ML20106C356: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot insert)
 
(StriderTol Bot change)
 
Line 2: Line 2:
| number = ML20106C356
| number = ML20106C356
| issue date = 09/12/1984
| issue date = 09/12/1984
| title = Suppls Response to NRC 840217 Ltr Re Violations Noted in Insp Rept 50-438/84-01.Corrective Actions:Environ Qualified Motor Starters Will Be Installed by 850330 & QC Procedure 3.4 Will Be Revised & Issued by 841014
| title = Suppls Response to NRC Re Violations Noted in Insp Rept 50-438/84-01.Corrective Actions:Environ Qualified Motor Starters Will Be Installed by 850330 & QC Procedure 3.4 Will Be Revised & Issued by 841014
| author name = Mills L
| author name = Mills L
| author affiliation = TENNESSEE VALLEY AUTHORITY
| author affiliation = TENNESSEE VALLEY AUTHORITY
Line 11: Line 11:
| contact person =  
| contact person =  
| document report number = NUDOCS 8410240128
| document report number = NUDOCS 8410240128
| title reference date = 02-17-1984
| package number = ML20106C350
| package number = ML20106C350
| document type = CORRESPONDENCE-LETTERS, INCOMING CORRESPONDENCE, UTILITY TO NRC
| document type = CORRESPONDENCE-LETTERS, INCOMING CORRESPONDENCE, UTILITY TO NRC
Line 26: Line 27:
==Dear Mr. O'Reilly:==
==Dear Mr. O'Reilly:==


BELLEFONTE NUCLEAR PLANT UNIT 1 - SUPPLEMENTAL RESPONSE TO VIOLATION 50-438/84-01 FAILURE TO PREVENT PRACTICES TNAT CAUSE DETERIORATION OF AN ILECTRICAL PANEL COMPONENT TVA responded to R. C. Lewis' letter dated February 17, 1984, report numbers 50-438/84-01, 50-439/84-01 concerning activities at the Bellefonte Nuclear Plant which appeared to have been in violation of NRC regulations by letter dated March 14, 1984. Below is our supplemental response to the
BELLEFONTE NUCLEAR PLANT UNIT 1 - SUPPLEMENTAL RESPONSE TO VIOLATION 50-438/84-01 FAILURE TO PREVENT PRACTICES TNAT CAUSE DETERIORATION OF AN ILECTRICAL PANEL COMPONENT TVA responded to R. C. Lewis' {{letter dated|date=February 17, 1984|text=letter dated February 17, 1984}}, report numbers 50-438/84-01, 50-439/84-01 concerning activities at the Bellefonte Nuclear Plant which appeared to have been in violation of NRC regulations by {{letter dated|date=March 14, 1984|text=letter dated March 14, 1984}}. Below is our supplemental response to the
             ' citation.
             ' citation.
As discussed with NRC-0IE Inspector P. E. Fredrickson on August 29, 1984, the date of September 1,1984, for completion of corrective actions indicated in our final report on this matter would not be met. TVA found it impossible to obtain any environmentally qualified motor starters. An exact replacement will now be installed by March 30, 1985, while the qualification problem is being separately reported on under nonconformance report (NCR) BLN EEB 8413.
As discussed with NRC-0IE Inspector P. E. Fredrickson on August 29, 1984, the date of September 1,1984, for completion of corrective actions indicated in our final report on this matter would not be met. TVA found it impossible to obtain any environmentally qualified motor starters. An exact replacement will now be installed by March 30, 1985, while the qualification problem is being separately reported on under nonconformance report (NCR) BLN EEB 8413.

Latest revision as of 19:29, 23 September 2022

Suppls Response to NRC Re Violations Noted in Insp Rept 50-438/84-01.Corrective Actions:Environ Qualified Motor Starters Will Be Installed by 850330 & QC Procedure 3.4 Will Be Revised & Issued by 841014
ML20106C356
Person / Time
Site: Bellefonte Tennessee Valley Authority icon.png
Issue date: 09/12/1984
From: Mills L
TENNESSEE VALLEY AUTHORITY
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML20106C350 List:
References
NUDOCS 8410240128
Download: ML20106C356 (1)


Text

_ _ _ _ . _ . . _ _ _ . _- __- - _ __ -_______ _ _

a - j,, e TENNESSEE VALLEY ' AUTHORITY )

i f6F6t."stnat Me"e?Y!#'fi q

g4 3[P l8 P 3 : Mta=b.c 12,1984 -

U.S. Nuclear Regulatory Cosmaission Region II

. Attn: Mr. James P. O'Reilly,- Regional Administrator 101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30323

Dear Mr. O'Reilly:

BELLEFONTE NUCLEAR PLANT UNIT 1 - SUPPLEMENTAL RESPONSE TO VIOLATION 50-438/84-01 FAILURE TO PREVENT PRACTICES TNAT CAUSE DETERIORATION OF AN ILECTRICAL PANEL COMPONENT TVA responded to R. C. Lewis' letter dated February 17, 1984, report numbers 50-438/84-01, 50-439/84-01 concerning activities at the Bellefonte Nuclear Plant which appeared to have been in violation of NRC regulations by letter dated March 14, 1984. Below is our supplemental response to the

' citation.

As discussed with NRC-0IE Inspector P. E. Fredrickson on August 29, 1984, the date of September 1,1984, for completion of corrective actions indicated in our final report on this matter would not be met. TVA found it impossible to obtain any environmentally qualified motor starters. An exact replacement will now be installed by March 30, 1985, while the qualification problem is being separately reported on under nonconformance report (NCR) BLN EEB 8413.

A second commitment to revise Bellefonte Quality Control Procedure (QCP) 3.4 has also been delayed. Because of the size of this QCP, TVA has broken it into three separate QCPs (3 4, 3.34, and 3 33) which are expected to be issued by October 14, 1984.

If you have any questions concerning this matter, please get in touch with R. H. Shell at FTS 858-2688.

Very truly yours, TENNESSEE VALLEY AUTHORITY L. M. Mills, Manager Nuclear Licensing cet Mr. Richard C. DeYoung, Dirtictor Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission Washington, D.C. 20555 h0g[oh 0