MONTHYEARIR 05000382/20244022024-10-10010 October 2024 Security Baseline Inspection Report 05000382/2024402 Public IR 05000382/20244032024-10-0909 October 2024 Security Baseline Inspection Report 05000382/2024403 IR 05000382/20240112024-10-0101 October 2024 State Fire Protection Team Inspection Report 05000382/2024011 IR 05000382/20230042024-09-27027 September 2024 Amended Integrated Inspection Report 05000382/2023004 IR 05000382/20253012024-09-0303 September 2024 Notification of NRC Initial Operator Licensing Examination 05000382/2025301 IR 05000382/20240052024-08-21021 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Waterford Steam Electric Station, Unit 3 Report 05000382/2024005 IR 05000382/20240132024-08-20020 August 2024 Notice of Violation; NRC Inspection Report 05000382/2024013 ML24228A2612024-08-20020 August 2024 Notice of Violation; NRC Inspection Report 05000382/2024013 IR 05000382/20240022024-08-0808 August 2024 Integrated Inspection Report 05000382/2024002 ML24141A1012024-05-20020 May 2024 Amended Integrated Inspection Report 05000382/2023004 IR 05000382/20240012024-05-0606 May 2024 Integrated Inspection Report 05000382/2024001 IR 05000382/20244012024-03-18018 March 2024 Material Control and Accounting Program Inspection Report 05000382/2024401 IR 05000382/20230062024-02-28028 February 2024 Annual Assessment Letter for Waterford Steam Electric Station, Unit 3 Report 05000382/2023006 ML24039A1992024-02-12012 February 2024 – Integrated Inspection Report 05000382/2023004 IR 05000382/20230102024-01-31031 January 2024 Comprehensive Engineering Team Inspection Report 05000382/2023010 IR 05000382/20230032024-01-23023 January 2024 Acknowledgment of Reply to a Notice of Violation NRC Inspection Report 05000382/2023003 ML23312A1832023-11-14014 November 2023 Integrated Inspection Report 05000382/2023003 and Notice of Violation IR 05000382/20234012023-10-0404 October 2023 Cyber Security Inspection Report 05000382/2023401 (Cover Letter Only) IR 05000382/20230052023-08-21021 August 2023 Updated Inspection Plan for Waterford Steam Electric Station, Unit 3 - (Report 05000382/2023005) IR 05000382/20233012023-08-15015 August 2023 NRC Initial Operator Licensing Examination Approval 05000382/2023301 IR 05000382/20230022023-08-0808 August 2023 Integrated Inspection Report 05000382/2023002 IR 05000382/20234022023-08-0707 August 2023 NRC Security Inspection Report 05000382/2023402 (Full Report) IR 05000382/20230402023-07-12012 July 2023 Revised 95001 Supplemental Inspection Report 05000382/2023040, Exercise of Enforcement Discretion, and Follow-Up Assessment Letter ML23158A1042023-06-0808 June 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000382/2023401 ML23145A2272023-06-0202 June 2023 95001 Supplemental Inspection Report 05000382/2023040, and Exercise of Enforcement Discretion IR 05000382/20230012023-04-24024 April 2023 Integrated Inspection Report 05000382/2023001, Independent Spent Fuel Storage Installation Report 07200075/2023001, and Exercise of Enforcement Discretion IR 05000382/20234032023-04-17017 April 2023 Security Baseline Inspection Report 05000382/2023403 IR 05000382/20220062023-03-0101 March 2023 Annual Assessment Letter for Waterford Steam Electric Station, Unit 3, (Report 05000382/2022006) IR 05000382/20230902023-02-0101 February 2023 Final Significance Determination of a White Finding, NOV, and Follow-Up Assessment Letter; NRC Inspection Report 05000382/2023090 IR 05000382/20220042023-01-26026 January 2023 Integrated Inspection Report 05000382/2022004 and Independent Fuel Storage Installation Inspection Report 07200075/2022001 IR 05000382/20220912023-01-12012 January 2023 Emergency Preparedness Inspection Report 05000382/2022091 and Preliminary White Finding and Apparent Violation IR 05000382/20220032023-01-0505 January 2023 Revised Integrated Inspection Report 05000382/2022003 IR 05000382/20220132022-11-28028 November 2022 Design Basis Assurance Inspection (Programs) Inspection Report 05000382/2022013 ML22300A1032022-11-0101 November 2022 Integrated Inspection Report 05000382/2022003 IR 05000382/20220022022-11-0101 November 2022 Revised