter of ) 'M - - AL DCCh.. m & SERV!CL

) RwlC4 COMMONWEALTH EDISON COMPANY ) Docket Nos. 50-454 OL

) 50-455 OL (Byron Nuclear Power Station, )

Units 1 & 2) )

Hon. Ivan W. Smith Administrative Judge and Chairman l

Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission Washington, D. C. 20555

Dear Judge Smith:

You have recently inquired regarding the Applicant's current estimates of the fuel load date for Byron Station Unit 1.

The Company has just concluded its semi-annual budget review. The target fuel load date for Byron Unit 1 remains August 31, 1983. The Company believes that fuel load by that date is achievable. Nonetheless, there are a substantial number of construction and pre-operational testing matters which must be concluded on a timely basis in order for fuel load to proceed on that date. Accordingly, as a planning contingency, the Company's budget for the project includes provisions which the Company believes sufficient to provide for a delay of up to four months in the tuel load date. Notwithstanding this planning con-tingency, Commonwealth Edison Company is devoting all resources necessary to achieve fuel load by the August 31, 1983 date.

l I will, of course, keep the Board and parties informed of any developments with respect to the fuel load date for Byron Unit 1.

I

- - Sincerely, M, y B301240105 830118 DR ADOCK 05000  ;

MIM:es Michael I. Miller One of the Attorneys for Commonwealth Edison Company cc Service List e