IR 05000382/2023010

From kanterella
Jump to navigation Jump to search
Comprehensive Engineering Team Inspection Report 05000382/2023010
ML24029A254
Person / Time
Site: Waterford Entergy icon.png
Issue date: 01/31/2024
From: Vincent Gaddy
NRC/RGN-IV/DORS/EB1
To: Sullivan J
Entergy Operations
Cullum C
References
IR 2023010
Download: ML24029A254 (20)


Text

January 31, 2024

SUBJECT:

WATERFORD STEAM ELECTRIC STATION - COMPREHENSIVE ENGINEERING TEAM INSPECTION REPORT 05000382/2023010

Dear Joseph Sullivan:

On January 22, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Waterford Steam Electric Station and discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements and was determined to be Severity Level IV. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement; and the NRC Resident Inspector at Waterford Steam Electric Station.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Vincent G. Gaddy, Chief Engineering Branch 1 Division of Operating Reactor Safety Signed by Gaddy, Vincent on 01/31/24 Docket No. 05000382 License No. NPF-38

Enclosure:

As stated

Inspection Report

Docket No.

05000382

License No.

NPF-38

Report No.

05000382/2023010

Enterprise Identifier:

I-2023-010-0020

Licensee:

Entergy Operations, Inc.

Facility:

Waterford Steam Electric Station

Location:

Killona, LA

Inspection Dates:

November 27, 2023 to December 15, 2023

Inspectors:

J. Braisted, Senior Reactor Inspector

D. Bryen, Reactor Inspector

W. Cullum, Senior Reactor Inspector

C. Franklin, Reactor Inspector

N. Mentzer, Reactor Inspector

E. Rosario, Reactor Inspector

F. Thomas, Reactor Inspector

C. Young, Senior Reactor Analyst

Approved By:

Vincent G. Gaddy, Chief

Engineering Branch 1

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a Comprehensive Engineering Team Inspection at Waterford Steam Electric Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Verify the Adequacy of Design of the Alternate Source Term Dose Consequence Analysis and Provide Complete and Accurate Information to the Commission Cornerstone Significance/Severity Cross-Cutting Aspect Report Section Barrier Integrity Green Severity Level IV NCV 05000382/2023010-01 Open/Closed None (NPP)71111.21M The inspectors identified a Green finding and associated Severity Level IV Non-cited Violation (NCV) of Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Appendix B, Criterion III, Design Control, and 10 CFR 50.9, Completeness and Accuracy of Information, when the licensee failed to verify the adequacy of design of the loss of coolant accident alternative source term radiological dose consequence analysis and provide related information to the Commission that was complete and accurate in all material respects.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

===71111.21M - Comprehensive Engineering Team Inspection The inspectors evaluated the following components and listed applicable attributes, permanent modifications, and operating experience:

