Forwards Insp Rept 50-285/87-02 on 870101-31 & Notices of Violation & Deviation.Status of Previously Identified Insp Findings Provided in Rept
ML20211Q225
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 02/19/1987
From: Gagliardo J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Andrews R
OMAHA PUBLIC POWER DISTRICT
Shared Package
ML20211Q231 List:
References
NUDOCS 8703030041
Download: ML20211Q225 (2)


See also: IR 05000285/1987002

Text

?

, .

FEB 191937

In Reply Refer To:

Docket: 50-285/87-02

Omaha Public Power District

ATTN: R. L. Andrews, Division Manager-

Nuclear Production

1623 Harney Street

Omaha, Nebraska 68102

Gentlemen:

This refers to the inspection conducted by Mr. P. H. Harrell of this office

during the period January 1-31 1987, of activities authorized by NRC Operating

LicenseDPR-40fortheFortCaihounStation,andtothediscussionofour

findings with you and other members of your staff at the conclusion of the

inspection.

Areas examined during the inspection included operational safety verifications,

maintenance, surveillance, plant tours, safety-related system walkdowns,

security observations, inoffice review of periodic and special reports,

followu) on previously identified items, followu) on a licensee event report,

10 CFR ) art 21 program review, and followup on IE Information Notice 86-106.

Within these areas, the inspection consisted of selective examination of

procedures and re)resentative records, interviews with personnel, and

observations by tie NRC inspector. The inspection findings are documented in

the enclosed inspection report.

During this inspection, it was found that certain of your activities were in

violation of NRC requirements. Consequently, you are required to respond to

,

in accordance with the provisions of

theseviolations,inwriting,ulesofPractice,"Part2,

Section 2.201 of the NRC's R Title 10,Codeof

Federal Regulations. Your response should be based on the specifics contained

in the Notice of Violation enclosed with this letter.

Also during this inspection, it was found that certain of your activities

appeared to deviate from a commitment made to the NRC. This item and reference

to the commitment is identified in the enclosed Notice of Deviation. You are

requested to respond to this deviation in writing. Your response should be

based on the specifics contained in the Notice of Deviation enclosed with this

letter.

We have also examined actions you have taken with regard to previously

identified inspection findings. The status of these items is identified in

paragraph 2 of the enclosed inspection report.

The responses directed by this letter and the accompanying Notices are not

subject to the clearance procedures of the Office of Management and Budget as

required by the Paperwork Reduction Act of 1980, PL 96-511.

I PI 7Yi C:RPB y C:RPBgd

'

PHarrell/tw RMul[likin DRHun M JEG'aligardo

t/n/87 1 / 13/87 p./13/87 p // / /87 g\

0703030041 870219

DR ADOCK 0500 5

Q 1

.

e, ..

.

Omaha Public Power District -2-

Should you have any questions concerning this inspection, we will be pleased to

discuss them with you.

Sincerely,

't.-:ce rena t>3

R. E. H!.', t/*

\

J.- E. Gagliardo, Chief

ReactorProjectsBranch

Enclosures:

1. Appendix A - Notice of Violation

2. Appendix B - N:tice of Deviation

3. Appendix C - NRC Inspection Report

.50-285/87-02

cc w/ enclosures:

W. G. Gates, Manager

P. O. Box 399

Fort Calhoun, Nebraska 68023

Harry H. Voigt, Esq.

LeBoeuf, Lamb, Leiby & MacRae

1333 New Ham) shire Avenue, NW

Washington, )C 20036

Kansas Radiation Control Program Director

Nebraska Radiation Control' Program Director

bec to DMB (IE01)

'

'

bcc distrib. by RIV:

  • RPB * Resident Inspector R. D. Martin, RA
  • R&SPB *SectionChief(RPB/B) *RSB
  • RIV File DRS&P * MIS System
  • RSTS Operator *D. Weiss, LFMB (AR-2015) *ProjectInspector(RPB/B)

'

  • w/766

l

!

i

i- _ _ _