LR-N02-0418, November 2002 Monthly Operating Report for Hope Creek

From kanterella
Jump to navigation Jump to search
November 2002 Monthly Operating Report for Hope Creek
ML023600202
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 12/13/2002
From: Waldinger L
Public Service Enterprise Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
LR-N02-0418
Download: ML023600202 (3)


Text

PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 DF1Nýý dT%

O PSEG NuclearLLC LR U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:

MONTHLY OPERATING REPORT HOPE CREEK GENERATING STATION DOCKET NO. 50-354 In compliance with Section 6.9, Reporting Requirements for the Hope Creek Technical Specifications, the operating statistics for November 2002 are being forwarded.

Sincerely, Operations Director RAR Attachments C Distribution 95-2168 REV 7/99

A' DOCKET NO.: 50-354 UNIT: Hope Creek DATE: 12/9/02 COMPLETED BY: F. Todd TELEPHONE: (856) 339-1316 Reporting Period November 2002 OPERATING DATA REPORT Design Electrical Rating (MWe-Net) 1083 Maximum Dependable Capacity (MWe-Net) 1049 Month Year-to-aate Louuiamave No. of hours reactor was critical 720 7949 120371 No. of hours generator was on line (service 720 7810 118075 hours)

Unit reserve shutdown hours 0 0 0 Net Electrical Energy (MWH) 771830 8038416 119674024 UNIT SHUTDOWNS NO. DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTIONI F=FORCED (HOURS) (1) SHUTTING COMMENT S=SCHEDULED DOWN THE REACTOR (2)

(1) Reason (2) Method A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Trip/Scram C - Refueling 3 - Automatic Trip/Scram D - Regulatory Restriction 4 - Continuation E - Operator Training/License Examination 5 - Other (Explain)

F - Administrative G - Operational Error (Explain)

H - Other

DOCKET NO.: 50-354 UNIT: Hope Creek DATE: 1219/02 COMPLETED BY: R. Ritzman TELEPHONE: (856) 339-1445 Summary Of Monthly Operating Experience

"* Hope Creek entered the month at approximately 100% power.

"* On November 23, power was reduced to approximately 97% due to an emergency 500KV line outage. Power was then reduced to approximately 81%

due to an "A" Feed Pump Trip. Power was returned to 100% on November 24.

" At the end of the month, Hope Creek completed 156 days of continuous on-line operation.