Summarizes Status of Installation of Whip Restraints & Jet Barriers,In Support of Request for Alternate Pipe Break Design Considerations
ML20101G801
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 12/21/1984
From: Foster D
GEORGIA POWER CO.
To: Adensam E
Office of Nuclear Reactor Regulation
References
GN-501, NUDOCS 8412280018
Download: ML20101G801 (2)


Text

e

. Georgia Power Company Route 2. Box 299A Waynesboro, Georgia 30830

  • Telephone 404 554-9961. Ext 3360 404 724 8114. Ext. 3360 D. O. Foster Georgia Power Gere 1ar. age IM sO#ern Mit statern Vogt!e Project December 21, 1984 Director of Nuclear Reactor Regulation Filei X7NO.06 Attention: Ms. Elinor G. Adensam, Chief Log: GN-501 Licensing Branch #4 Division of Licensing U.S. Nuclear Regulatory Commission Washington, D.C. 20555 NRC DOCKET NUMBERS 50-424 AND 50-425 CONSTRUCTION PERMIT NUMBERS CPPR-108 AND CPPR-109 V0GTLE ELECTRIC GENERATING PLANT - UNITS 1 AND 2 ALTERNATE PIPE BREAK DESIGN CONSIDERATIONS

Dear Mr. Denton:

Io support your review of the GPC request to eliminate from design con-sideration the dynamic effects of the postulated pipe breaks in the reactor coolant system main loop piping, we have prepared a summary of the status of the installation of the whip restraints and jet barriers associated with those breaks. The following identifies the physical status of the restraints, and the construction impacts associated with the completion of the installation, and defines the status of the jet impingement barriers.

RCS PIPE WHIP RESTRAINTS INSTALLATION STATUS (Unit 1) e Crossover Leg Horizontal Run Restraints (8 total)

The support structure has been installed in each loop. The bearing surface and its attachments to the RCS piping have not been installed.

Installation at this stage of construction will require restraint portions not yet installed to be cut, installed, and rewelded.

e Crossover Leg Vertical Run Restraints (4 total)

Only the embeds have been installed.

e Steam Generator Inlet (Hot Leg) Restraints (4 total)

Only the embeds have been installed. Several installation inter-ferences exist which may have to be relocated to allow restraint installation.

8412280018 841221

--paa '

slo 7 ,l,

Director of Nuclear Reactor Regulation File: 17N0.06 December 21, 1984 -Log: GN-501 Page 2 e Hot Leg Primary Shield Wall Restraints (4 total)

Installation complete except for bearing bars.

e Cold Leg Primary Shield Wall Restraints (4 total)

Installation complete except for bearing bars.

RCS PIPE WHIP RESTRAINTS INSTALLATION STATUS (Unit 2) e Crossover Leg Horizontal Run Restraints (8 total)

Same as Unit 1.

e All Other RCS Restraints (16 total)

Only the embeds have been installed. Interferences identified for Unit 1 are also applicable to Unit 2.

RCS JET IMPINGEMENT BARRIERS INSTALLATION STATUS (Units 1 and 2)

Approximately 180 essential impactees have been identified for the 28 postulated RCS breaks. Jet loads on these targets have been calculated, but not yet evaluated. No barriers have been identified or installed to date. Expected number of barriers is estimated to be 15 to 25.

If you have any questions on the above information, please do not hesitate to contact us.

Yours truly, D. . Fo er i

DOF/ JAB /sw xc: R. A. Thomas J. A. Bailey G. F. Trowbridge, Esquire J. E. Joiner, Esquire C. A. Stangler