LR-N04-0211, April 2004 Monthly Operation Report for Hope Creek Generating Station

From kanterella
Jump to navigation Jump to search
April 2004 Monthly Operation Report for Hope Creek Generating Station
ML041390523
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 05/07/2004
From: Hutton J
Public Service Enterprise Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
LR-N04-0211
Download: ML041390523 (3)


Text

PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 MAY 0 7 2004 LR-N04-021 1 o PSEG Nuclear LLC U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 MONTHLY OPERATING REPORT HOPE CREEK GENERATING STATION DOCKET NO. 50-354 In compliance with Section 6.9, Reporting Requirements for the Hope Creek Technical Specifications, the operating statistics for April 2004 are being forwarded.

Sincerely, Attachments C Distribution

-1aq 95-2168 REV. 7/99

DOCKET NO.:

UNIT:

DATE:

COMPLETED BY:

TELEPHONE:

50-354 Hope Creek 5/5/04 F. Todd (856) 339-1316 Reporting Period April 2004 OPERATING DATA REPORT Design Electrical Rating (MWe-Net)

Maximum Dependable Capacity (MWe-Net)

No. of hours reactor was critical No. of hours generator was on line (service hours)

Unit reserve shutdown hours Net Electrical Energy (MWH) 1083 1049 Month 531 428 2217 128173 0

0 0

228783 2057099 129796371 UNIT SHUTDOWNS NO.

DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTION/

F=FORCED (HOURS)

(1)

SHUTTING COMMENT S=SCHEDULED DOWN THE REACTOR (2) 2 4/1/04 S

291 Hrs.

B 4

Repair F020 Valve Steam Leak and Control 4/13/04 Rod Drive Mechanisms (1) Reason (2) Method A - Equipment Failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)

H - Other 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)

DOCKET NO.: 50-354 UNIT: Hope Creek DATE: 5/5/04 COMPLETED BY: R. Ritzman TELEPHONE: (856) 339-1445 Summary Of Monthly Operating Experience Hope Creek entered the month in a planned maintenance outage.

Hope Creek was placed back on-line on April 13 and operated for the remainder of the month at less than 100% reactor power.

  • At the end of the month, Hope Creek completed 17 days of continuous on-line operation.