LR-N02-0355, September 2002 Monthly Operating Report for Hope Creek

From kanterella
Jump to navigation Jump to search
September 2002 Monthly Operating Report for Hope Creek
ML022960477
Person / Time
Site: Hope Creek 
Issue date: 10/14/2002
From: Garchow D
Public Service Enterprise Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
LR-N02-0355
Download: ML022960477 (9)


Text

PSEG Nuclear LLC P 0 Box 236, Hancocks Bridge. New Jersey 08038-0236 OCT 1 4 2002 LR-N02-0355 O PSEG Nuclear LLC U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:

MONTHLY OPERATING REPORT HOPE CREEK GENERATING STATION DOCKET NO. 50-354 In compliance with Section 6.9, Reporting Requirements for the Hope Creek Technical Specifications, the operating statistics for September 2002 are being forwarded.

Sincerely, D. F. G rchow Vice President - Operations RAR Attachments C Distribution 95-2168 REV 7/99

DOCKET NO.:

UNIT:

DATE:

COMPLETED BY:

TELEPHONE:

50-354 Hope Creek 10/09/02 F. Todd (856) 339-1316 Reporting Period September 2002 OPERATING DATA REPORT Design Electrical Rating (MWe-Net)

Maximum Dependable Capacity (MWe-Net)

No. of hours reactor was critical No. of hours generator was on line (service hours)

Unit reserve shutdown hours Net Electrical Energy (MWH) 1083 1049 Month Year-to-date Cumulative 720 6484 118906 720 6345 116610 0

0 0

737734 6490345 118125953 UNIT SHUTDOWNS NO.

DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTION/

F=FORCED (HOURS)

(1)

SHUTTING COMMENT S=SCHEDULED DOWN THE REACTOR (2)

(1) Reason (2) Method A - Equipment Failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)

H - Other 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)

DOCKET NO.: 50-354 UNIT: Hope Creek DATE: 10/09/02 COMPLETED BY: R. Ritzman TELEPHONE: (856) 339-1445 Summary Of Monthly Operating Experience

"* Hope Creek began the month at 100% power.

"* On September 28, power was reduced to approximately 40% for planned Motor Generator Set Brush Replacement.

"* At the end of the month, Hope Creek completed 95 days of continuous on-line operation.

PSEG Nuclear LLC P.O Box 236, Hancocks Bridge, New Jersey 08038-0236 OCT 1 4 2002 LR-N02-0356 o PSEG Nuclear LLC U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:

MONTHLY OPERATING REPORT SALEM GENERATING STATION UNIT 1 DOCKET NO. 50-272 In compliance with Section 6.9, Reporting Requirements for the Salem Unit 1 Technical Specifications, the operating statistics for September 2002 are being forwarded.

Sincerely, D. F. archow Vice President - Operations RAR Attachments C Distribution 95-2168 REV 7/99

DOCKET NO.:

UNIT:

DATE:

COMPLETED BY:

TELEPHONE:

50-272 Salem 1 10/09/02 F. Todd (856) 339-1316 Reporting Period September 2002 OPERATING DATA REPORT Design Electrical Rating (MWe-Net)

Maximum Dependable Capacity (MWe-Net)

No. of hours reactor was critical No. of hours generator was on line (service hours)

Unit reserve shutdown hours Net Electrical Energy (MWH) 1130 1096 Month I Year-to-date Cumulative 720 6393 140620 720 6313 136008 0

0 0

805507 6979449 138262847 UNIT SHUTDOWNS NO.

DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTION/

F=FORCED (HOURS)

(1)

SHUTTING COMMENT S=SCHEDULED DOWN THE REACTOR (2)

(1) Reason (2) Method A - Equipment Failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)

H - Other 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)

DOCKET NO.: 50-272 UNIT: Salem I DATE: 10/09/02 COMPLETED BY: R. Ritzman TELEPHONE: (856) 339-1445 Summary Of Monthly Operating Experience

"* Salem 1 entered the month at approximately 100%.

"* There were no reportable power reductions at Salem 1 during September.

"* At the end of the month, Salem 1 completed 201 days of continuous on line operation.

PSEG Nuclear LLC P 0. Box 236, Hancocks Bndge, New Jersey 08038-0236

,r OCT 1 4 2002 LR-N02-0357 o PSEG Nuclear LLC U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:

MONTHLY OPERATING REPORT SALEM GENERATING STATION UNIT 2 DOCKET NO. 50-311 In compliance with Section 6.9, Reporting Requirements for the Salem Unit 2 Technical Specifications, the operating statistics for September 2002 are being forwarded.

Sincerely, D. F. Ga ow Vice President - Operations RAR Attachments C Distribution 95-2168 REV 7/99

DOCKET NO.:

UNIT:

DATE:

COMPLETED BY:

TELEPHONE:

50-311 Salem 2 10/09/02 F. Todd (856) 339-1316 Reporting Period September 2002 OPERATING DATA REPORT Design Electrical Rating (MWe-Net)

Maximum Dependable Capacity (MWe-Net)

No. of hours reactor was critical No. of hours generator was on line (service hours)

Unit reserve shutdown hours Net Electrical Energy (MWH) 1131 1092 Month Year-to-date Cumulative 720 5494 118207 720 5411 114749 0

0 0

774858 5898115 116719656 UNIT SHUTDOWNS NO.

DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTION/

F=FORCED (HOURS)

(1)

SHUTTING COMMENT S=SCHEDULED DOWN THE REACTOR (2)

(1) Reason (2) Method A - Equipment Failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)

H - Other 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)

DOCKET NO.: 50-311 UNIT: Salem 2 DATE: 10/09/02 COMPLETED BY: R. Ritzman TELEPHONE: (856) 339-1445 Summary Of Monthly Operating Experience

"* Salem 2 began the month at 100% reactor power.

"* On September 21, power was reduced to approximately 45% to perform planned Turbine Valve Testing. Power was returned to 100% on September 23.

"* At the end of the month, Salem 2 completed 136 days of continuous on line operation.