LR-N03-0468, October 2003 Monthly Operating Report for Hope Creek Generating Station

From kanterella
Jump to navigation Jump to search
October 2003 Monthly Operating Report for Hope Creek Generating Station
ML033290307
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 11/17/2003
From: Hutton J
Public Service Enterprise Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
LR-N03-0468
Download: ML033290307 (3)


Text

PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 NOV 17 2003 LR-N03-0468 o PSEG Nuclear LLC U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:

MONTHLY OPERATING REPORT HOPE CREEK GENERATING STATION DOCKET NO. 50-354 In compliance with Section 6.9, Reporting Requirements for the Hope Creek Technical Specifications, the operating statistics for October 2003 are being forwarded.

Sincerely, Hope Creek Plant Manager Attachments C Distribution

" ,

2p

219 95-2168 REV. 7/99

DOCKET NO.: 50-354 UNIT: Hope Creek DATE: 11/11/03 COMPLETED BY: F. Todd TELEPHONE: (856) 339-1316 Reporting Period October 2003 OPERATING DATA REPORT Design Electrical Rating (MWe-Net)

Maximum Dependable Capacity (MWe-Net)

No. of hours reactor was critical No. of hours generator was on line (service hours)

Unit reserve shutdown hours Net Electrical Energy (MWH) 1083 1049 Month Year-to-date Cumulative 686 6187 127302 661 5991 124810 0

0 0

641234 6094536 126573227 UNIT SHUTDOWNS NO.

DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTION/

F=FORCED (HOURS)

(1)

SHUTTING COMMENT S=SCHEDULED DOWN THE REACTOR (2) 6 10/4/03 F

84 Hrs.

A 2

Control Intercept Valve hydraulic oil leak

____ 10/8/03 (1) Reason (2) Method A - Equipment Failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)

H - Other 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)

-Z L..

I V

DOCKET NO.:

UNIT:

DATE:

COMPLETED BY:

TELEPHONE:

50-354 Hope Creek 11/11/03 R. Ritzman (856) 339-1445 Summary Of Monthly Operating Experience The unit entered the month at approximately 38% reactor power, reaching 100% on October 3.

On October 4, Hope Creek was shutdown due to a control intercept valve hydraulic oil leak. The plant was returned on-line on October 7, and reached 100% power on October 12.

On October 29, the unit was reduced to approximately 79% power due to solar magnetic disturbance and ended the month at a reduced power level.

At the end of the month, Hope Creek completed 24 days of continuous on-line operation.