LR-N03-0434, September 2003 Monthly Operating Report for Hope Creek Generating Station

From kanterella
Jump to navigation Jump to search
September 2003 Monthly Operating Report for Hope Creek Generating Station
ML032950607
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 10/13/2003
From: Hutton J
Public Service Enterprise Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
LR-N03-0434
Download: ML032950607 (3)


Text

PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 OCT 13 2003 LR-N03-0434 o PSEG ATuclearLLC U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:

MONTHLY OPERATING REPORT HOPE CREEK GENERATING STATION DOCKET NO. 50-354 In compliance with Section 6.9, Reporting Requirements for the Hope Creek Technical Specifications, the operating statistics for September 2003 are being forwarded.

Sincerely, lope Creek Plant Manager Attachments C Distribution IF'

kj; 95-2168 REV. 7/99

.1 DOCKET NO.:

UNIT:

DATE:

COMPLETED BY:

TELEPHONE:

50-354 Hope Creek 10/08/03 F. Todd (856) 339-1316 Reporting Period September 2003 OPERATING DATA REPORT Design Electrical Rating (MWe-Net)

Maximum Dependable Capacity (MWe-Net)

No. of hours reactor was critical No. of hours generator was on line (service hours)

Unit reserve shutdown hours Net Electrical Energy (MWH) 1083 M" _ _

_ _jIl 1049 1~a NN1- -

Month Year-to-date Cumulative 516 5501 126616 478 5330 124149 0

0 0

480493 5453302 1125931993 UNIT SHUTDOWNS NO.

DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTION/

F=FORCED (HOURS)

(1)

SHUTTING COMMENT S=SCHEDULED DOWN THE REACTOR (2) 5 9/19/03 F

242 Hrs.

A 3

Reactor Scram due to electrical transient and 9/28/03 Feed Pump failure (1) Reason (2) Method A - Equipment Failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)

H - Other 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)

DOCKET NO.: 50-354 UNIT: Hope Creek DATE: 10/07/03 COMPLETED BY: R. Ritzman TELEPHONE: (856) 339-1445 Summary Of Monthly Operating Experience The unit entered the month at approximately 100% reactor power.

On September 19, there was an automatic scram due to an electrical transient and feed pump failure. The unit was placed back on the grid on September 29.

At the end of the month, Hope Creek completed 1 day of continuous on-line operation.