LR-N03-0308, June 2003 Monthly Operating Report for Hope Creek Generating Station

From kanterella
Jump to navigation Jump to search
June 2003 Monthly Operating Report for Hope Creek Generating Station
ML032040185
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 07/11/2003
From: Waldinger L
Public Service Enterprise Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
LR-N03-0308
Download: ML032040185 (3)


Text

01%

PSEG Nucleor LLC.

P.O. Box 236,1 6ancoDks Bridge, New Jersey 08038-0236 JUL 1 1 2003 LR-N03-0308 O PSEG Nuclear LLC U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:

MONTHLY OPERATING REPORT HOPE CREEK GENERATING STATION DOCKET NO. 50-354 In compliance with Section 6.9, Reporting Requirements for the Hope Creek Technical Specifications, the operating statistics for June 2003 are being forwarded.

Sincerely, Attachments C Distribution 95-2168 REV. 7/99

DOCKET NO.:

UNIT:

DATE:

COMPLETED BY:

TELEPHONE:

50-354 Hope Creek 7/8/03 F. Todd (856) 339-1316 Reporting Period June 2003 OPERATING DATA REPORT Design Electrical Rating (MWe-Net)

Maximum Dependable Capacity (MWe-Net)

No. of hours reactor was critical No. of hours generator was on line (service hours)

Unit reserve shutdown hours Net Electrical Energy (MWH) 1083 1049 Month Year-to-date Cumulative 720 3497 124613 720 3364 122182 0

0 0

743334 3405765 123884456 UNIT SHUTDOWNS NO.

DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTION!

F=FORCED (HOURS)

(1)

SHUTTING COMMENT S=SCHEDULED DOWN THE REACTOR (2)

(1) Reason (2) Method A - Equipment Failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)

H - Other 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)

DOCKET NO.: 50-354 UNIT: Hope Creek DATE: 7/8/03 COMPLETED BY: R. Ritzman TELEPHONE: (856) 339-1445 Summary Of Monthly Operating Experience The unit entered the month at approximately 100% reactor power.

On June 18, power was reduced to approximately 42% due to the "A" Emergency Diesel Generator Intercooler Pump seal leak. Power was returned to approximately 100% on June 20.

On June 25, the unit was reduced to approximately 79% power due to a 500kv line outage. Power was returned to approximately 100% on June 26.

On June 30, power was reduced to approximately 76% due to a 13.8kv breaker trip. Power was returned to approximately 100% later that day.

At the end of the month, Hope Creek completed 47 days of continuous on-line operation.