Structures, Systems, and Components (SSCs) (IP section 03.01)===

(1) Safety Injection (SI) Sump Outlet Header A Isolation Valve SI-602A
  • Motor-operated valve (MOV) program documents, in-service testing (IST)plan, and SI system design basis document
  • Design bases review calculation for SI-602A, including evaluations of torque switch settings and weakest link
  • SI system piping and instrumentation diagram and the MOV electrical schematic diagram
  • Valve and actuator vendor manuals for installation, operation, and maintenance
  • Inservice testing records including procedures and results for position indication, leakage, opening, and closing
  • Diagnostic testing records including procedures and results
  • Maintenance work order history records and visual inspections
  • Visual inspection of the as-built configuration and material condition
(2) Refueling Water Storage Pool
  • Safety injection (SI) system design basis document
  • Calculations for refueling water storage pool (RWSP) volume design requirements and required submergence to prevent vortexing
  • Records of chemistry samples for temperature, boron concentration, and pH
  • SI system piping and instrumentation diagram
  • Maintenance work order history records of visual inspections
  • Visual inspection of the as-built configuration and material condition
(3) Component Cooling Water (CCW) Header A to B Supply Isolation Valve CC-200B
  • Air-operated valve (AOV) program documents, in-service testing (IST) plan, and CCW system design basis document
  • Design bases review calculation for CC-200B
  • CCW system piping and instrumentation diagram and the AOV electrical schematic diagram
  • Valve and actuator vendor manuals for installation, operation, and maintenance
  • Inservice testing records including procedures and results for position indication, opening, and closing
  • Diagnostic testing records including procedures and results
  • Maintenance work order history records and visual inspections
  • Visual inspection of the as-built configuration and material condition
(4) Component Cooling Water Surge Tank
  • Component Cooling Water (CCW) system design basis document
  • Calculations for CCW surge tank volume design requirements and required submergence to prevent vortexing
  • CCW Surge tank level & Makeup circuit design
  • Records of internal coating inspection, and CCW Chemistry controls including biocide,
  • CCW system piping and instrumentation diagram
  • Maintenance work order history records of visual inspections
  • Visual inspection of the as-built configuration and material condition
(5) Emergency Diesel Generator (EDG) A Room Exhaust Fan
  • EDG room ventilation system design basis document
  • Calculations for EDG heat load and required ventilation air flow
  • Records of EDG ventilation seismic qualification and system testing
  • EDG room ventilation system diagram
  • Maintenance work order history records and visual inspections
  • Design calculations
  • Design drawings
  • Diagnostic testing records including procedures and results
  • Maintenance work order history records
  • Visual inspection of the as-built configuration and material condition
(7) High Pressure Safety Injection Header Cold Leg Flow Control Isolation Valve SI-226A
  • Motor-operated valve (MOV) program documents, in-service testing (IST)plan, and SI system design basis document
  • Design bases review calculation for SI-226A, including evaluations of torque switch settings and weakest link
  • SI system piping and instrumentation diagram
  • Valve and actuator vendor manuals for installation, operation, and maintenance
  • Inservice testing records including procedures and results for position indication, opening, and closing
  • Diagnostic testing records including procedures and results
  • Maintenance work order history records and visual inspections
  • Visual inspection of the as-built configuration and material condition
(8) Emergency Feedwater (EFW) Motor Driven Pump A
  • EFW System design basis document
  • Calculations for pump head curve and NPSH
  • EFW system piping and instrumentation diagram
  • Pump vendor manuals for installation, operation, and maintenance
  • Inservice testing records including procedures and results
  • Maintenance work order history records and visual inspections
  • Visual inspection of the as-built configuration and material condition (9)480 V Switchgear Bus 3B31-S (SSD-ESWGR-31B)
  • Visual inspection of switchgear for as-built configuration and material condition
  • Environmental conditions for equipment
  • Voltage analysis and short circuit calculations
  • Protection settings and coordination study
  • Vendor manual for conformance with manufacturer instructions for installation and maintenance
  • Preventive maintenance and periodic verification testing
  • Component maintenance history
  • Schematic and wiring drawings
  • System health report
(10) DC switchgear 3B, DC Power Distribution Panel 3B-DC-S (DC-EPDP-B-DC):
  • System health report
  • Maintenance, inspection, and testing procedures
  • Component maintenance history
  • Schematic and wiring drawings
  • Vendor operating and maintenance requirements
  • Short circuit calculations, coordination studies, load flow calculations, and maintenance activities to ensure they were appropriate for the design of the Class 1E DC 3B-DC-S Power Distribution Panel
  • Corrective action documents

Modifications (IP section 03.02) (5 Samples)

(1) EC-77544, Broad Range Gas Monitor (BRGM) System Replacement
(2) EC-83354, Replace SI-512A with a Swing Check Valve
(3) EC-91881, Substitute CPC D RTD Input
(4) EC-83913, Main Steam Isolation Valve (MSIV) Solenoid Valve Upgrade
(5) EC-84942, AMTEK Solid State Controls Component Substitution Justification

10 CFR 50.59 Evaluations/Screening (IP section 03.03) (18 Samples)

(1) EC-75220, Evaluation of Impacted Safety Related Calculations
(2) EC-77544, Broad Range Gas Monitor System Replacement
(3) EC-88102, Update to Consider Normal Shutdown with LOOP as Bounding CCW Pump Runout Case
(4) EC-88373, Stroke Time Evaluation of Various SI, CVR, SBV Valves
(5) EC-90132, Clarification of Seismic Design Requirements for Piping and Valves Upstream of EBA Tank Isolation Valves (EBA-203, EBA-204, 4BA1/2-5)
(6) EC-90302, Issue SPEC-21-00004-W WF3 Essential Chiller Specification per EC-

