IR 05000382/2022003

From kanterella
Revision as of 15:20, 9 November 2022 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Integrated Inspection Report 05000382/2022003
ML22300A103
Person / Time
Site: Waterford Entergy icon.png
Issue date: 11/01/2022
From: John Dixon
NRC/RGN-IV/DORS/PBD
To: Ferrick J
Entergy Operations
Dixon J
References
IR 2022003
Download: ML22300A103 (14)


Text

November 01, 2022

SUBJECT:

WATERFORD STEAM ELECTRIC STATION, UNIT 3 INTEGRATED INSPECTION REPORT 05000382/2022003

Dear John Ferrick:

On September 30, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Waterford Steam Electric Station, Unit 3. On October 18, 2022, the NRC inspectors discussed the results of this inspection with you and other members of your staff.

The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Signed by Dixon, John on 11/01/22 John L. Dixon, Jr., Chief Projects Branch D Division of Operating Reactor Safety Docket No. 05000382 License No. NPF-38

Enclosure:

As stated

Inspection Report

Docket Number: 05000382 License Number: NPF-38 Report Number: 05000382/2022003 Enterprise Identifier: I-2022-003-0007 Licensee: Entergy Operations, Inc.

Facility: Waterford Steam Electric Station, Unit 3 Location: Killona, LA 70057 Inspection Dates: July 1, 2022, to September 30, 2022 Inspectors: D. Childs, Resident Inspector T. Farina, Senior Operations Engineer A. Patz, Senior Resident Inspector Approved By: John L. Dixon, Jr., Chief Projects Branch D Division of Operating Reactor Safety Enclosure

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Waterford Steam Electric Station, Unit 3, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Unit 3 began the inspection period at rated thermal power and remained at or near rated thermal power for the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated the adequacy of the overall preparations to protect risk-significant systems from seasonal heavy rains and severe weather due to potential for hurricane development on August 31, 2022.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) emergency feedwater system trains A, B, and AB during and following maintenance on emergency feedwater pump B on July 28, 2022
(2) emergency diesel generator system train B while train A was inoperable during surveillance testing on September 6, 2022

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) fire area RAB 2-002, elevation +46.00' reactor auxiliary building main steam isolation valve passage and fire area RAB 3A-003, elevation +21.00' reactor auxiliary building vestibule on July 6, 2022
(2) fire area RAB 32-001, elevation -35.00' auxiliary component cooling water room and pipe penetration area on July 18, 2022
(3) fire area RAB 8B-001, elevation +21.00' reactor auxiliary building switchgear room B on August 12, 2022
(4) fire area RAB 17-001, elevation +21.00' reactor auxiliary building component cooling water pump B room, and fire area RAB 21-001, elevation +21.00' reactor auxiliary building component cooling water heat exchanger B room, on September 1, 2022
(5) fire area RAB 8A-001, elevation +21.00' reactor auxiliary building switchgear room A on September 2, 2022
(6) fire area RAB 25-001, elevation +21.00' reactor auxiliary building decon area on September 27, 2022

71111.06 - Flood Protection Measures

Inspection Activities - Internal Flooding (IP Section 03.01) (1 Sample)

The inspectors evaluated internal flooding mitigation protections in the:

(1) elevation +21.00' component cooling water pump and heat exchanger areas on September 1, 2022

71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance

Requalification Examination Results (IP Section 03.03) (1 Sample)

(1) The inspectors reviewed and evaluated the licensed operator examination failure rates for the requalification annual operating exams administered on August 30, 2022.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated licensed operator simulator training on September 20, 2022.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) engineered safety features actuation system train B following auxiliary component cooling water pump B failure to start during testing on September 21, 2022
(2) control room air handling system train B following failure of an electric relay on September 30, 2022

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) elevated green risk for motor-driven emergency feedwater pump B outage during the week of July 25, 2022
(2) planned yellow risk due to low-pressure safety injection and containment spray train B outages during the week of August 8, 2022
(3) elevated green risk due to unexpected plant protection system power supply failure during the week of September 6, 2022

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) component cooling water system following identification of inleakage on July 28, 2022
(2) reactor trip circuit breakers following surveillance failure on August 5, 2022
(3) feedwater ultrasonic flow meter following erratic indication and repair difficulties on September 8, 2022
(4) containment fan cooler train B following loss of motor control center 317B on September 22, 2022
(5) offsite power following automatic isolation of west switchyard bus on September 29, 2022

