MONTHYEARLR-N06-0084, January 2006 Monthly Operating Report for Hope Creek Generating Station2006-02-15015 February 2006 January 2006 Monthly Operating Report for Hope Creek Generating Station LR-N06-0009, December 2005 Monthly Operating Report for Hope Creek Generating Station2006-01-12012 January 2006 December 2005 Monthly Operating Report for Hope Creek Generating Station LR-N05-0551, October 2005 Monthly Operating Report for Hope Creek Generating Station2005-11-15015 November 2005 October 2005 Monthly Operating Report for Hope Creek Generating Station LR-N05-0522, September 2005 Monthly Operating Report for Hope Creek Generating Station2005-10-14014 October 2005 September 2005 Monthly Operating Report for Hope Creek Generating Station LR-N05-0450, August 2005 Monthly Operating Report for Hope Creek Generating Station2005-09-12012 September 2005 August 2005 Monthly Operating Report for Hope Creek Generating Station LR-N05-0415, July 2005 Monthly Operating Report for Hope Creek Generating Station2005-08-15015 August 2005 July 2005 Monthly Operating Report for Hope Creek Generating Station LR-N05-0353, June 2005 Monthly Operating Report for Hope Creek Generating Station2005-07-13013 July 2005 June 2005 Monthly Operating Report for Hope Creek Generating Station LR-N05-0313, May 2005 Monthly Operating Report for Hope Creek Generating Station2005-06-15015 June 2005 May 2005 Monthly Operating Report for Hope Creek Generating Station LR-N05-0262, April 2005 Monthly Operating Report for Hope Creek Generating Station2005-05-13013 May 2005 April 2005 Monthly Operating Report for Hope Creek Generating Station LR-N05-0207, March 2005 Monthly Operating Report for Hope Creek Generating Station2005-04-14014 April 2005 March 2005 Monthly Operating Report for Hope Creek Generating Station ML0508104192005-03-14014 March 2005 February 2005 Monthly Operating Report for Hope Creek Generating Station LR-N05-0090, January 2005 Monthly Operating Report for Hope Creek Generating Station2005-02-14014 February 2005 January 2005 Monthly Operating Report for Hope Creek Generating Station LR-N05-0010, December 2004 Monthly Operating Report for Hope Creek Generating Station2005-01-13013 January 2005 December 2004 Monthly Operating Report for Hope Creek Generating Station LR-N04-0571, November 2004 Monthly Operating Report for Hope Creek2004-12-14014 December 2004 November 2004 Monthly Operating Report for Hope Creek LR-N04-0504, October 2004 Monthly Operating Report for Hope Creek Generating Station2004-11-15015 November 2004 October 2004 Monthly Operating Report for Hope Creek Generating Station LR-N04-0446, September 2004 Monthly Operating Report for Hope Creek Generating Station2004-10-15015 October 2004 September 2004 Monthly Operating Report for Hope Creek Generating Station LR-N04-0404, August 2004 Monthly Operating Report for Hope Creek Generating Station2004-09-13013 September 2004 August 2004 Monthly Operating Report for Hope Creek Generating Station LR-N04-0355, July 2004 Monthly Operating Report for Hope Creek Generating Station2004-08-12012 August 2004 July 2004 Monthly Operating Report for Hope Creek Generating Station LR-N04-0301, June 2004 Monthly Operating Report for Hope Creek Generating Station2004-07-12012 July 2004 June 2004 Monthly Operating Report for Hope Creek Generating Station LR-N04-0255, May 2004 Monthly Operating Report for Hope Creek Generating Station2004-06-14014 June 2004 May 2004 Monthly Operating Report for Hope Creek Generating Station LR-N04-0211, April 2004 Monthly Operation Report for Hope Creek Generating Station2004-05-0707 May 2004 April 2004 Monthly Operation Report for Hope Creek Generating Station LR-N04-0169, March 2004 Monthly Operating Report for Hope Creek Generating Station2004-04-15015 April 2004 March 2004 Monthly Operating Report for Hope Creek Generating Station LR-N04-0109, February 2004 Monthly Operating Report for Hope Creek Generating Station2004-03-10010 March 2004 February 2004 Monthly Operating Report for Hope Creek Generating Station LR-N04-0059, January 2004 Monthly Operating Report for Hope Creek Generating Station2004-02-17017 February 2004 January 2004 Monthly Operating Report for Hope Creek Generating Station LR-N04-0011, December 2003 Monthly Operating Report for Hope Creek Generating Station2004-01-13013 January 2004 December 2003 Monthly Operating Report for Hope Creek Generating Station LR-N03-0517, November 2003 Monthly Operating Report for Hope Creek Generating Station2003-12-15015 December 2003 November 2003 Monthly Operating Report for Hope Creek Generating Station LR-N03-0468, October 2003 Monthly Operating Report for Hope Creek Generating Station2003-11-17017 November 2003 October 2003 Monthly Operating Report for Hope Creek Generating Station LR-N03-0434, September 2003 Monthly Operating Report for Hope Creek Generating Station2003-10-13013 October 2003 September 2003 Monthly Operating Report for Hope Creek Generating Station LR-N03-0392, August 2003 Monthly Operating Report for Hope Creek2003-09-12012 September 2003 August 2003 Monthly Operating Report for Hope Creek LR-N03-0357, July 2003 Monthly Operating Report for Hope Creek2003-08-12012 August 2003 July 2003 Monthly Operating Report for Hope Creek LR-N03-0308, June 2003 Monthly Operating Report for Hope Creek Generating Station2003-07-11011 July 2003 June 2003 Monthly Operating Report for Hope Creek Generating Station