===90302 for Essential Chillers RFRMCHL0001 A, B, C

(7) EC-91867, Minimum Required Wall Thickness for 132" CW Lines and Selected Tanks
(8) EC-92876, Evaluate Use of Alloy 690 Thermowells for Cold Leg RTDS
(9) EC-94658, FHD-232A Leak Repair Evaluation
(10) EC-93448 Screen, Revision of Calc and Spec of Battery A and AB
(11) EC-91881, Substitute CPC D RTD Input
(12) PAD-OP-902-005 Screen, Station Blackout Recovery Procedure Change
(13) PAD-OP-901-310 Screen, Loss of Train A Safety Bus Procedure Change
(14) EC-93747, Generate AOV Design Basis Calculation for PMU-144
(15) EC-95077, RCS FME - RCITE0112CD Thermowell and RTD
(16) EC-94858, ECE91-053 12IAV55C Acceptance Range Change
(17) EC-95070, Temporary Load Bank for Integrated Diesel Test A Train Turbine Control System
(18) EC-90044, Temp Indication Switch Standard EN-IC-S-025-W

Operating Experience Samples (IP section 03.04)===

(1) OE-NOE-2022-00067, INPO IER L3 22-3 Power Excursion and Delayed Scram During Zero-Power Physics Testing
(2) OE-NOE-2020-00166, IRIS 475373 Manual Scram due to Electro-Hydraulic Control System Levels
(3) OE-NOE-2022-00192, IRIS 535302 Loss of Power to Emergency Class Buses

INSPECTION RESULTS

Failure to Verify the Adequacy of Design of the Alternate Source Term Dose Consequence Analysis and Provide Complete and Accurate Information to the Commission Cornerstone Significance/Severity Cross-Cutting Aspect Report Section Barrier Integrity Green Severity Level IV NCV 05000382/2023010-01 Open/Closed None (NPP)71111.21M The inspectors identified a Green finding and associated Severity Level IV Non-cited Violation (NCV) of Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Appendix B, Criterion III, Design Control, and 10 CFR 50.9, Completeness and Accuracy of Information, when the licensee failed to verify the adequacy of design of the loss of coolant accident alternative source term radiological dose consequence analysis and provide related information to the Commission that was complete and accurate in all material respects.

Description:

Waterford submitted license amendment request (LAR) 198 (ML042020294) to the NRC for full implementation of an alternative radiological source term (AST) for calculating offsite radiological doses and doses to control room personnel during design basis accidents (DBAs). The NRC approved the request on March 29, 2005, in a letter to Waterford (ML050890248) which also contained its safety evaluation of the change. NRC Regulatory Guide (RG) 1.183, Alternative Radiological Source Terms for Evaluating Design Basis Accidents at Nuclear Power Reactors, dated July 2000, provides guidance on methods acceptable to the NRC for implementing an AST, and Waterford described use of this guidance in their original LAR submittal in addition to other relevant correspondence submitted to the NRC (ML042470194, ML042890193, and ML043010129). As stated in RG 1.183, full implementation of the AST revises the plant licensing basis to specify the AST in place of the previous accident source term, and the DBA loss of coolant accident (LOCA)must be re-analyzed using the guidance in Appendix A. However, licensees may use methods other than those described in RGs (i.e., exceptions) for compliance with regulations if they provide an acceptable basis.

In the NRCs safety evaluation of the dose consequences of Waterfords DBA LOCA, the NRC stated, based upon information provided in correspondence, that Waterford performed an analysis of the radiological consequences of a (large break) LBLOCA for the (extended power uprate) EPU conditions using the guidance on source term and activity release in RG 1.183. Waterford evaluated three release pathways in the LBLOCA dose analysis: (1)leakage to the reactor auxiliary building serviced by the controlled ventilation area system (CVAS);

(2) leakage to the secondary containment that is serviced by the shield building ventilation system (SBVS); and
(3) leakage from the containment directly to the environment.

