LR-N04-0211, April 2004 Monthly Operation Report for Hope Creek Generating Station
| ML041390523 | |
| Person / Time | |
|---|---|
| Site: | Hope Creek |
| Issue date: | 05/07/2004 |
| From: | Hutton J Public Service Enterprise Group |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| LR-N04-0211 | |
| Download: ML041390523 (3) | |
Text
PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 MAY 0 7 2004 LR-N04-021 1 o PSEG Nuclear LLC U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 MONTHLY OPERATING REPORT HOPE CREEK GENERATING STATION DOCKET NO. 50-354 In compliance with Section 6.9, Reporting Requirements for the Hope Creek Technical Specifications, the operating statistics for April 2004 are being forwarded.
Sincerely, Attachments C Distribution
-1aq 95-2168 REV. 7/99
DOCKET NO.:
UNIT:
DATE:
COMPLETED BY:
TELEPHONE:
50-354 Hope Creek 5/5/04 F. Todd (856) 339-1316 Reporting Period April 2004 OPERATING DATA REPORT Design Electrical Rating (MWe-Net)
Maximum Dependable Capacity (MWe-Net)
No. of hours reactor was critical No. of hours generator was on line (service hours)
Unit reserve shutdown hours Net Electrical Energy (MWH) 1083 1049 Month 531 428 2217 128173 0
0 0
228783 2057099 129796371 UNIT SHUTDOWNS NO.
DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTION/
F=FORCED (HOURS)
(1)
SHUTTING COMMENT S=SCHEDULED DOWN THE REACTOR (2) 2 4/1/04 S
291 Hrs.
B 4
Repair F020 Valve Steam Leak and Control 4/13/04 Rod Drive Mechanisms (1) Reason (2) Method A - Equipment Failure (Explain)
B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)
H - Other 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)
DOCKET NO.: 50-354 UNIT: Hope Creek DATE: 5/5/04 COMPLETED BY: R. Ritzman TELEPHONE: (856) 339-1445 Summary Of Monthly Operating Experience Hope Creek entered the month in a planned maintenance outage.
Hope Creek was placed back on-line on April 13 and operated for the remainder of the month at less than 100% reactor power.
- At the end of the month, Hope Creek completed 17 days of continuous on-line operation.