Monthly Operating Rept for Oct 1982
ML20028A057
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 11/02/1982
From: Norris H
CAROLINA POWER & LIGHT CO.
To:
Shared Package
ML20028A055 List:
References
NUDOCS 8211160349
Download: ML20028A057 (3)


Text

OPERATING DATA REPORT DOCRET NO: 50-261 DATE: 821102

  • COMPLETED BY: H. Ray Norris TELEPHONE: (803) 383-4524-OPERATING STATUS Notes:
1. Unit Name: H. B. Robinson, Unit No. 2 There are presently 157 spent fuel
2. Reporting Period: 821001, 0000 / 821031, 2400 assemblies in the spent fuel pool.
3. Licensed Thermal Power (FMt): 2300
4. Nameplate Rating (Gross MUe): 739
5. Design Electrical Rating (Net IMe):_, 700 700
6. bbximum Dependable
7. Maximum Capacity(Net Dependable Capacity (Gross FMe):,_ 66)

MWe): _ _ .

8. If Changes Occur in Capacity Ratings (Item Number 3 through 7) Since Last Report, Give Reasons: No Change
9. Power Level to Which Restricted, If Any (Met MWe): 1955 MWt Reactor Power
10. Reasons For Restrictions, If Any: Although the unit is not restrictea by any out'sla'e agency, the power level is presently reduced due to steam generator considerations.

This Month Yr.-to-Date Cumulative

11. Hours in Reporting Period 745 7296 102222
12. Number of Hours Reactor Was Critical 718.30 3097.93 75443.35
13. Reactor Reserve Shutdown Hours 0 0 1085.30 ~
14. Hours Generator On-Line 714.87 2888.64 73443.95
15. U11t Reserve Shutdown Hours 0 0 23.20
16. Gross Thermal Energy Generated (Fnal) 1331043 5106670 148202044
17. Cross Electrical Energy Generated (FMH) 419848 1609523 47687493
18. Net Electrical Energy Generated (MWU) 394977 1479404 45099655
19. Unit Service Factor 95.96 39.59 71.85
20. Unit Availability Factor 95.96 39.59 71.87
21. Unit Capacity Factor (Using MDC Net)

~

79.72 30.49 66.34

22. Unit Capacity Factor (Using DER Net) 75.74 28.97 63.03
23. Unit Forced Outage Rate 0 8.66 14.37
24. Shutdowns Scheduled Over Next 6 lbnths (Type, Date, and Duration of Each):

Type-2 5/1/83, Four Week Steam Generator Inspection Outage

25. If Shut Down At End of Report Period, Estimated Date of Startup: On Line
26. Units In Test Status (Prior to Commercial Operation): Forecast Achieved INITIAL CRITICALITY --- ---

INITIAL ELECTRICITY --- ---

COMMERCIAL OPERATION --- ---

8211160349 821110 PDR ADOCK 05000261 R PDR (9/77) ag

0 AVERAGE DAILY UNIT POWER LEVEL I)OCKET NO.53-761 UNIT H. B. Robinson DATE 821102 COMPLETED BY H. Rav Norric TELEPHONE .(803) 383-4524 MONT11 OCTOBER DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe Net) (MWe Net) g 548 g7 535 550 jg 558 2

3 551 39 560 4 552 20 559 g 553 21 560 552 511 6 3 553 0 7 23 g 552 24 412 9 554 25 558 10 537 26 561 gg 552 27 561 12 _

554 28 561 g3 555 29 562 3.g 556 30 562 555 3g 561 33 16 558 INS 1RUCT10NS On this format, list the avmp daily umt power levelin MWe Net for each day in the reporting month. Compute to the nearest v. hole innawstt.

(9/77) dd 4

DOCKET NO. _ 50-261 l UNIT N AME H- B- Rnhinann .

- UNIT SHUTDOWNS AND POWER REDUCTIONS DATE 871102 ,

' H_ Rav Mntri e COMPLETED BY OCTOBER TELEPilONE ( R fili 1R h!a?4 REPORT MONTl!

":. a

,{g 3 JYh Licensee ,E r, je, Cause A Correctiver -

Action to

, g,y No. Date g 3g ( .5 s 5 Event Report a mO c.'@

j' Prevent Recurrence 6-f: $ j 53 O *

  • --- PC VALVEX- Unit retired for repair of CVCS 10-01 821024 S 30.13 B 1 '

Letdown Relief Vaive and other .

maintenance items. - .

~ . .

9 ee

. . 4 3

I - 2 Method: Exhibit C Instructions

  • Iteawn:

for Preparation of Data F: Forced 1. Manual -

S: Sehedsded A l'innipment Failure (Explain) 2-Manual Scram.

Entrs Sheets for Licensee n Mainter.ance of Test

  • Even't Repin (LER) Fde (NUREG.

J Automatic Scram.

C Refueling 4 Other (Explain) 0161)

D Reputatory Resiriction E-Operator Training & License Examination 5 F-Adnunistrative Exhibit ! Jame Sourec G Operational Error (Eiplain)

Il Other (Explain)

(9/77) .

6

,