AECM-85-0035, Forwards High Groundwater Level Study,Grand Gulf Unit 1, Describing Cause for Exceeding Design Groundwater Level in Response to Concerns Expressed in 841115 Telcon.Change to Design Basis Groundwater Level Unnecessary

From kanterella
Jump to navigation Jump to search

Forwards High Groundwater Level Study,Grand Gulf Unit 1, Describing Cause for Exceeding Design Groundwater Level in Response to Concerns Expressed in 841115 Telcon.Change to Design Basis Groundwater Level Unnecessary
ML20107F495
Person / Time
Site: Grand Gulf  Entergy icon.png
Issue date: 02/14/1985
From: Dale L
MISSISSIPPI POWER & LIGHT CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
Shared Package
ML20107F502 List:
References
AECM-85-0035, AECM-85-35, TAC-54498, TAC-M54498, NUDOCS 8502260144
Download: ML20107F495 (4)


Text

O %'-

MISSISSIPPI POWER & LIGHT COMPANY

)) Helping Build Mississippi EdhMhhildd5 P. O. B O X 16 4 0, J A C K S O N, MIG SIS SIP PI 39215-1640 February 14, 1985 NUCLE AR LICEN$ LNG & $A/ETY DEPARTMENT U. S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation Washington, D. C. 20555 Attention: Mr. Harold R. Denton, Director

Dear Mr. Denton:

SUBJECT:

Grand Gulf Nuclear Station Units 1 and 2 Docket Nos. 50-416 and 50-417 License No. NPF-29 File: 0260/15320 Groundwater Level at Grand Gulf AECM-85/0035 Grand Gulf Nuclear Station (GGNS) Units 1 and 2 have a Construction Monitoring and Dewatering System located around the power block and the Standby Service Water Basins. The purpose of this system is to monitor and dewater the perched aquifer which underifes the power block. Unusually heavy rainfall during the period of January through July 1983 caused the water level in this aquifer to rise and, in the case of dewatering well 8 (DW-8) slightly exceed the design basis groundwater elevation for GCNS of 109.0 feet Mean Sea Level (MSL). This incident was initially described in the Mississippi Power &

Light (MP&L) letter to the NRC dated March 9, 1984 (AECM-84/0020).

Subsequently a teleconference was held on November 15, 1984 between MP&L and the NRC staff to discuss questions resulting from the NRC staff's review of AECM-84/0020. The purpose of this letter is to address the concerns expressed in the November 15, 1984 teleconference (Attachment 1). Additionally, this letter provides the results of a December 1983 study performed to determine the cause for exceeding the design groundwater level (Attachment 2).

The abnormally heavy rainfall experienced during the period January - July 1983, affected some site areas much greater than others. In particular well DW-8, located on the Southeast corner of Unit I directly behind the Radwaste Building, was the only well that exceeded 109.00 ft. MSL. There is a very low probability of a similar rainfall event occurring during the life of the plant (1 in 200 year event). The use of Unit I construction dewatering wells will continue as a precautionary meneure until construction and backfilling is completed for Unit 2. After these Unit 2 activities are completed, monitoring of the perched aquifer and mapping of the site area will be performed to determine the expected normal groundwater conditions for the operating life of the plant. Therefore, MP&L feels that it is unnecessary to change the design basin groundwater level from 109.0 ft. MSL.

8502260144 850214 PDR ADOCK 05000416 S PDR \

J0P14AECM85020701 - IMember Middle South Utilities System g g i

. 1 7.

. AECM-85/0035 Page 2 If you have any questions, please contact this office.

Yours truly,

(

. F. Dale Director MLC/JGC:rw Attachment cc: Mr. J.'B.-Richard (w/a)

Mr. R. B. McGehee (w/a)

Mr. N. S. Reynolds (w/a)

Mr. G. B. Taylor (w/o) t Mr.. Richard C. DeYoung, Director (w/a)'

Office of. Inspection & Enforcement U. S. Nuclear Regulatory Commission Washington, D. C. 20555 lMr.lJ. Nelson Grace, Regional-Administrator (w/a) (

LU.'S. Nuclear-Regulatory Commission "

Region II

'101 Marietta.St., N. W., Suite 2900

~

-Atlanta,. Georgia 30323-e 1 6 >

. \ * $ g -

a

) N

/

k i $

P .;

\ ,

'r j $

- .P ) . , .

=

,,:< 4, > <

41 4 . . c' t ., ,- f ;

n -_

31 E

  • ' ' 1 #

g 1 ,! w , . , .

  • y'- '

..-e.'

