ML20202E717

From kanterella
Revision as of 21:32, 1 January 2021 by StriderTol (talk | contribs) (StriderTol Bot change)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Discusses Lazarus 860402 Telcon Approving Util 860331 Request to Postpone Emergency Preparedness Implementation Appraisal Until Wk of 860519.Schedule Will Make 860529 Fuel Load Date Impossible
ML20202E717
Person / Time
Site: Nine Mile Point Constellation icon.png
Issue date: 04/04/1986
From: Bellamy R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Hooten B
NIAGARA MOHAWK POWER CORP.
References
NUDOCS 8604140036
Download: ML20202E717 (2)


Text

y

(

APR f 41986 Docket No. 50-410 Niagara Mohawk Power Corporation ATTN: Mr. B. G. Hooten Executive Director Nuclear Operations 300 Erie Boulevard, West Syracuse, New York 13202 Gentlemen:

Subject:

Schedule for Performance of the Emergency Preparedness Implementation Appraisal (EPIA)

On March 31, 1986, Messrs. Rademacher and Chwalek of your staff contacted

~Mr. Lazarus of this office to requ.st that the EPIA scheduled to be performed at Nine Mile Point Unit 2 beginning April 14, 1986, be postponed until May 19, 1986. The request was based upon their judgement that sufficient progress had

-not been made in several areas which would make it prudent to postpone the appraisal.

In a telephone conversation with Mr. Rademacher on April 2,1986, Mr. Lazarus agreed to postpone the appraisal until the week of May 19, 1986. Please be advised that this schedule will make it very difficult, if not impossible for -

the staff to support your projected May 29, 1986 fuel load date, because of the time required to evaluate any open issues following the appraisal and coordinate acceptable resolution of those issues with NRC licensing.

Sincerely.

OrigI m i si m e:3 97, Ronald R. Bellamy, Chief tseue190036 860404 e Emergency Preparedness and PDR ADOCK 05000410 Radiological Protection Branch F PDR Division of Radiation Safety and Safeguards cc:

Connor & Wetterhahn John W. Keib, Esquire D. Quamme, NMP-2 Project Director J. A. Perry, Vice President of QA C. Beckham, NMPC QA Manager T. J. Perkins, General Superintendent R. B. Abbott, Station Superintendent Department of Public Service, State of New York PublicDocumentRoom(PDR)

Local Public Document Room (LPDR)

Nuclear Safety Information Center (NSIC)

NRC Resident Inspector State of New York 0FFICIAL RECORD COPY 56M

F b

Niagara Mohawk Power Corporation 2 bec:

Region I Docket Room (with concurrences)

DRP Section Chief Region I, SLO S. Collins J. Linville S. Hudson F. Kantor, IE/HQ M. Haughey, NRR RI:DRSS RI:DRSS RI DRP RI:CRSS s Lazarus Harpster ,\3 Collins Bellamy N 4/ td86 4/ /86 (4/f/86 4/9/86 0FFICIAL RECORD COPY e_________________