LR-N05-0522, September 2005 Monthly Operating Report for Hope Creek Generating Station

From kanterella
Jump to navigation Jump to search
September 2005 Monthly Operating Report for Hope Creek Generating Station
ML052980377
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 10/14/2005
From: Massaro M
Public Service Electric & Gas Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
LR-N05-0522
Download: ML052980377 (3)


Text

I PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 OCT 1 4 2005 LR-N05-0522

@ PSEG Nuclear LLC U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 MONTHLY OPERATING REPORT HOPE CREEK GENERATING STATION DOCKET NO. 50-354 In compliance with Section 6.9, Reporting Requirements for the Hope Creek Technical Specifications, the operating statistics for September 2005 are being forwarded.

Sincerely, Michael J. Massaro Hope Creek Plant Manager Attachments C Distribution 05-2t68 REV. 7ss

DOCKET NO.:

UNIT:

DATE:

COMPLETED BY:

TELEPHONE:

50-354 Hone Creek 10/13/05 K. Hight (856) 339-3887 Reporting Period September 2005 OPERATING DATA REPORT Design Electrical Rating (MWe-Net)

Maximum Dependable Capacity (MWe-Net)

No. of hours reactor was critical No. of hours generator was on line (service hours)

Unit reserve shutdown hours Net Electrical Energy (MWH) 1083 1049

-o Month Year-to-date Cumulative 667 5549 140336 619 5170 137250 0

0 0

633860 5317765 139105903 UNIT SHUTDOWNS NO.

DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTION!

F=FORCED (HOURS)

(1)

SHUTTING COMMENT S=SCHEDULED DOWN THE REACTOR (2) 6 9/1/05 F

101.2 A

4 B Torus To Drywell Vac l

lBreaker failed to close.

9 /5 /0 5 (1) Reason (2) Method A - Equipment Failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)

H - Other I - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)

U.

DOCKET NO.: 50-354 UNIT: Hone Creek DATE: 10/1 3/05 COMPLETED BY: F. Possessky TELEPHONE: (856) 339-1160 Summarv Of Monthly Operating Experience

  • The unit entered the month at 0% power due to shutdown for repairs to 'B' Torus to Drywell vacuum breaker.
  • Commenced Unit startup on September 1. On September 2, prior to synchronization to the grid, the reactor was manually shutdown to repair a packing leak on the 'D' MSIV. The unit started up on September 4, and achieved -100% power on September 6
  • On September 13, power was lowered to 78% to remove the IA and IB Feedwater Heaters from service for vent pipe repair. Power was returned to 100% on September 14.
  • At the end of the month, the unit remained at 100% and completed 26 days of continuous on-line operation.