PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 JUL 1 5 2002 LR-N02-0250 0 PSEG
\\Tuclear LLC U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:
MONTHLY OPERATING REPORT HOPE CREEK GENERATING STATION DOCKET NO. 50-354 In compliance with Section 6.9, Reporting Requirements for the Hope Creek Technical Specifications, the operating statistics for June 2002 are being forwarded.
Sincerely, D. F. Ga how Vice President - Operations RAR Attachments C Distribution 95-2168 REV. 7/99
DOCKET NO.:
UNIT:
DATE:
COMPLETED BY:
TELEPHONE:
50-354 Hope Creek 07/08/02 F. Todd (856) 339-1316 Reporting Period June 2002 OPERATING DATA REPORT Design Electrical Rating (MWe-Net)
Maximum Dependable Capacity (MWe-Net)
No. of hours reactor was critical No. of hours generator was on line (service hours)
Unit reserve shutdown hours Net Electrical Energy (MWH) 1083 1049 Month 653 4276 116698 605 4137 114402 0
0 0
564236 4221815 115857423 UNIT SHUTDOWNS NO.
DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTION/
F=FORCED (HOURS)
(1)
SHUTTING COMMENT S=SCHEDULED DOWN THE REACTOR (2) 2 6/22/02 F
115 hrs A
3 Loss of Secondary Condensate 6/27/02 Pump/Moisture Separator High Level (1) Reason (2) Method A - Equipment Failure (Explain)
B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)
H - Other 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)
DOCKET NO.:
UNIT:
DATE:
COMPLETED BY:
TELEPHONE:
50-354 Hope Creek 07/08/02 R. Ritzman (856) 339-1445 Summary Of Monthly Operatinq Experience Hope Creek began the month at 100% power.
On June 10, Hope Creek reduced power to approximately 75% as requested by the Load Dispatcher due to a fire near the 500KV 5021 Deans Line.
Power was restored to approximately 100% on June 11.
On June 15, power was reduced to approximately 40% power to perform plant maintenance on the Motor Generator set brushes. Power was restored to 100% on June 18.
On June 22, Hope Creek automatically scrammed due to a turbine runback and turbine trip resulting from the loss of a secondary condensate pump and Moisture Separator high level. The unit was brought back on-line on June 27.
" At the end of the month, Hope Creek competed 3 days of continuous on-line operation.