LR-N03-0257, May 2003 Monthly Operating Report for Hope Creek2003-06-11011 June 2003 May 2003 Monthly Operating Report for Hope Creek LR-N03-0225, April 2003 Monthly Operating Report for Hope Creek Generating Station2003-05-14014 May 2003 April 2003 Monthly Operating Report for Hope Creek Generating Station LR-N03-0161, March 2003 Monthly Operating Report for Hope Creek Generating Station2003-04-14014 April 2003 March 2003 Monthly Operating Report for Hope Creek Generating Station LR-N03-0117, February 2003 Monthly Operating Report for Hope Creek Generating Station2003-03-11011 March 2003 February 2003 Monthly Operating Report for Hope Creek Generating Station LR-N03-0060, January 2003 Monthly Operating Report for Hope Creek Generating Station2003-02-14014 February 2003 January 2003 Monthly Operating Report for Hope Creek Generating Station LR-N03-0006, December 2002 Monthly Operating Report for Hope Creek2003-01-14014 January 2003 December 2002 Monthly Operating Report for Hope Creek LR-N02-0418, November 2002 Monthly Operating Report for Hope Creek2002-12-13013 December 2002 November 2002 Monthly Operating Report for Hope Creek LR-N02-0396, October 2002 Monthly Operating Report for Hope Creek Generating Station2002-11-13013 November 2002 October 2002 Monthly Operating Report for Hope Creek Generating Station LR-N02-0355, September 2002 Monthly Operating Report for Hope Creek2002-10-14014 October 2002 September 2002 Monthly Operating Report for Hope Creek LR-N02-0326, August 2002 Monthly Operating Report for Hope Creek2002-09-16016 September 2002 August 2002 Monthly Operating Report for Hope Creek LR-N02-0294, July 2002 Monthly Operating Report for Hope Creek2002-08-14014 August 2002 July 2002 Monthly Operating Report for Hope Creek LR-N02-0250, June 2002 Monthly Operating Report for Hope Creek Generating Station2002-07-15015 July 2002 June 2002 Monthly Operating Report for Hope Creek Generating Station LR-N02-0210, May 2002 Monthly Operating Report for Hope Creek2002-06-12012 June 2002 May 2002 Monthly Operating Report for Hope Creek LR-N02-0187, April 2002 Monthly Operating Report for Hope Creek2002-05-15015 May 2002 April 2002 Monthly Operating Report for Hope Creek LR-N02-0158, March 2002 Monthly Operating Report for Hope Creek2002-04-12012 April 2002 March 2002 Monthly Operating Report for Hope Creek LR-N02-0091, February 2002 Monthly Operating Report for Hope Creek, Unit 12002-03-14014 March 2002 February 2002 Monthly Operating Report for Hope Creek, Unit 1 LR-N02-0050, January 2002 Monthly Operating Report for Hope Creek Generating Station, Unit 12002-02-13013 February 2002 January 2002 Monthly Operating Report for Hope Creek Generating Station, Unit 1 ML0204504372002-01-15015 January 2002 December 2001 Monthly Operating Report for Hope Creek Generating Station, Unit 1 2006-02-15
[Table view] |
Text
PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 JAN 1 5 2002 0 PSEG LRN-02-0019 Nuclea LLC U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:
MONTHLY OPERATING REPORT HOPE CREEK GENERATING STATION UNIT I DOCKET NO. 50-354 In compliance with Section 6.9, Reporting Requirements for the Hope Creek Technical Specifications, the operating statistics for December 2001 are being forwarded.
- Operations RAR Attachments C Distribution 95-2168 REV. 7/99
INDEX NUMBER SECTION OF PAGES Operating Data Report ...............................................................................
Monthly Operating Summary ......................................................................
DOCKET NO.: 50-354 UNIT: Hope Creek DATE: 01/11/02 COMPLETED BY: F. Todd TELEPHONE: (856) 339-1316 Reporting Period December 2001 OPERATING DATA REPORT Design Electrical Rating (MWe-Net) 1083 Maximum Dependable Capacity (MWe-Net) 1049 Month Year-to-aate yumuiative No. of hours reactor was critical 661 7975 112422 No. of hours generator was on line (service 633 7859 110264 hours)
Unit reserve shutdown hours 0 0 0 Net Electrical Energy (MWH) 623007 8065273 111635608 UNIT SHUTDOWNS NO. DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTION/
F=FORCED (HOURS) (1) SHUTTING COMMENT S=SCHEDULED DOWN THE REACTOR (2) 3 12/6101 F 111 A I MS Safety valve repair to 12111101 1 1 I II I (1) Reason (2) Method A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Trip/Scram C - Refueling 3 - Automatic Trip/Scram D - Regulatory Restriction 4 - Continuation E - Operator Training/License Examination 5 - Other (Explain)
F - Administrative G - Operational Error (Explain)
H - Other
DOCKET NO.: 50-354 UNIT: Hope Creek DATE: 01/11/02 COMPLETED BY: R. Ritzman TELEPHONE: (856) 339-1445 Summary Of Monthly Operating Experience
- Hope Creek began the month at 100% power.
- On December 5, the unit was taken off line for maintenance on the Main Steam Safety Relief Valve. The unit was returned to service on December 11.
- On December 13, power was reduced from 85% to approximately 62% for Turbine Control Valve Testing. Power ascension to 100% power was completed on December 14.
- On December 17, power was reduced to approximately 66% to perform Turbine Control Valve Testing and was returned to 100% power on December 18.
- On December 29, power was reduced to approximately 84% for Turbine Control Valve Testing. The unit returned to 100% power on December 30 and remained there for the remainder of the month.
- At the end of the month, the plant completed 20 days of continuous operation.