Additionally, emergency core cooling system (ECCS) components outside containment were assumed to leak 0.5 gallons per minute (gpm) of containment sump water into areas serviced by the CVAS, starting when the ECCS goes into recirculation mode. The CVAS and SBVS are safety-related systems that may be credited to limit the radiological dose consequences offsite and in the control room in accordance with RG 1.183.

Appendix A to RG 1.183 describes the assumptions that are acceptable to the NRC for evaluating the radiological consequences of a LOCA at a light water reactor. Section 5 of Appendix A provides the specific details for evaluating engineered safety feature (ESF)system leakage. These are systems that recirculate sump water outside of the primary containment, such as the ECCS at Waterford. The release source includes leakage through valve packing glands, pump shaft seals, flanged connections, and other similar components. The source may also include leakage through valves isolating interfacing systems. The guidance goes on to state that consideration should be given to leakage through valves isolating ESF recirculation systems from tanks vented to atmosphere, e.g.,

ECCS pump miniflow return to the refueling water storage tank. At Waterford, the equivalent tank is called the refueling water storage pool (RWSP). Finally, leakage should be taken as two times the sum of the simultaneous leakage from all components in the ESF recirculation systems.

The inspectors reviewed Procedure OP-903-110, Reactor Auxiliary Building (RAB) Systems Fluid Leak Test, which Waterford cited as the basis for the ESF system leakage criteria of 0.5 gpm. The purpose of OP-903-110 is to provide leak rate tests on those portions of ESF systems outside containment that could contain highly radioactive fluid during a serious transient or accident. The inspectors observed that the ECCS pumps take suction from the RWSP and return it to the RWSP through the miniflow return lines during the test. In other words, certain valves that would normally be closed and isolate the RWSP from the ECCS during the recirculation phase of a LOCA are open during the test, so the test does not verify that the system leakage criteria is met. Additionally, the inspectors observed that the RWSP is not vented to the CVAS but to the nonsafety-related RAB normal ventilation system whose design does not allow it to be credited to limit radiological dose consequences in accordance with RG 1.183. Finally, the inspectors reviewed Calculation EC-S92-001, Revision 1, which was Waterfords evaluation of NRC Information Notice 91-56, Potential Radioactive Leakage to Tank Vented to Atmosphere, but had since been retired. The inspectors observed that valves SI-106A(B), SI-107A(B), SI-120A(B), SI-121A(B), SI-412A(B), SI-417A(B), and CS-118A(B) were all listed as potential leak paths from the containment sump to the RWSP. Since RG 1.183 specifically stated to consider unfiltered leakage through isolation valves into tanks, such as the RWSP, and the Waterford analysis did not consider this source, nor state any exceptions, the inspectors concluded that the leakage through the valves was an unanalyzed and unfiltered release pathway and, consequently, Waterford had provided incomplete and inaccurate information to the NRC.

The inspectors also reviewed the NRCs safety evaluation of LAR 186 (ML030760620)regarding realignment of RWSP boundary isolation valves to the nonsafety-related RWSP purification system. This LAR authorized Waterford to implement a design change where two normally closed manual valves (FS-423 and FS-404) were altered to normally open. In the safety evaluation, the NRC concluded that Waterford would have adequate time to isolate the RWSP either from a pipe crack in the RSWP purification system concurrent with a LOCA or from draw-down by the RWSP purification system aligned to the spent fuel pool (SFP) during a LOCA before reaching the analytical limit of the RWSP. The inspectors also observed that the need to isolate the RWSP from the RWSP purification system is time-critical and the operation is performed locally. Though the RWSP purification system is not part of the ECCS, it is hydraulically connected to the RWSP at the onset of a LOCA, and the inspectors observed that the operator action to close the isolation valves may not occur until after Waterford transitioned to recirculation from the containment sump. Additionally, portions of the purification system are in areas not serviced by the CVAS, and Waterford does not implement a purification system leak test like OP-903-110. The inspectors also observed that EC-S92-001 identified that SI-347 is another normally open valve with potentially similar consequences. Since RG 1.183 specifically stated to consider leakage through valve packing, pump seals, flanged connections, and valves isolating other systems, such as the RWSP purification system, and the Waterford analysis did not consider this source, nor state any exceptions, the inspectors concluded that the leakage through the valves was another unanalyzed and unfiltered release pathway and, consequently, Waterford had provided incomplete and inaccurate information to the NRC.

