Forwards Corrected Pages to VEGP-2 ISI Summary Rept for Spring 1998 Maint/Refueling Outage. Change Bar in Margin of Affected Pages Denotes Changes to Rept
ML20199F798
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 01/13/1999
From: Beasley J
SOUTHERN NUCLEAR OPERATING CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20199F802 List:
References
LCV-1222-A, NUDOCS 9901220062
Download: ML20199F798 (2)


Text

_

J. Bernie Beasley, Jr., PE Southern Nuclear Vice President Operating Company. Inc.

Vogtle Project 40 invemess Center Parkway P.O. Box 1295

' Birmingham, Alabama 35201 Tel 205.992.7110 Fax 205.992 0403 SOUTHERN COMPANY Energy to Serve YourWorld" January 13,~1999 LCV-1222-A Docket No.: 50-425 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk

- Washington, D. C.

20555 Ladies and Gentlemen:

VOGTLE ELECTRIC GENERATING PLANT CORRECTION TO INSERVICE INSPECTION

SUMMARY

REPORT By letter LCV-1222 dated July 13,1998, the " Owner's Report for Inservice Inspection (ASME Form NIS-1)" was submitted to the NRC for inservice inspection (ISI) activities conducted during the Spring 1998 maintenance / refueling outage at Vogtle Electric Generating Plant, Unit 2 (VEGP-2). That report constitutes the ISI summary report submitted to the NRC in accordance with the requirements ofIWA-6000 of ASME Section XI.

While preparing a revision to the ISI program document for the VEGP-2 first ten-year ISI interval, several minor errors were observed in the above referenced ISI summary report and require correction. Specifically, two Class I welds listed in the summary tables included in the report did not contain a notation that limitations were experienced during their volumetric (ultrasonic) examination and required relief. Those particular errors resulted in the number of Class 1 welds having examination coverage limitations being incorrectly identified in the text of the report. Minor editorial changes were also identified as being required in the text to ensure consistency with the summary tables.

None of the changes required to correct the subject report affect the results of the inservice inspection activities or the health and safety of the public. Relief, where necessary, has been requested under separate cover in our letter LCV-1280 dated November 30,1998.

Enclosed are the corrected pages to the VEGP-2 ISI summary report for our Spring 1998 maintenance / refueling outage. A change bar in the margin of the affected pages denotes changes to the report.

L l

1eM O@/

f 9901220062 990113 PDR ADOCK 05000425 G

PDR

U. S. Nuclear Regulatory Commission LCVr1222-A.

Page Two Should there be any questions in this regard, please contact this office.

Sincerely, ff' j

W J. B. Beasley, Jr JBB/JAE/jae,

Enclosure:

Corrected pages for VEGP-2 ISI Summary Report for Spring 1998 Maintenance / Refueling Outage (Pages 2-6,2-7,6-6,6-8, and 6-9) xc: Hartford Steam Boiler Inspection and Insurance Company Mr. F. E. Bellais, Jr. (w/ enclosure)

Southern Nuclear Operating Company Mr. W. L. Burmeister (w/o enclosure)

Mr. J. T. Gasser (w/o enclosure) l Mr. M. Sheibani (w/ enclosure)

SNC Document Management (w/ enclosure)

U. S. Nuclear Regulatory Commission Mr. D. H. Jaffe, Senior Project Manager, NRR (w/ enclosure)

I Mr. L. A. Reyes, Regional Administrator (w/cnclosure)

Mr. J. Zeiler, Senior Resident Inspector, Vogtle (w/ enclosure) s P-

--.r.

.