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the following post-maintenance testing activities to verify system operability and/or functionality:

(1) emergency feedwater pump A after planned maintenance on the motor on July 6, 2022
(2) emergency feedwater pump B after planned maintenance on July 28, 2022
(3) low-pressure safety injection train A header to reactor coolant loop 2A flow control valve SI-139A following planned maintenance on August 9, 2022
(4) containment spray train A header isolation valve CS-125A following planned solenoid replacements on August 11, 2022
(5) component cooling water pump B following corrective maintenance on August 18, 2022
(6) plant stack wide range radiation monitors following identification of incorrect reference values on September 9, 2022

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance testing activities to verify system operability and/or functionality:

Surveillance Tests (other) (IP Section 03.01) (2 Samples)

(1) dry cooling tower A diesel driven sump pump surveillance testing on August 31, 2022
(2) containment spray pump surveillance testing on September 29, 2022

Inservice Testing (IP Section 03.01) (1 Sample)

(1) steam generator 2 atmospheric dump valve inservice testing on July 21, 2022

71114.06 - Drill Evaluation

Drill/Training Evolution Observation (IP Section 03.02) (1 Sample)

The inspectors evaluated:

(1) a full site integrated drill for a simulated site area emergency on September 13,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS08: Heat Removal Systems (IP Section 02.07) ===

(1) Unit 3 (July 1, 2021, through June 30, 2022)

MS09: Residual Heat Removal Systems (IP Section 02.08) (1 Sample)

(1) Unit 3 (July 1, 2021, through June 30, 2022)

MS10: Cooling Water Support Systems (IP Section 02.09) (1 Sample)

(1) Unit 3 (July 1, 2021, through June 30, 2022)

71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)

(1) The inspectors reviewed the licensees corrective action program and maintenance rule tracking program for potential adverse trends in radiation monitor equipment performance and corrective actions that might be indicative of a more significant safety issue.

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On August 30, 2022, the inspectors presented the annual requalification exam inspection results to Van Ford, Superintendent, Operations Training, and other members of the licensee staff.

On October 18, 2022, the inspectors presented the integrated inspection results to John Ferrick and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection Type Designation Description or Title Revision or

Procedure Date

71111.01 Engineering W3F1-2015-0042 Flood Hazard Reevaluation Report 07/21/2015

Evaluations

71111.01 Procedures OP-901-521 Severe Weather and Flooding 340

71111.04 Procedures OP-009-002 Emergency Diesel Generator 360

71111.04 Procedures OP-009-003 Emergency Feedwater 312

71111.05 Calculations ECF91-010 Combustible Loading Calculation for Fire Area RAB 8 4

71111.05 Corrective Action CR-WF3-YYYY- 2022-05705

Documents NNNN

71111.05 Fire Plans RAB 17-001 Component Cooling Water Heat Exchanger B Fire Plan 9

71111.05 Fire Plans RAB 2-002 Main Steam Isolation Valve Passage 7

71111.05 Fire Plans RAB 21-001 Component Cooling Water Pump B Fire Plan 9

71111.05 Fire Plans RAB 25-001 RAB +21 Decon Area 9

71111.05 Fire Plans RAB 32-001 Auxiliary Component Cooling Water Room & Pipe 11

Penetration Area

71111.05 Fire Plans RAB 3A-003 Vestibule 4

71111.05 Fire Plans RAB 8A-001 Switchgear Room A 13

71111.05 Fire Plans RAB 8B-001 Reactor Auxiliary Building +21.00' elevation 14

71111.05 Miscellaneous TCP 22-110 Transient Combustible Permit for Fire Area RAB 8 04/11/2022

71111.05 Miscellaneous TCP 22-116 Transient Combustible Permit for Fire Zone RAB 8A 04/18/2022

71111.05 Procedures EN-DC-161 Control of Combustibles 24

71111.05 Procedures EN-DC-161 Control of Combustibles 25

71111.05 Procedures MM-006-106 Plant Door Maintenance 335

71111.05 Work Orders 52969317

71111.06 Calculations MNQ3-5 Flooding Analysis Outside Containment 6

71111.11A Miscellaneous N/A 2022 Annual NRC Operating Test Results 08/29/2022

71111.11Q Procedures EN-TQ-100 Operations Training Program Description 3

71111.11Q Procedures OP-902-000 Standard Post Trip Actions 17

71111.11Q Procedures OP-902-003 Loss of Offsite Power / Loss of Forced Circulation 11