Corrective Actions: The licensee performed an initial evaluation of the unanalyzed release pathways and determined the additional dose offsite and to the control room would remain below the acceptance criteria in 10 CFR 50.67, "Accident Source Term," for allowable dose. Additionally, the unanalyzed release pathways are serviced by the nonsafety-related RAB normal ventilation system which is filtered but not to the degree that RG 1.183 would allow crediting it for filtration.

Corrective Action References: CR-WF3-2023-18180

Performance Assessment:

Performance Deficiency: The inspectors determined that the failure to verify the adequacy of design of the LOCA AST offsite and control room radiological dose consequence analysis in accordance with 10 CFR Part 50, Appendix B, Criterion III, was a performance deficiency. This performance deficiency resulted in the licensee providing incomplete and inaccurate information to the NRC in accordance with 10 CFR 50.9.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Design Control attribute of the Barrier Integrity cornerstone and adversely affected the cornerstone objective to provide reasonable assurance that physical design barriers protect the public from radionuclide releases caused by accidents or events. Specifically, the licensee failed to verify the adequacy of design of the radiological dose consequence analysis when it failed to account for leakage of contaminated water through isolation valves to the refueling water storage pool which vents to an area of the reactor auxiliary building that represents an unfiltered release pathway and additional dose offsite and to the control room.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The inspectors determined the finding was of very low safety significance (Green) because the finding only represented a degradation of the radiological barrier function provided for the control room, auxiliary building, or spent fuel pool.

Cross-Cutting Aspect: Not Present Performance. No cross-cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance.

Enforcement:

The ROPs significance determination process does not specifically consider the regulatory process impact in its assessment of licensee performance. Therefore, it is necessary to address this violation which impedes the NRCs ability to regulate using traditional enforcement to adequately deter non-compliance.

Severity: This violation was less serious than the Severity Level III violation example described by Section 6.9.c.1 of the NRC Enforcement Policy, which stated that Inaccurate or incomplete information is provided or maintained. If this information had been completely and accurately provided or maintained, it would likely have caused the NRC to reconsider a regulatory position or undertake a substantial further inquiry. Specifically, the inspectors determined, based upon a review of multiple, approved AST LAR submittals for other licensees, which did include leakage through RSWP isolation valves in their LOCA analyses, that the NRC would not likely have caused the NRC to reconsider a regulatory position or undertake a substantial further inquiry had the information been complete and accurate. The Policy did not contain an applicable Severity Level IV violation example. However, the inspectors determined the violation met the Policy definition of Severity Level IV in that it created the potential of a more than minor safety consequence because it resulted in an increase in radiological dose offsite and to the control room.

Violation: Title 10 CFR Part 50, Appendix B, Criterion III, Design Control, states, in part, that measures shall be established for verifying or checking the adequacy of design, such as by the performance of design reviews, by the use of alternate or simplified calculational methods, or by the performance of a suitable testing program.

Contrary to the above, between July 15, 2004, and December 11, 2023, the licensee failed to verify or check the adequacy of design of its LOCA AST offsite and control room radiological dose analysis. Specifically, licensee did not include in its source term, two unfiltered release pathways through isolation valves to the RWSP and through the RWSP purification system when implementing the guidance described in RG 1.183.

10 CFR 50.9, Completeness and Accuracy of Information, states, in part, that information provided to the Commission by a licensee shall be complete and accurate in all material respects.