Integrated Inspection Report 05000382/2022002 IR 05000382/20224022022-10-24024 October 2022 NRC Security Inspection Report 05000382 2022402 IR 05000382/20220122022-09-16016 September 2022 Digital Instrumentation and Control Modification Inspection Report 05000382/2022012 IR 05000382/20224032022-09-14014 September 2022 NRC Security Inspection Report 05000382 2022403 IR 05000382/20220902022-09-12012 September 2022 Final Significance Determination of a White Finding, Notice of Violation and Follow-Up Assessment Letter, NRC Insp Rprt 05000382/2022090 IR 05000382/20220102022-08-24024 August 2022 Biennial Problem Identification and Resolution Inspection Report 05000382/2022010 ML22229A0662022-08-17017 August 2022 Security Baseline Inspection Report 05000382/2022403 ML22217A1112022-08-0909 August 2022 Integrated Inspection Report 05000382/2022002 IR 05000382/20220112022-07-14014 July 2022 License Renewal Phase 1 Inspection Report 05000382/2022011 IR 05000382/20224012022-06-16016 June 2022 Security Baseline Inspection Report 05000382/2022401 IR 05000382/20225012022-06-11011 June 2022 Emergency Preparedness Inspection Report 05000382/2022501 and Preliminary White Finding IR 05000382/20220012022-05-17017 May 2022 Reissue IR 05000382/2022001 ML22124A3062022-05-0808 May 2022 Integrated Inspection Report 05000382/2022001 IR 05000382/20223012022-03-28028 March 2022 NRC Examination Report 05000382/2022301 IR 05000382/20210142022-03-0909 March 2022 Digital Instrumentation and Control Modification Inspection Report 05000382/2021014 IR 05000382/20210062022-03-0202 March 2022 Annual Assessment Letter for Waterford Steam Electric Station, Unit 3 - (Report 05000382/2021006) 2024-09-03
[Table view] Category:Letter
MONTHYEARIR 05000382/20244022024-10-10010 October 2024 Security Baseline Inspection Report 05000382/2024402 Public IR 05000382/20244032024-10-0909 October 2024 Security Baseline Inspection Report 05000382/2024403 IR 05000382/20240112024-10-0101 October 2024 State Fire Protection Team Inspection Report 05000382/2024011 IR 05000382/20230042024-09-27027 September 2024 Amended Integrated Inspection Report 05000382/2023004 ML24229A1042024-09-25025 September 2024 Integrated Inspection Report 05000382/2023004, Disputed Non-Cited Violation Revised ML24268A1132024-09-24024 September 2024 Acknowledgment of Response to NRC Inspection Report 05000382/2024013, and Notice of Violation ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 IR 05000382/20240052024-08-21021 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Waterford Steam Electric Station, Unit 3 Report 05000382/2024005 ML24220A2642024-08-20020 August 2024 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment IR 05000382/20240132024-08-20020 August 2024 Notice of Violation; NRC Inspection Report 05000382/2024013 ML24228A2612024-08-20020 August 2024 Notice of Violation; NRC Inspection Report 05000382/2024013 05000382/LER-2024-004, Automatic Reactor Trip Due to Lightning Strike2024-08-15015 August 2024 Automatic Reactor Trip Due to Lightning Strike IR 05000382/20240022024-08-0808 August 2024 Integrated Inspection Report 05000382/2024002 ML24164A2512024-08-0707 August 2024 Issuance of Amendment No. 271 Technical Specification Change to Revise Surveillance Requirements Included in the Surveillance Frequency Control Program ML24213A1632024-08-0101 August 2024 2024 Waterford Notification of Biennial Problem Identification and Resolution Inspection and Request for Information ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification ML24150A3852024-06-0404 June 2024 Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000382/2024011) and Request for Information ML24060A2192024-05-30030 May 2024 Authorization of Alternative to Use EN-RR-01 Concerning Proposed Alternative to Adopt Code Case N-752 ML24141A1012024-05-20020 May 2024 Amended Integrated Inspection Report 05000382/2023004 ML24137A3352024-05-16016 May 2024 Automatic Reactor Trip Due to Transformer Failure ML24128A0422024-05-0707 May 2024 License Amendment Request to Remove Obsolete License Conditions IR 05000382/20240012024-05-0606 May 2024 Integrated Inspection