Text
PSEG Nuclear LLC P.O Box 236, Hancocks Bndge, New Jersey 08038-0236 APR 1 4 2003 LR-N03-01 61 o PSEG Nuclear LLC U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:
MONTHLY OPERATING REPORT HOPE CREEK GENERATING STATION DOCKET NO.60-354 In compliance with Section 6.9, Reporting Requirements for the Hope Creek Technical Specifications, the operating statistics for March 2003 are being forwarded.
Sincerely, Lon Wafdinger Operations Director RAR Attachments C Distribution 4>
D 95-2168 REV 7/99
DOCKET NO.:
UNIT:
DATE:
COMPLETED BY:
TELEPHONE:
50-354 Hope Creek 4/8/03 F. Todd (856) 339-1316 Reporting Period March 2003 OPERATING DATA REPORT Design Electrical Rating (MWe-Net)
Maximum Dependable Capacity (MWe-Net)
No. of hours reactor was critical No. of hours generator was on line (service hours)
Unit reserve shutdown hours Net Electrical Energy (MWH) 1083 1049 Month 544 458 1874 120693 409815 1919967 122398658 UNIT SHUTDOWNS NO.
DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTION/
F=FORCED (HOURS)
(1)
SHUTTING COMMENT S=SCHEDULED DOWN THE REACTOR (2) 1 3/7/03 S
168 B
1 Recirc Pump Seal Replacement 3/14/03 2
3/16/03 F
118 A
1 Turbine Bypass Valve 3/21/03 (1) Reason (2) Method A - Equipment Failure (Explain)
B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)
H - Other 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)
DOCKET NO.: 50-354 UNIT: Hope Creek DATE: 4/8/03 COMPLETED BY: R. Ritzman TELEPHONE: (856) 339-1445 Summary Of Monthly Operating Experience
- On March 7, the unit was taken offline for the planned replacement of the "B" Recirculation Pump Seal. The unit was placed back online on March 14.
- On March 16, the unit was at approximately 20% power and was shutdown to repair a turbine bypass valve. The unit was placed back online on March 21.
- At the end of the month, Hope Creek completed 10 days of continuous on-line operation.