LR-N03-0392, August 2003 Monthly Operating Report for Hope Creek

From kanterella
Jump to navigation Jump to search
August 2003 Monthly Operating Report for Hope Creek
ML032670971
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 09/12/2003
From: Hutton J
Public Service Enterprise Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
LR-N03-0392
Download: ML032670971 (3)


Text

PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 SEP 1 2 2003 o PSEG NuclearLLC LR-N03-0392 U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:

MONTHLY OPERATING REPORT HOPE CREEK GENERATING STATION DOCKET NO. 50-354 In compliance with Section 6.9, Reporting Requirements for the Hope Creek Technical Specifications, the operating statistics for August 2003 are being forwarded.

Sincerely, KOamesat Dutton

,v perations Director Attachments C Distribution 111.4A 96-2168 REV. 7199

DOCKET NO.: 50-354 UNIT: Hope Creek DATE: 9/9/03 COMPLETED BY: F. Todd TELEPHONE: (856) 339-1316 Reporting Period August 2003 OPERATING DATA REPORT Design Electrical Rating (MWe-Net) 1083 Maximum Dependable Capacity (MWe-Net) 1049 wMonth Tear-to-aate 1umulauve No. of hours reactor was critical 744 4985 126101 No. of hours generator was on line (service 744 4852 123670 hours)

Unit reserve shutdown hours 0 0 0145 Net Electrical Energy (MWH) 781856 14972809 1125451500 UNIT SHUTDOWNS NO. DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTION!

F-FORCED (HOURS) (1) SHUTTING COMMENT S=SCHEDULED DOWN THE

____ _______ ___________ ________ ______ REACTOR (2)

=~~~~~~~~~

(1) Reason (2) Method A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Trip/Scram C - Refueling 3 - Automatic Trip/Scram D - Regulatory Restriction 4- Continuation E - Operator TraininglLicense Examination 5 - Other (Explain)

F - Administrative G - Operational Error (Explain)

H - Other

DOCKET NO.: 50-354 UNIT: Hope Creek DATE: 9/9/03 COMPLETED BY: R. Ritzman TELEPHONE: (856) 339-1445 Summary Of Monthly Operating Experience

  • The unit entered the month at approximately 100% reactor power and operated throughout the month with no significant power reductions.
  • At the end of the month, Hope Creek completed 109 days of continuous on-line operation.