Submits Revised Response to RAI Re Licensee 980713 Proposed Amend to Ts,Eliminating Periodic Response Time Testing Requirements on Selected Sensors & Protection Channels. Corrected Copy of Table,Encl
ML20199F770
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 01/13/1999
From: Beasley J
SOUTHERN NUCLEAR OPERATING CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
LCV-1175-B, NUDOCS 9901220050
Download: ML20199F770 (6)


Text

. - - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _

, *. J. Barais Beasley. Jr., P.E.

Southern Nucleer Vice President Operating Company,Inc.

Vogtle Project 40 inverness Center Parkway P.O. Box 1295 Birmingham. Alabama 35201 Tel 205.9923110 Fax 205 992.0403 SOUTHERN COMPANY Energy to Serve Your World" January 13, 1999 LCV-Il75-B Docket Nos. 50-424 50-425 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk

' Washington, D. C. 20555 Ladies and Gentlemen:

VOGTLE ELECTRIC GENERATING PLANT REQUEST TO REVISE TECHNICAL SPECIFICATIONS REVISED RESPONCE TO REQUEST FOR ADDITIONAL INFORMATION By letter dated December 16,1998, SNC responded to a request for additional information (RAl) regarding our' submittal of July 13,1998, LCV-1175. Our submittal of July 13,1998, proposed to revise the Vogtle Electric Generating Plant Unit 1 and Unit 2 Technical Specfications to eliminate periodic response time testing requirements on selected sensors and protection channels. Our response of December 16,1998, to the RAI, contained a typographical error. The table entitled " Process / Function / Reactor Trip / Allocation / Tabic" reported a time of 145 ms for the OTDT (Vary Precs) 7300/NIS String. Instead of 145 ms, the time should have been shown as 140 ms. A corrected copy of the table is attached to this letter. We apologize for any inconvenience that this error may have caused.

Sincerely, J A I B. easl y,J JBB/NJS

Enclosure:

Corrected Table I

\

xc: Southern Nuclear Operating Company

\

Mr. J. T. Gasser Mr. M. Sheibani h i k

NORMS

_j . U Y7 9901220050 990113 PDR ADOCK 05000424 p PDR o

L. . . _ _ _ _ . . _ _ _ _ _ _ _ _ _

U. S. Nuclear Regulatory Commission I LCV-1175-B l Page 2 j l

U. S. Nuclear Regulatory Cornmission  ;

Mr. L. A. Reyes, Regional Administrator i Mr. D.11. Jaffe, Senior Project Manager, NRR '

Mr. John Zeiler, Senior Resident Inspector, Vogtle ,

State of Georgia Mr. L. C. Barrett, Commissioner, Department of Natural Resources i I

i f

l i

l 1

1 1

)

k

. , s- . . e s- -=

y . -

~

' VOGTLE UNITS 1 AND 2 .

PROCESS / FUNCTION / REACTOR TRIP / ALLOCATION / TABLE FUNCTION SENSOR TIME 7300/NIS STRING TIME SSPS RELAYS TIME PZR, PRESS Ill , Tobar 32PG 200ms NLP+NAL 65ms Input 20ms j Veritrak 76P11 200ms j Rosemount I154Sil9 200ms PZR. PRESS. LO Tobar 32PG 200ms NLP+NAL 65ms input 20ms Veritrak 76Pil 200ms i Roserr:ount i154Sil9 200ms j

~50 LFUFL LO-LO T*foar 32DP 400ms NLP+NAL 65ms input 20ms Veritrak 76DP 400ms  !

~~Rosemount i154Dil5 200ms ,

t F

V RCS FLOW LO Tohar 32DP 400ms NLP+NAL- 65ms Input 20ms  ;

Veritrak 76DP 400ms Rosemount 115311B5 200ms r

OPDT (Vary Tavg) Weed N9004E-2B (Note 1) NRA+NSA+NSA+NSA+NSA+NAL 368ms Input 20ms  ;

OPDT(Vary DeltaT) Weed N9004E-2B (Note 1) NRA+NSA+NSA+ NAL 293ms input 20ms OTDT(Vary Tavg) Weed N9004E-2B (Note 1) NRA+NSA+NSA+NSA+NAL 330.5ms Input 20ms [

i OTDF(Vary DeltaT) Weed N9004E-2B (Note 1) NRA+NSA+NSA+ NAL 293ms input 20ms  !

OTDT (Vary Press) Tobar 32PG 200ms NLP+NSA+NSA+NAL 140ms Input 20ms Veritrak 76Pil 200ms y Rosemount i154Si19 200ms OTDT(Vary Flux) Detectors Exempt N/A NIS (Ims) + NSA +NCil+NSA+NAL 148.5ms Input 20ms  ;

e RCP VOLTAGU LO GE NGV/ SAM (Note 1) N/A N/A Input 20ms  ;

i RCP FREQ. LO ABB (Note 1) N/A N/A Input 20ms j I

NIS LEVEL ill Detectors Exempt N/A NIS FMEA 65ms Input 20ms -

I i

- _ ~ - _ - . _--_ . _ _ - . . . _ _ _ . _ _ _ _ - _ _ _ _ - _ _ - - _ _ . - - _ - - - . - - . - _ _ _ _ _ _ - _ _ _ _ _ _ - - - - _ _ _ . - - -

