'V PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 JUL 1 3 2005 LR-N05-0353
@ PSEG ATuclearI IC U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 MONTHLY OPERATING REPORT HOPE CREEK GENERATING STATION DOCKET NO. 50-354 In compliance with Section 6.9, Reporting Requirements for the Hope Creek Technical Specifications, the operating statistics for June 2005 are being forwarded.
Sincerely, Michael J. Massaro Hope Creek Plant Manager Attachments C Distribution 2'q 95-2168 REV. 7199
DOCKET NO.:
UNIT:
DATE:
COMPLETED BY:
TELEPHONE:
50-354 HoDe Creek 7/8/05 K. Hight (856) 339-3887 Reporting Period June 2005 OPERATING DATA REPORT Design Electrical Rating (MWe-Net)
Maximum Dependable Capacity (MWe-Net)
No. of hours reactor was critical No. of hours generator was on line (service hours)
Unit reserve shutdown hours Net Electrical Energy (MWH) 1083 1049 l
Idz__
Month Year-to-date Cumulative 542 3473 138260 481 3142 135222 0
0 0
487381 3203860 136991998 UNIT SHUTDOWNS NO.
DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTION/
F=FORCED (HOURS)
(1)
SHUTTING COMMENT S=SCHEDULED DOWN THE REACTOR (2) 5 6/7/05 F
239 A
2 Drywell unidentified leakage > 5 gpm and 6/17/05 trending up.
4 I
I 4
+
+
(1) Reason (2) Method A - Equipment Failure (Explain)
B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)
H - Other 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)
DOCKET NO.: 50-354 UNIT: HoDe Creek DATE: 7/8/05 COMPLETED BY: R. Ritzman TELEPHONE: (856) 339-1445 Summary Of Monthly Operating Experience
- The unit started the month at 100% power.
- On June 4, power was reduced to 62% for a planned deep shallow rod swap. The unit was returned to 100% on June 6.
- On June 7, the unit was manually scrammed due to increasing unidentified drywell leakage. The unit was returned to service on June 17, reaching approximately 100% power on June 18.
- At the end of the month, Hope Creek completed 13 days of continuous on-line operation.