ML24141A101

From kanterella
Jump to navigation Jump to search
Amended Integrated Inspection Report 05000382/2023004
ML24141A101
Person / Time
Site: Waterford Entergy icon.png
Issue date: 05/20/2024
From: John Dixon, Alfred Sanchez
NRC/RGN-IV/DORS/PBD
To: Sullivan J
Entergy Operations
References
IR 2023004
Download: ML24141A101 (31)


See also: IR 05000382/2023004

Text

Joseph Sullivan, Site Vice President

Entergy Operations, Inc.

17265 River Road

Killona, LA 70057

SUBJECT:

WATERFORD STEAM ELECTRIC STATION, UNIT 3 - AMENDED

INTEGRATED INSPECTION REPORT 05000382/2023004

Dear Joseph Sullivan:

On December 31, 2023, the U.S. Nuclear Regulatory Commission (NRC) completed an

inspection at Waterford Steam Electric Station, Unit 3. On January 24, 2024, the NRC

inspectors discussed the results of this inspection with you and other members of your staff.

The results of this inspection are documented in the enclosed report. This letter and enclosure

amend Inspection Report 05000382/2023004, issued on February 12, 2004, ADAMS accession

number ML24039A199.

This amendment clarifies the completed samples identified in Inspection Procedure 71111.08 to

reflect that samples were completed in Sections 03.02 and 03.04

Two findings of very low safety significance (Green) are documented in this report. Two of these

findings involved violations of NRC requirements. We are treating these violations as non-cited

violations (NCVs) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violations or the significance or severity of the violations documented in this

inspection report, you should provide a response within 30 days of the date of this inspection

report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional

Administrator, Region IV; the Director, Office of Enforcement; and the NRC Resident Inspector

at Waterford Steam Electric Station, Unit 3.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a

response within 30 days of the date of this inspection report, with the basis for your

disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk,

Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; and the

NRC Resident Inspector at Waterford Steam Electric Station, Unit 3.

May 20, 2024

J. Sullivan

2

This letter, its enclosure, and your response (if any) will be made available for public inspection

and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document

Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public

Inspections, Exemptions, Requests for Withholding.

Sincerely,

John L. Dixon, Jr., Chief

Reactor Projects Branch D

Division of Operating Reactor Safety

Docket No. 05000382

License No. NPF-38

Enclosure:

As stated

cc w/ encl: Distribution via LISTSERV

Signed by Dixon, John

on 05/20/24

J. Sullivan

3

WATERFORD STEAM ELECTRIC STATION, UNIT 3 - AMENDED INTEGRATED

INSPECTION REPORT 05000382/2023004 - DATED MAY 20, 2024

DISTRIBUTION:

JMonninger, ORA

JLara, ORA

GMiller, DORS

MHay, DORS

DCylkowski, RC

FGaskins, RIV/OEDO

VDricks, ORA

LWilkins, OCA

JDrake, NRR

AMoreno, RIV/OCA

RAlexander, RSLO

JDixon, DORS

ASanchez, DORS

APatz, DORS

DChilds, DORS

LReyna, DORS

R4-DORS-IPAT

R4Enforcement

DOCUMENT NAME: WATERFORD STEAM ELECTRIC STATION, UNIT 3 - AMEMDED INTEGRATED

INSPECTION REPORT 05000382/2023004

ADAMS Accession Number: ML24141A101

SUNSI Review

ADAMS:

Non-Publicly Available

Non-Sensitive

Keyword:

By: AAS

Yes No

Publicly Available

Sensitive

NRC-002

OFFICE

BC:DORS/EB2

BC:DORS/D

NAME

NTaylor

JDixon

SIGNATURE

/RA/

/RA/

DATE

05/20/2024

05/20/2024

J. Sullivan

4

OFFICIAL RECORD COPY

U.S. NUCLEAR REGULATORY COMMISSION

Inspection Report

Docket Number:

05000382

License Number:

NPF-38

Report Number:

05000382/2023004

Enterprise Identifier:

I-2023-004-0009

Licensee:

Entergy Operations, Inc.

