Corrected Monthly Operating Rept for Aug 1982
ML20028A059
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 09/02/1982
From: Norris H
CAROLINA POWER & LIGHT CO.
To:
Shared Package
ML20028A055 List:
References
NUDOCS 8211160357
Download: ML20028A059 (2)


Text

,

OPERATING DATA. REPORT DOCKET NO:

50-261 DATE:

820902 COMPLETED BY:

H. Ray Norris TELEP110NE:

(803) 383-4524 OPERATING STATUS Notes:

1. Unit Name:

H. B. Robinson Unit No. 2 There are presently 157 spent

2. Reporting Period: 820801.0000/820831.2400 fuel assemblies in the ' pent s
3. Licensed Thermal Power (MWt):

2300 fuel pool.

4. Nameplate Ra. ting (Gross tale):

739

5. Design Electrical Rating (Net }Me):700
6. tbximum Dependable Capacity (Gross FMe):

700

7. Maximum Dependable Capacity (Net FMe):

665

8. If Changes Occur in Capacity Ratings (Item Number 3 through 7) Since Last Report, Give Reasons:

No change

9. Power Level to Which Restricted, If Any (Not Mile):

1955 MWT Reactor Power

10. Reasons For Restrictions, If Any: Although the Unit is not restricted by any outside agency, the power level is presently reduced due to steam generator considerations.

This Month' Yr.-to-Date Cumulative

11. Hours in Reporting Period 744 5,831 100,757
12. Number of Hours Reactor Was Critical 304.73 1,671.83 74,017.25
13. Reactor Reserve Shutdown llours 0

0 1.085.30

14. Hours Generator On-Line 215.10 1,582.20 72.137.51

.15. Unit Reserve Shutdowa Hours 0

0 23.20

16. Gross Thermal Energy Generated (IMI)
  • 245157
  • 2746467

'*145841841

17. Gross Electrical Energy Generated (FMH) 72.952

.871.282 46.'949.252

18. Net Electrical Energy Generated (FMH)
  • 54837
  • 788696
  • 44408947
19. Unit Service Factor 28.91 27.13 7 L. 59 '
20. Unit Availability Factor 28.91 27.13 71.61
21. Unit Capacity Factor (Using MDC N'et) 11.08 20.33 66.27
22. Unit Capacity Factor (Using DER Net) 10.53

_19.32 62.96

23. Unit Forced Outage Rate
  • 40.37
  • 8.43
  • 14.46
24. Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):

l, Type-2, 2/26/83, Four week steam generator inspection outage.

25 If Chut Down At End of Report Period, Estimated Date of Startup:

On line

26. Units In Test Status (Prior to Commercial Operation):

Forecast Achieved INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION 8211160357 821110 PDR ADOCK 05000261 R

PDR

  • Corrected on 821102 (9/77)

Cg

J 50-261 DOCKET NO.

H. B. Robinson UNIT SHUTDOWNS AND POWER REDUCTIONS UNIT N AME 820902 DATE COMPLETED BY H. Ray Norris REPORT MONTil Augus t TELEPHONE (803) 383-4524 i

e.

E E

.] ?

3

$Y5 Lisensec 5 r, "g t Cause & Correesive -

r v

No.

Date y,

3g s

ji5 Event g,7 9-3 Action to mO E'

Prevent Recurrence

~ 5 =!!

Report

  • E A

H s

v

.e 5

ZZ ZZZZZZ Shuutdown for maintenance / refueling 2-01 820801 S

350.08 B/C 3

outage HB HTEXCH While bringing the unit off line 08-02 82'0815 F

131.59 B

3 due to, faulty MW* indication, the unit tripped.

Cause-low icvel S/G resulting in low level trip.

HH VALVEX High level S/G. Cause-trip due to 08-03 820821 F

6.00 A

3 feedwater reg. valve malfunction.

HH VALVEX High level S/G. Cause-trip due to 08-04 820821 F

8.01 A

3 feedwate'r reg. valve malfunction.

HA TURBIN Required turbine over speed trip 08-05 820822

  • S 32.27 B

1 test following refueling /maintenanc a outage.

~

HA TURBIN Required turbine test-adjusted over-

~

08-06 820825

'

  • S.,

0.23 B y

speed trip.

4 3

I

. 2 Method:

Exhibit G Instructions for Preparation of Data F: For(cd Reaw n; I. Manual S: Scheduled A l'iluipment Failure (Explain) 2-Manual Scram.

Entr> Sheets for Licensee 3 Autmnatic Scram.

Event Repor (LER) File (NUREG-n Maintenance of Test C. Refueling 4-Other'(Explain) 0161)

D Regulatory Restriction 1:.-Operator Training & License Examination 5

F-Admmisirative Exhibit ! Same Sourec G. Operational Error (Explain)

(9/77)

Il-Other (Explain) o Corrected on 821102 t

........ - -.