..4. Y  :

7_

7g i T 't f . f I ' d #

s .A..

'h '9.-

, , a

' ' 5

-+

s -; . r ..n q rio e i

, 9 ', _ j- i r _

g g

b-- .

.g - m ,

. = .

+ n

~.~ .- - . - - . ~ . . -_-. - - ~ . - - - _ . - - - - - - -

s,.

3

.. i i-Attachssnt I to AECM-85/0035 Outlined below are MP&L responses to the NRC staff questions asked during the November 15,'1984 teleconference.

Question 1 Does a groundwater level above 109.0 ft. MSL impact the safe operation of CGNS? l

- MP&L Response.

A review of design calculations was performed to determine sensitivity of GGNS Unit 1 buildings to a maximum groundwater elevation of 114'-6". In

-reanalysing the' Unit _1. buildings, the following elements were considered:

a. The effect of a higher hydrostatic pressure on the overall building's stability, as well as on the structu.ral . adequacy of the various building components.
b. 'The effects of a higher groundwater table on the leak tightness integrity of the buildings.

The results of the reanalysis of~the Unit I buildings, assuming a maximum >

scoundwater elevation of 114'-6", indicated that (1) the structural integrity of.the Unit 1 buildings will not be impaired and (2) the

, . presence of the existing waterstops above elevation 109.0 ft will i i

. preserve the-leak tightness integrity. Therefore MP&L concludes that the m safety of the plant was not affected when DW-8 exceeded 109.0 ft. MSL by

1. 21 f t . -

.. Question'2 o u Would operation of the Unit 1 Dewstering Wells maintain the water level t

.below 109.0 ft. MSLT ,

MP&L Response Based ~en past history of'dewaterina'we11' operation, MP&L believes that the water level would-he maintained at a level below 109.0 fe. MSL for all

~

rainfall events up to a Probable Maximun Flood (Reference AECM-81/0343, dated September'3, 1981).

m Entremely heavy rainfalls were experienced during the January - July

_1983. time period in which the' perched aquifer exceeded 109.0 ft. MSL.' '

'These ratafalls were equivalent to a 1 la 200 year event- (see Attachment
21. la additten to these heavy. rains the Unit I construction dauntering

. 7

~

wolls were not operattag. Since only'eme well showed elevattens above

'100.0 ft..ISt, and by only 1.21 ft;,-it=is highly unlikely if all'.the wolle

.[

were operating that grounduetor elevattees would exceed 109.0 ft. MBL.

p 3, c9 m

,e a I' < ', A( 3

_4 .- './','

, s m . . . -

4., ,

1 t

s +- 5 , i? ,h_

9 Il I- j '] j

'- ~

L

'g

-,, n= 4,  ;,.
3. . ,

4

.a~'-

LJer44IIISCOS020702 - 1 ,- y u ;*

7a,i*an .

.c. .

. Attachm:nt i to AECM-85/0035 Question 3 Is there a connection between the perched aquifer and groundwater or is recharge to the perched aquifer limited to the percolation of rain water?

MP&L Response The maximum regional groundwater level recorded in the power block area is 84.0 ft. MSL. During normal Mississippi River elevation, the regional groundwater table ranges from 60 to 80 ft. MSL, normally sloping towards the river. However, a temporary reversal of groundwater elevations occurs during flood stages of the river with a maximum elevation of 103 ft.

MSL during the local Probable Maximum Flood. Perched groundwater levels recorded in the power block areas are generally below 100 ft. MSL with the highest measured being 113.0 ft. MSL at the ultimate heat sink. Since the regional groundwater level is normally below the perched groundwater level, the recharge of the perched aquifer is limited to percolation of rain water.

Question 4 What actions will be taken to avoid a similar incident in the future?

MP&L Response The construction dewatering system was installed to remove seepage of groundwater into the excavation and inflow of precipitation during construction. Upon completion of construction on Unit 1, the dewatering wells (DW-6, DW-7, DW-8) and SSW Basin well (DW-5) were deactivated.

As a precautionary measure against a similar incident in the future, the Unit 1 Wells (DW-6, DW-7, and DW-8) and SSW Basin well (DW-5) were restarted in November, 1983 and will continue until Unit 2 construction and backfilling activities are completed. Monitoring of the perched

' aquifer will continue for approximately one year following the completion i

of Unit 2. A groundwater contour map of the site area irdicating expected normal groundwater conditions during the operating life of the plant will be developed per FSAR Section 2.4.13.2.5.

1 I

l i

J0P14NISC85020702 - 2 b