71111.12 Corrective Action CR-WF3-YYYY- 2022-1562, 2022-3627, 2022-04666

Documents NNNN

71111.12 Miscellaneous SD-CC Component Cooling Water 25

Inspection Type Designation Description or Title Revision or

Procedure Date

71111.12 Miscellaneous SD-PPS Plant Protection System 22

71111.12 Miscellaneous W3-DBD-38 Safety Related HVAC - Control Room 302

71111.12 Procedures EN-FAP-LI-001 Performance Improvement Review Group (PRG) Process 19

71111.12 Procedures EN-LI-102 Corrective Action Program 47

71111.12 Procedures EN-LI-118 Causal Evaluation Process 35

71111.12 Procedures OP-903-068 Emergency Diesel Generator and Subgroup Relay 326

Operability Verification

71111.13 Corrective Action CR-WF3-YYYY- 2022-06304 09/06/2022

Documents XXXXX

71111.13 Miscellaneous Tagout : 2022-0106-LPSI Pump A 08/09/2022

71111.13 Miscellaneous Tagout: 2022-0107-CS Train A 08/09/2022

71111.13 Miscellaneous Tagout: 2022-0108- 0809/2022

71111.13 Procedures EN-OP-119 Protected Equipment Postings 16

71111.13 Work Orders 52980548, 52988875

71111.13 Work Orders 53000802 09/06/2022

71111.15 Corrective Action CR-WF3-YYYY- 2022-5674 08/05/2022

Documents XXXXX

71111.15 Engineering ER-W3-2002- Install Software to Improve Path Reliability on LEFM 10/31/2002

Changes 0519-000

71111.15 Miscellaneous DES-I-018 Feedwater Flow Measurement Instrumentation Specification 0

for Main Feedwater System

71111.15 Miscellaneous DES-I-018 Feedwater Flow Measurement Instrumentation Specification 0

for Main Feedwater System

71111.15 Miscellaneous Technical Technical Requirements Manual - Amendment 17 177

Requirements

Manual 0

71111.19 Procedures ME-004-330 4kV Induction Motor Maintenance 304

71111.19 Procedures ME-007-008 Motor Operated Valves 20

71111.19 Procedures MI-004-644 Testing of Solenoid Valves 1

71111.19 Procedures OP-903-050 Component Cooling Water and Auxiliary Component Cooling 44

Water Pump and Valve Operability Test

71111.19 Procedures OP-903-121 Safety Systems Quarterly IST Valve Tests 35

71111.19 Work Orders 52988875, 52952762, 52980548, 52946634, 52953000,

Inspection Type Designation Description or Title Revision or

Procedure Date

2946634, 53006370

71111.22 Corrective Action CR-WF3-YYYY- 2019-3025, 2019-3164, 2020-5920, 2020-6021, 2020-7200,

Documents NNNN 2021-0344, 2022-1819, 2022-4487

71111.22 Engineering EC 88384 Operability Input to CR-WF3-2020-6021 10/25/2020

Changes

71111.22 Engineering EC 88921 Rebaseline MS-116B 01/25/2021

Changes

71111.22 Engineering ECM97-059 Design Basis Review for Atmospheric Dump Valves MS- 001

Changes 116A and MS-116B

71111.22 Procedures CEP-IST-4 Standard on Inservice Testing 311

71111.22 Procedures ECS09-005 Air Operated Valves - Design Basis Accident Times 001

71111.22 Procedures OP-100-014 Technical Specification and Technical Requirements 364

Compliance

71111.22 Procedures OP-903-035 Containment Spray Pump Operability Check 34

71111.22 Procedures OP-903-120 Containment and Miscellaneous Systems Quarterly IST 035

Valve Tests

71111.22 Procedures SEP-WF3-IST-1 WF3 Inservice Testing Bases Document 010

71111.22 Procedures SEP-WF3-IST-2 WF3 Inservice Testing Plan 011

71111.22 Procedures W4-DBD-6 Main Steam System - design basis document 302

71111.22 Work Orders 52894192, 52955201, 52860841, 53002488, 552605,

2715847

10