LR-N05-0551, October 2005 Monthly Operating Report for Hope Creek Generating Station

From kanterella
Jump to navigation Jump to search
October 2005 Monthly Operating Report for Hope Creek Generating Station
ML053260426
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 11/15/2005
From: Massaro M
Public Service Enterprise Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
LR-N05-0551
Download: ML053260426 (3)


Text

PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 NOV 15 2005 0 PSEG ANuclear LLC LR-N05-0551 U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 MONTHLY OPERATING REPORT HOPE CREEK GENERATING STATION DOCKET NO. 50-354 In compliance with Section 6.9, Reporting Requirements for the Hope Creek Technical Specifications, the operating statistics for October 2005 are being forwarded.

Sincerely, Michael J. Massaro Hope Creek Plant Manager Attachments C Distribution

, 1 1

95-2168 REV. 7/99

DOCKET NO.: 50-354 UNIT: Hope Creek DATE: 11/09/05 COMPLETED BY: K. Hiqht TELEPHONE: (856) 339-3887 Reporting Period October 2005 OPERATING DATA REPORT Design Electrical Rating (MWe-Net) 1083 _ I _ = _ _11_

Maximum Dependable Capacity (MWe-Net) 1049 __ BeW_

Month Year-to-date Cumulative No. of hours reactor was critical 745 6294 141081 No. of hours generator was on line (service 745 5915 137995 hours)

Unit reserve shutdown hours 0 0 0 Net Electrical Energy (MWH) 785704 6103469 139891607 UNIT SHUTDOWNS NO. DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTION/

F=FORCED (HOURS) (1) SHUTTING COMMENT S=SCHEDULED DOWN THE

._ REACTOR (2)

I I I_

(1) Reason (2) Method A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Trip/Scram C - Refueling 3 - Automatic Trip/Scram D - Regulatory Restriction 4 - Continuation E - Operator Training/License Examination 5 - Other (Explain)

F - Administrative G - Operational Error (Explain)

H - Other

DOCKET NO.: 50-354 UNIT: Hope Creek DATE: 11/09/05 COMPLETED BY: F. Possesskv TELEPHONE: (856) 339-1160 Summary Of Monthly Operating Experience

  • The unit entered the month at 100% power.
  • On October 05, power was lowered to 98% to remove the 6A feedwater heater from service for troubleshooting.
  • On October 08, power was lowered to 70% to perform control rod scram time testing. Power was returned to 100% on October 09.
  • On October 09, power was lowered to 98% to remove the 6A feedwater heater from service for troubleshooting.
  • At the end of the month, the unit remained at 98% and completed 57 days of continuous on-line operation.