Contrary to the above, between July 15, 2004, and October 19, 2004, the licensee failed to provide information to the Commission that was complete and accurate in all material respects. Specifically, in the licensing correspondence listed below, the licensee documented that they had performed the radiological dose consequence analysis using the guidance of RG 1.183, they had taken some exceptions to RG 1.183, and that ECCS was assumed to leak 0.5 gpm outside containment but to areas of the RAB serviced by the CVAS. However, the dose consequence analysis did not conform to the guidance in RG 1.183 because it did not include release pathways (i.e., ECCS leakage through RSWP isolation valves and leakage through the RWSP purification system) that should have been analyzed. Though Waterford did take exceptions to RG 1.183, the exceptions were not related to leakage through isolation valves. Additionally, these release pathways involved releases to areas of the RAB not serviced by the CVAS and were, therefore, unfiltered. Because the licensee did not follow the guidance of RG 1.183 by failing include the unfiltered release pathways in their dose analysis or provide an acceptable alternative to excluding the unfiltered release pathways, the information provided to the NRC was incomplete and inaccurate. Finally, this information was material to the NRC because full implementation of the AST revised the licensing basis for Waterfords accident source term and the addition of these unfiltered release pathways increases the analyzed radiological dose offsite and to the control room.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On January 22, 2024, the inspectors presented the Comprehensive Engineering Team Inspection results to Joseph Sullivan and other members of the licensee staff.
  • On December 14, 2023, the inspectors presented the exit meeting for the Comprehensive Engineering Team Inspection results to Joseph Sullivan, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

3-H

Diesel Generator Room Ventilation

EC-24731

Emergency Feedwater System Head Curves

EC-E91-055

AC Short Circuit Calculations

EC-E91-251

Short Circuit Study For PDP 3B-DC-S & PDP 3B1-DC-S

EC-I95-019

Plant Protection System Indication and Recording Loop

Uncertainty Calculation

EC-M84-001

Tank Volume vs. Level Tables

EC-M92-027

MOV Design Basis Review Calculation No. SI.003

EC-M92-037

MOV Design Basis Review Calculation No. SI.002

EC-M97-026

Required Submergence to Prevent Vortexing in the RWSP

EC-M97-044

Design Basis Review for CCW Isolation Valves CC-200A(B),

CC-501, CC-562, CC-563, and CC-727

EC-M98-008

RWSP Volume Design Requirements

EC-S92-001

NRC IN 91-56: Post-LOCA Releases Through RWSP

EC-S97-020

Toxic Chemical Analysis to Assess Control Room

Habitability

EC90-050

Degraded Voltage Relay Setpoint & Plant Load Study

EC91-056

Relay Settings and Coordination Curves for 6.9kV 4.16kV

and 480 buses

ECE13-001

480 VAC Masterpact NT/NW Micrologic 5.0A Device

Settings and Coordination Study

ECE17-001

EF# Arc Flash Risk Assessment

ECE91-050

Degraded Voltage Relay Setpoint & Plant Load Study

ECE91-194

Load Study For PDP-3B-DC-S and 3B1-DC-S

ECM21-002

Minimum Required Wall Thickness for 132 CW lines and

Selected Tanks

ECS09-005

Air-Operated Valves - Design Basis Accident Times

EE2-11-05

Calculation of Fault Clearing Time of Protective Devices

Used as Back-up Protection of Electrical Penetration

MNQ-10-12

NPSH Available for EFW Pumps

71111.21M

Calculations

MNQ9-2

Component Cooling Water System

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

MNQ9-46

NPSH Available for CCW Pumps

Corrective Action

Documents

Condition Report

(CR-WF3-)

2014-03711, 2015-01904, 2021-00147, 2021-00244, 2023-

15701, 2023-17135, 2022-01335, 2023-15663, 2019-01534,

20-00258, 2021-05371, 2021-05624, 2023-15971, 2022-

03722, 2023-13732, 2023-15260, 2020-06272, 2019-08585,

23-17364, 2022-02962, 2023-00351, 2023-00867, 2023-

290, 2023-15683, 2023-16984,

Corrective Action

Documents

Resulting from

Inspection

Condition Report

(CR-WF3-)

