ML20027A949

From kanterella
Jump to navigation Jump to search
Responds to NRC 820712 Ltr Re Violations Noted in IE Insp Repts 50-424/82-13 & 50-425/82-13.Corrective Actions: Contractor Craftsmen Assigned to Perform Daily Insp of Chemical & Vol Control Sys Charging Pumps
ML20027A949
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 08/11/1982
From: Foster D
GEORGIA POWER CO.
To: Robert Lewis
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML20027A941 List:
References
GN-188, NUDOCS 8209160214
Download: ML20027A949 (2)


Text

_ _ _ _ _ _ _ _ _ _ _ _ _ -

i i *. **

'e f.:,,

u *

., , f-l Georgia Power Company

' Post Offce Box 4545 k.,

Atlanta, Georgia 30302

  • ff,<,

' /8 p Telephone 404 522-6000

/& VOgtle Project Southern Company Services, Inc.

Post Office Box 2625 Birmingham. Alabama 35202 Telephone 205 870-6011 August 11, 1982 United States Nuclear Regulatory Commission Office of Inspection and Enforcement Region II - Suite 3100 101 Marietta Street File: X7BG10 Atlanta, Georgia 30303 Log: GN-188

Reference:

50-424/82-13 50-425/82-13 Attention: R. C. Lewis Gentlemen:

The Georgia Power Company wishes to submit the following information concerning the violations discussed in your inspection report 50-424/82-13 and 50-425/82-13.

We concur with the finding identified concerning failure to take effective corrective action. The reason for the violation was ineffective controls because we were in the process of implementing a new housekeeping crocedure.

Contractor craftsmen have been assigned to perform a daily inspection of the chemical and volume control system (CVCS) charging pumps for com-pliance to storage requirements. In addition, to better control access to the rooms containing these pumps, the Unit 2 rooms will be locked until piping installation starts and the Unit I rooms will be locked after work in this area is complete.

The new housekeeping procedure has been fully implemented and requires Quality Control inspectors to inspect storage areas at least monthly to verify:

1) area cleanliness and access control,
2) condition of coatings and preservatives,
3) protective covers and seals maintained,
4) identification and markings, and
5) inspection for physical damage.

In addition to the above, weekly and spot / random walk-throughs will help avoid future violations in this area.

8209160214 920820 PDR ADOCK 05000424 G FDR

____-______ ________ ]

R. C. Lewis i' *[. #

50-424/82-13; 50-425/82-13 August 11, 1982 Page 2 Full compliance was achieved on June 1,1982.

This response contains no proprietary infonnation and may be placed in the NRC Public Document Room upon receipt.

Yours truly a

D. O. Foster Project General Manager D0F/CWH/tlp xc: U. S. Nuclear Regulatory Commission Attn: Victor J. Stello, Jr., Director Office of Inspection and Enforcement Washington, D.C. 20555 R. J. Kelly R. E. Conway G. F. Head J. T. Beckham, Jr.

J. H. Boykin D. E. Dutton R. H. Pinson D. L. McCrary R. A. Thomas J. A. Bailey

0. Batum H. H. Gregory, III E. D. Groover L. T. Gucwa M. Malcom C. R. Miles, Jr.

M. Manry P. D. Rice R. W. Staffa J. L. Vota W. F. Sanders

,