Report 05000382/2024001 ML24067A1032024-04-25025 April 2024 Closeout of Generic Letter 2004 02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors ML24101A3882024-04-10010 April 2024 Response to Request for Confirmation of Information by the Office of Nuclear Reactor Regulation Proposed Alternative Request EN-RR-22-001 Risk-Informed Categorization and Treatment for Repair ML24089A2262024-03-29029 March 2024 Entergy Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Exams IR 05000382/20244012024-03-18018 March 2024 Material Control and Accounting Program Inspection Report 05000382/2024401 ML24074A3742024-03-15015 March 2024 Acknowledgement of Response to NRC Inspection Report 05000382/2023004 and Disputed Non-Cited Violation ML24075A1712024-03-15015 March 2024 Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3)) ML24074A2892024-03-14014 March 2024 Proof of Financial Protection (10 CFR 140.15) ML24032A0032024-03-0606 March 2024 – Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0053 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000382/20230062024-02-28028 February 2024 Annual Assessment Letter for Waterford Steam Electric Station, Unit 3 Report 05000382/2023006 ML24039A1992024-02-12012 February 2024 – Integrated Inspection Report 05000382/2023004 IR 05000382/20230102024-01-31031 January 2024 Comprehensive Engineering Team Inspection Report 05000382/2023010 IR 05000382/20230032024-01-23023 January 2024 Acknowledgment of Reply to a Notice of Violation NRC Inspection Report 05000382/2023003 ML24012A1962024-01-12012 January 2024 Response to 2nd Round Request for Additional Information Concerning Relief Request Number EN-RR-22-001 – Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and ML23340A2292023-12-28028 December 2023 Withdrawal of an Amendment Request to Revise Technical Specification 3/4.3.2 to Remove Exemption from Testing Certain Relays at Power to Support Elimination of Potential Single Point Vulnerability (EPID L-2022-LLA-0169)-LTR ML23349A1672023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23348A3572023-12-14014 December 2023 Application to Revise Technical Specifications to Use Online Monitoring Methodology – Slides and Affidavit for Pre-Submittal Meeting ML23340A1592023-12-13013 December 2023 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment ML23352A0292023-12-13013 December 2023 Entergy - 2024 Nuclear Energy Liability Evidence of Financial Protection ML23333A1362023-11-29029 November 2023 Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23325A1442023-11-21021 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23312A1832023-11-14014 November 2023 Integrated Inspection Report 05000382/2023003 and Notice of Violation ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV IR 05000382/20234012023-10-0404 October 2023 Cyber Security Inspection Report 05000382/2023401 (Cover Letter Only) IR 05000382/20230052023-08-21021 August 2023 Updated Inspection Plan for Waterford Steam Electric Station, Unit 3 - (Report 05000382/2023005) IR 05000382/20233012023-08-15015 August 2023 NRC Initial Operator Licensing Examination Approval 05000382/2023301 IR 05000382/20230022023-08-0808 August 2023 Integrated Inspection Report 05000382/2023002 IR 05000382/20234022023-08-0707 August 2023 NRC Security Inspection Report 05000382/2023402 (Full Report) 2024-09-06
[Table view] |
Text
October 09, 2024
SUBJECT:
WATERFORD STEAM ELECTRIC STATION, UNIT 3 - SECURITY BASELINE INSPECTION REPORT 05000382/2024403
Dear Joseph Sullivan:
On August 29, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Waterford Steam Electric Station, Unit 3. On September 19, 2024, the NRC inspectors discussed the results of this inspection with Dave Oertling, General Manager Plant Operations, and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Douglas E. Dodson, II, Chief Physical Security Branch Division of Radiological Safety & Security Docket No. 05000382 License No. NPF-38
Enclosure:
As stated
Inspection Report
Docket Number: 05000382
License Number: NPF-38
Report Number: 05000382/2024403
Enterprise Identifier: I-2024-403-0003
Licensee: Entergy Operations, Inc.