23-17870, 2023-17880, 2023-17881, 2023-17892, 2023-

17910, 2023-17911, 2023-17912, 2023-18092, 2023-18180,

23-18189, 2023-18230, 2023-18042, 2023-17930, 2023-

17926

1564-1630

Containment Spray Pumps Design Curve

74470-772-001

Instrument Nozzles, Waterford III Piping, Component Code

  1. 91-0118-0001

B289, Sheet 109

Power Distribution & Motor Data, 125 V D-C Distribution

Panel 3B-DC-S

B289, Sheet 21

Power Distribution and Motor Data 480V SWGR

[Switchgear] 3B31-S One Line Diagram

B289, Sheet 21-1

Power Distribution and Motor Data, 480V SWGR

[Switchgear] 3B31-S One Line Diagram

B289, Sheet

21A1

Power Distribution & Motor Data, 480V Switchgear 3B31-S

Programmer Settings

B424

Control Wire Diagram: Component Cooling Water Isolation

and Makeup

ESSE-BA-IC144

Main Control Room Emergency Breathing Air Piping

F42932

16" Type 9220 Valve Assembly w/Bettis 732C-SR80-M3

Actuator

D

G160

Flow Diagram: Component Closed Cooling Water System

G163

Flow Diagram Containment Spray & Refueling Water

Storage Pool

G167

Flow Diagram Safety Injection System

G195

Piping Diagram Safety Injection System

G287, Sheet 1

25 VDC and 120 VAC One Line Diagram

Drawings

H33760-1201

Sensor, Temperature

C

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

L-3439

Component Cooling Water Surge Tank

09/23/1977

EC 39363

MOV Design Basis Review Calculation NO SI.003

EC 75220

Evaluation of Impacted Safety Related Calculations

EC 77544

Broad Range Gas Monitor (BRGM) System Replacement

EC 83354

Replace SI-512A with a Swing Check Valve

EC 83913

MSIV Solenoid Valve Upgrades

EC 84529

Planned FCR for EC-83913 - MSIV Solenoid Valve Upgrade

- Incorporate Vendor Supplied Documentation

EC 84942

AMTEK Solid State Controls Component Substitution

Justification

000

EC 88102

Update to Consider Normal Shutdown with LOOP as

Bounding CCW Pump Runout Case

EC 88373

Stroke Time Evaluation of Various SI, CVR, and SBV Valves

EC 90044

Temperature Indication Switch Standard EN-IC-S-025-W

000

EC 90132

Clarification of Seismic Design Requirements for Piping and

Valves Upstream of EBA Tank Isolation Valves (EBA-203,

EBA-204, 4BA1/2-5)

