LR-N05-0313, May 2005 Monthly Operating Report for Hope Creek Generating Station

From kanterella
Jump to navigation Jump to search
May 2005 Monthly Operating Report for Hope Creek Generating Station
ML051790229
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 06/15/2005
From: Massaro M
Public Service Enterprise Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
LR-N05-0313
Download: ML051790229 (3)


Text

-

PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 JUN 1 5 2005 LR-N05-031 3 o PSEG NuclearLLC U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 MONTHLY OPERATING REPORT HOPE CREEK GENERATING STATION DOCKET NO. 50-354 In compliance with Section 6.9, Reporting Requirements for the Hope Creek Technical Specifications, the operating statistics for May 2005 are being forwarded.

Sincerely, Michael J. Massaro Hope Creek Plant Manager Attachments C Distribution 95-2168 REV. 7199

I..

asI DOCKET NO.:

UNIT:

DATE:

COMPLETED BY:

TELEPHONE:

50-354 Hope Creek 6/8/05 K. Hight (856) 339-3887 Reporting Period May 2005 OPERATING DATA REPORT Design Electrical Rating (MWe-Net)

Maximum Dependable Capacity (MWe-Net)

No. of hours reactor was critical No. of hours generator was on line (service hours)

Unit reserve shutdown hours Net Electrical Energy (MWH) 1083

_i l

1049 Month Year-to-date Cumulative 744 2930 137717 744 2662 134741 0

2140 0

813305 ]2716479 136504617 UNIT SHUTDOWNS NO.

DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTIONI F=FORCED (HOURS)

(1)

SHUTTING COMMENT S=SCHEDULED DOWN THE REACTOR (2)

ID I_:I I.

(1) Reason (2) Method A - Equipment Failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)

H - Other 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)

DOCKET NO.:

UNIT:

DATE:

COMPLETED BY:

TELEPHONE:

50-354 Hone Creek 6/8/05 R. Ritzman (856) 339-1445 Summary Of Monthly Operating Experience

  • Hope Creek began the month at approximately 100% reactor power and operated there throughout the month.
  • At the end of the month, Hope Creek completed 51 days of continuous on-line operation.