Facility: Waterford Steam Electric Station, Unit 3
Location: Killona, LA
Inspection Dates: August 26, 2024, to August 29, 2024
Inspectors: T. Weir, Physical Security Inspector
Approved By: Douglas E. Dodson, II, Chief Physical Security Branch Division of Radiological Safety & Security
Enclosure
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a security baseline inspection at Waterford Steam Electric Station,
Unit 3, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2201, Security Inspection Program for Commercial Nuclear Power Reactors. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
SAFEGUARDS
71130.07 - Security Training
The inspectors evaluated the security training program through completion of the following
===procedure elements:
Security Training===
Main article: IP 71130.07
(1)
- Tier II: All Requirements
- Tier III: 7 Requirements (02.10, 02.11, 02.12 a-b, 02.13 a-c)
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On September 19, 2024, the inspectors conducted a telephonic re-exit and presented the security baseline inspection results to Dave Oertling, General Manager Plant Operations, and other members of the licensee staff.
- On August 29, 2024, the inspectors presented the security baseline inspection results to Joe Sullivan, Site Vice President, and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection Type Designation Description or Title Revision or
Procedure Date
71130.07 Corrective Action 23-02020, 23-
Documents 02022, 23-02023,
23-12079
Corrective Action 24-04274, 24-
Documents 04275, 24-04276,
Resulting from 24-04282, 24-
Inspection 04324, 24-04325,
24-04326
Miscellaneous Law Enforcement Firearms Instructor Certifications
Handgun and Rifle Armorer Certifications
OCAT Instructor Certifications
FCOF-DLHNDGN Semi-Automatic Daylight Handgun 01/19/2024
FCOF-DLRIFLE Semi-Automatic Daylight Rifle 01/19/2024
FCOF-LLHNDGN Lowlight Semi-Automatic Handgun 01/19/2024
FCOF-LLRIFLE Semi-Automatic Low Light Rifle 01/19/2024
FCOF-Semi-Automatic Thermal Optic 05/11/2022
THERMLRIFLE
FLP-SEC-Lesson Plan - Vehicle Search Revision 2
VEHSEA
WLP-SEC-Lesson Plan - Arrest, Detention, and Investigation Waterford Revision 1
ADIVES 3 Use of Force Training
WLP-SECI-Lesson Plan - Patrol Procedures and Response to Alarms Revision 1
PARESP
Procedures EN-NS-212 Weapons Maintenance Program Revision 9
EN-NS-238 Firearms and Security Equipment Accountability Revision 2
EN-NS-300 Security Training Program Revision 11
EN-NS-301 Security Systematic Approach to Training (SAT) Process Revision 6
EN-NS-303 Security Training Oversight Program Revision 8
EN-NS-304 Security On-the-Job Training, Task Performance Evaluation Revision 12
and Training Exemptions
EN-NS-304 Security On-the-Job Training, Task Performance Evaluation Revision 12
and Training Exemptions
Inspection Type Designation Description or Title Revision or
Procedure Date
EN-NS-304-01 On-the-Job Training (OJT) Process Revision 2
EN-NS-304-02 Task Performance Evaluation (TPE) Process Revision 0
EN-NS-307 Security Supervisor Training and Development Program Revision 1
Self-Assessments LO-WF3-2023-IP 71130.07 Security Training Focused Self-Assessment 05/28/2024
00071
QA-16-2023-W3-Security, Including Cyber Security Audit Notification/Audit 12/14/2023
Plan Memorandum
5