LR-N04-0255, May 2004 Monthly Operating Report for Hope Creek Generating Station

From kanterella
Jump to navigation Jump to search

May 2004 Monthly Operating Report for Hope Creek Generating Station
ML041740623
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 06/14/2004
From: Hutton J
Public Service Enterprise Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
LR-N04-0255
Download: ML041740623 (3)


Text

PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 JUN1 4 2004 LR-N04-0255 O PSEG NuclearLLC U. S. Nuclear Regulatory Commission Document Control Desk.

Washington, DC 20555 MONTHLY OPERATING REPORT HOPE CREEK GENERATING STATION DOCKET NO. 50-354 In compliance with Section 6.9, Reporting Requirements for the Hope Creek Technical Specifications, the operating statistics for May 2004 are being forwarded.

Sincerely, omes C.

Putto n

Ppe Creek Plant Manager Attachments C Distribution C[

'e;L 95-2168 REV. 7/99

DOCKET NO.: 50-354 UNIT: Hope Creek DATE: 617104 COMPLETED BY: F. Todd TELEPHONE: (856) 339-1316 Reporting Period May 2004 OPERATING DATA REPORT Design Electrical Rating (MWe-Net)

Maximum Dependable Capacity (MWe-Net)

No. of hours reactor was critical No. of hours generator was on line (service hours)

Unit reserve shutdown hours Net Electrical Energy (MWH) 1083

'I 1049 Month Year-to-date Cumulative 744 3099 131625 744 2961 128917 0

0 0

785519 2842618 130581890 UNIT SHUTDOWNS NO.

DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTION/

F=FORCED (HOURS)

(1)

SHUTTING COMMENT S=SCHEDULEDDOWN THE REACTOR (2)

(1) Reason (2) Method A - Equipment Failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)

H - Other 1 - Manual 2 - Manual Trip/Scram 3 -Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)

DOCKET NO.: 50-354 UNIT: Hope Creek DATE: 6/7/04 COMPLETED BY: R. Ritzman TELEPHONE: (856) 339-1445 Summary Of Monthly Operating Experience

  • Hope Creek entered the month at approximately 91% reactor power, reaching 100% on May 2.
  • There were no power reductions greater than 20% at Hope Creek for the month of May.
  • At the end of the month, Hope Creek completed 48 days of continuous on-line operation.