VOGTLE UNITS 1 AND 2 PROCESS / FUNCTION / REACTOR TRIP / ALLOCATION / TABLE / (Continued)

FUNCTION SENSOR TIME 7300/NIS STRING TIME SSPS RELAYS TIME NIS RATE 111 Detectors Exempt N/A NIS FMEA 200ms Input 20ms CONTAINMENT Barton 764/351 - 1.0sec NLP+NAL 65ms input 20ms PRESS. REACTOR TRIP FROM (SI)

STEAMLINE PRFSS Tobar 3&'A 200ms NLP+NAL 65ms input 20ms LO REACTOR TRIP veritrak 76PG 200ms FROM (SI) Ros mount i154S119 200ms Rosemount i153GB9 200ms _3_

f (Note 1) Allocated sensor times not used for these variables. These components will continue to be tested as required.

Allocated sensor times are derived from method (3) section (9) WCAP-13632 rev. 2 (Vendor Engineering Specifications). Tobar, Veritrak, and Barton times were provided on Table 9-1. Rosemount times are from Rosemount manuals 4302 and 4631. The Rosemount response time specifications may also be found in NUREG/CR-5383. Transmitter FMEAs are based upon EPRI report NP-7243 rev 1.

Values for 7300 cards are from tables 4-7 throug5 4-12 of WCAP-14036 rev.1. Cards inst:lled are 4NCil,4NRA,6NLP,4NSA, and 9NAL or older artwork levels. NIS components installed are: Summing and Level Amp (3359C48G01), Isolatioa Amp (6065D75G01), Rate Circuit Assy (3359C41G01), and Bistable Relay Driver Assy (3359C39G01). These were evaluated per NIS FMEA schematic diagram 6t65D99.

SSPS Input and Master iciays are Potter & Jrur .deld Kil series relays. SSPS Slave relays are Potter & Brumfield MDR relays. Values are tabulated from section 4.8 Westinghouse SSPS FMEA.

VOGTLE UNITS 1 AND 2 PROCESS / FUNCTION / ENGINEERED SAFETY FEATURE / ALLOCATION / TABLE FUNCTION SENSOR TIME 7300/NIS STRING TIME SSPS RELAYS TIME CONT. PRESS 111-1 Barton 764/351 1.0sec NLP+NAL 65ms Input + Master + Slave 88ms CONT. PRESS 111-2 Barton 764/351 Losec NLP+NAL 65ms input , Master + Slave fi8ms CONT. PRESS 111-3 Barton 764/351 1.0sec NLP+NAL 65ms L,put + Master + Slave- 83ms~

STEAM LINE PRESS Tobar 32PA 200ms N1.P+NAL 65ms igu + isiaster + Slave 88ms LO Veritrak 76PG 200ms Rosemount 1154Sil9 200ms Rosemount 1153GB9 200ms STEAM LINE PRESS Tobar 32PA 200ms NLP+NAL 65ms input + Master + Slave 88ms til NEG RATE Veritrak 76PG 200ms Rosemour ? I154S119 200ms Rosemount 1153GB9 200ms PZR PRESS LO SI Tobar 32PG 200ms NLP+NAL 65ms Input + Master + Slave 88ms Veritrak 76PII 200ms Rosemount i154Sil 9 200ms RWST LEVEL 1.0-LO Tobar 32DP 400ms NLP&NAL 65ms Input + Master + Slave 88ms Veritrak 76DP 400ms Rosemount 1153DB5 200ms SG LEVEL LO-LO Tobar 32DP 400ms NLP+NAL __

65ms input

  • Master + Slave 88ms Veritrak 76DP 400ms Rosemount i154Dil5 200ms SG LEVEL 111-111 Tobar 32DP 400ms NLP+NAL 65ms Input + Master + S!af 88ms Veritrak 76DP 400ms Rosemount il54Dil5 200ms

..J.-:

VOGTLE UNITS I AND 2 A PROCESS / FUNCTION / ENGINEEMED SAFETY FEATURE / ALLOCATION / TABLE 3~

FUNCTION SENSOR TIME 7300/NIS STRING UMP SSPS RELAYS TIMS CONTAINMENT Westinghouse (Note 1) N/A N/A Input + Master + Slave 88ms.

AREA RADIATION LEVEL 111 2

CONTAINMENT Westinghouse (Note 1) N/A N/A input + Master + Slave + Slave 124ms VENT RADIATION LEVEL 111 e+M-(Note 1) Allocated sensor times not used for these variables. These components will continue to be tested as required.

Allocated sensor times are derived from method (3) section (9) WCAP-13632 rev. 2 (Vendor Engineering Specifications). Tobar, Veritrak, and Barton times were provided on Table 9-1. Rosemount times are from Rosemount manuals 4302 and 4631. The Rosemount response time specifications may also be found in NUREG/CR-5383. Transmitter FMEAs are based upon EPRI report NP-7243 rev 1.

Values for 7300 cards are from tables 4-7 through 4-12 of WCAP-14036 rev.1. Cards installed are 4NCll,4NRA,6NLP,4NSA, and 9NAL or older artvark levels.