EC 91114

MOV Design Basis Review Calculation No. SI.003

EC 91426

Evaluation of EC-M89-002 to Increase Supply Pressure for

N2 Accumulators III and IV

EC 91867

Minimum Required Wall Thickness for 132" CW Lines and

Selected Tanks

EC 92876

Evaluate Use of Alloy 690 Thermowells for Cold Leg RTDs

EC 93747

Generate Air Operated Valve Design Basis Calculation for

PMU-144

EC 94658

FHD-232A Leak Repair Evaluation

EC 94858

ECE91-053 12IAV55C Acceptance Range Change

EC 95070

Temporary Load Bank for Integrated Diesel Test A Train

Turbine Control System

EC 95077

RCS Foreign Material Evaluation - RCITE0112CD

Thermowell and RTD CR-WF3-2022-3722 - Evaluation for

Continued Operation

Engineering

Changes

ER-W3-99-0184-

01-02

Weld Repair of Inconel Instrument Nozzles on the Hot Legs

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Engineering

Evaluations

22-01

Substitute CPC D RTD Input RC ITE0112CD1 with RC

ITE0115-1

457002467

Paul Munroe Enertech MSIV Pump Valve

LOU-1564.108

EBASCO Purchase Specification for Main Steam Isolation

Valves

08/02/1984

LOU-1564.724

EBASCO Purchase Specification for Miscellaneous Shop

Fabricated Tanks

09/14/1984

SEP-WF3-IST-1

WF3 Inservice Testing Bases Document

SEP-WF3-IST-2

WF3 Inservice Testing Plan

SEP-WF3-IST-3

WF3 Inservice Testing Cross Reference Document

TCABP

Time Critical Action Program Bases

TD-B015.0045

Babcock and Wilcox CCW and ACCW Pump Model

2X14X16 DE Manual

TD-B237.0195

GH Bettis Service Instructions, Disassembly, & Reassembly

for Spring Return Series Pneumatic Actuators

TD-C173.0015

C & D AutoReg Charger Handbook, 3 Phase, 6 Pulse SCR

Chargers

TD-C173.0025

C & D Standby Battery Vented Cell Installation & Operating

Instructions, RS-1476, Section 12-800

TD-F130.0015

Fisher Controls Valve Bodies

TD-F130.0015

Fisher Controls Valves Bodies

TD-G080.0155

General Electric Low Voltage Power Circuit Breakers,

Various Instructions

TD-L200.0045

Limitorque Type SMB Instruction & Maintenance Manual

Bulletin SMBI-82D

TD-S250.0025

Solid State Controls Ferroresonant UPS Technical Manual

Number 95-006000-90 Rev. B 9/91

TD-W120.3095

Westinghouse Molded Case Circuit Breakers Series C, K-

Frame, For Type DK, KDB, KD, HKD, KDC, KW, HKW,

KWC

W3-DBD-001

Safety Injection System

305

W3-DBD-003

Emergency Feedwater System

W3-DBD-008

Electrical Distribution (DC Portion) Design Basis Document

301

Miscellaneous

W3-DBD-011

Electrical Distribution (AC Portion) Design Basis Document

2

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

W3-DBD-14

Safety Related, Air Operated Valves

304

W3-DBD-4

Component Cooling Water, Auxiliary Component Cooling

Water

307

EN-DC-115-01

Industry Standard Design Process (IP-ENG-001)

EN-DC-312

Motor Operated Valve (MOV) Test Data Review

EN-LI-100

Process Applicability Determination

EN-MA-118

Foreign Material Exclusion

EN-OP-103

Reactivity Management Program

EN-OP-115

Conduct of Operations

EN-OP-120

Operator Fundamentals Program

EN-OP-123

Time Critical Action Program Standard

ME-003-330

480 Volt G.E. Switchgear Breakers

318

OP-002-003

Component Cooling Water

2

OP-002-006

Fuel Pool Cooling and Purification

331

OP-010-003

Plant Startup

365

OP-010-005

Plant Shutdown

347

OP-0101-007

Plant Cooldown

007

OP-901-212

Rapid Plant Power Reduction

24

OP-901-310

Loss of Train A Safety Bus

314

OP-901-311

Loss of Train B Safety Bus

2

OP-901-510

Component Cooling Water System Malfunction

306

OP-901-511

Instrument Air Malfunction

OP-902-000

Standard Post Trip Actions

OP-902-005

Station Blackout Recovery Procedure

OP-902-008

Functional Recovery Procedure

OP-902-009

Emergency Operating Procedure Standard Appendices

23

OP-903-001

Technical Specification Surveillance Logs

105

OP-903-014

Emergency Feedwater Flow Verification

318

OP-903-046

Emergency Feed Pump Operability Check

25

OP-903-118

Primary Auxiliaries Quarterly IST Valve Tests

OP-903-121

Safety System Quarterly IST Valve Tests

OP-903-129

Component Cooling Water Makeup Pump Operability Check

Procedures

OP-904-004

Turbine Miscellaneous Test and Checks

2

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

UNT-006-033

Technical Specifications Surveillance Frequency List

Work Orders

Work Order (WO-

)

00019593, 00019634, 00019649, 52873452, 52944019,

2960918, 52960918, 53034122, 00495839, 00167498,

00514233, 00565026, 00026241, 00026243, 00298246,

00050249, 00563831, 00563832, 51794244, 52984649,

2333000, 52364836, 52487650, 52504349, 52544989,

2575173, 52581739, 52609098, 52645886, 52667983,

2675538, 52689470, 52691659, 52778435, 52881422,

2832648, 52944180, 52962382, 52962657, 54008005,

00504476, 00504477, 00527322, 53033253, 52958193,

2963037, 53002842, 00536432, 54032998, 53036041,

2947469, 52968126, 54003050