Facility:

Waterford Steam Electric Station, Unit 3

Location:

Killona, LA 70057

Inspection Dates:

October 1, 2023, to December 31, 2023

Inspectors:

D. Childs, Resident Inspector

J. Drake, Senior Reactor Inspector

N. Greene, Senior Health Physicist

R. Kopriva, Senior Project Engineer

J. O'Donnell, Senior Health Physicist

A. Patz, Senior Resident Inspector

B. Tharakan, Technical Assistant

Approved By:

John L. Dixon, Jr., Chief

Reactor Projects Branch D

Division of Operating Reactor Safety

2

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees

performance by conducting an integrated inspection at Waterford Steam Electric Station, Unit 3,

in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs

program for overseeing the safe operation of commercial nuclear power reactors. Refer to

https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Follow ALARA Planning and Control Procedures Resulting in Unplanned Dose

Cornerstone

Significance

Cross-Cutting

Aspect

Report

Section

Occupational

Radiation Safety

Green

NCV 05000382/2023004-02

Open/Closed

[H.4] -

Teamwork

71124.01

The inspectors identified a Green finding and associated non-cited violation (NCV) of

Technical Specification 6.8.1.a for a failure to follow as low as reasonably achievable

(ALARA) planning and control procedures during the 2024 Unit 1 refueling outage.

Specifically, the licensee's planning or radiological controls did not prevent unplanned dose for

two separate work activities conducted during the 2024 refueling outage.

Failure to Maintain FLEX Equipment Starting Batteries

Cornerstone

Significance

Cross-Cutting

Aspect

Report

Section

Mitigating

Systems

Green

NCV 05000382/2023004-03

Open/Closed

[H.12] - Avoid

Complacency

71152A

The inspectors reviewed a self-revealed Green finding and associated NCV of 10 CFR

50.155(b)(1), which states, in part, strategies and guidelines to mitigate beyond-design-basis

events from natural phenomena must be capable of being implemented site-wide and must

include maintaining or restoring core cooling capabilities. Specifically, from approximately

February 14 to May 16, 2023, the licensee failed to ensure the starting batteries for the

FLEX N and N+1 diesel generators had sufficient capacity to perform their required functions.

Additional Tracking Items

Type

Issue Number

Title

Report Section

Status

URI

05000382/2023004-01

Steam Generator 1 In-Situ

Tube Pressure Testing

Failures.

71111.08P

Open

3

PLANT STATUS

Unit 3 began the inspection period at rated thermal power. On October 14, 2023, the unit was

shut down for refueling outage 25 and remained shut down for the remainder of the inspection

period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in

effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with

their attached revision histories are located on the public website at http://www.nrc.gov/reading-

rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared

complete when the IP requirements most appropriate to the inspection activity were met

consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection

Program - Operations Phase. The inspectors performed activities described in IMC 2515,

Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of

IPs. The inspectors reviewed selected procedures and records, observed activities, and

interviewed personnel to assess licensee performance and compliance with Commission rules

and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Impending Severe Weather Sample (IP Section 03.02) (1 Sample)

(1)

The inspectors evaluated the adequacy of the overall preparations to protect

risk-significant systems against external flooding from heavy rains and high winds on

November 20, 2023.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (1 Sample)

The inspectors evaluated system configurations during partial walkdowns of the following

systems/trains:

(1)

train B 7KV, 4KV and 480V safety-related electrical distribution systems while train A

was out for planned maintenance on November 2, 2023

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1)

The inspectors evaluated system configurations during a complete walkdown of the

containment fan cooler system on October 31, 2023.

4

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (8 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a

walkdown and performing a review to verify program compliance, equipment functionality,

material condition, and operational readiness of the following fire areas:

(1)

fire area RAB 5-001, elevation +35.00' reactor auxiliaries building electrical

penetration room B on October 17, 2023

(2)

fire area RAB 6-001, elevation +35.00' reactor auxiliaries building electrical

penetration room A on October 18, 2023

(3)

fire area RCB-001, elevations -4.00' and +21.00' reactor containment building on

October 20, 2023

(4)

fire area RAB 16-001, elevation +21.00' emergency diesel generator 3A room on

October 23, 2023

(5)

fire area RCB-001, elevation +46.00' reactor containment building on October 24,

2023

(6)

fire area RAB 8C-001, elevation +21' switchgear room AB on October 30, 2023

(7)

fire area RAB 9-001, elevation +21.00' remote shutdown room on October 30, 2023

(8)

fire area RAB 1E-001, elevation +35.00' cable vault on November 8, 2023

71111.07A - Heat Exchanger/Sink Performance

Annual Review (IP Section 03.01) (1 Sample)

The inspectors evaluated readiness and performance of:

(1)

component cooling water heat exchanger A on November 3, 2023

71111.08P - Inservice Inspection Activities (PWR)

The inspectors verified that the reactor coolant system boundary, reactor vessel internals, risk-

significant piping system boundaries, and containment boundary are appropriately monitored for

degradation and that repairs and replacements were appropriately fabricated, examined and

accepted by reviewing the following activities from October 23 to November 30, 2023.

PWR Inservice Inspection Activities Sample - Nondestructive Examination and Welding

Activities (IP Section 03.01) (1 Sample)

The inspectors verified that the following nondestructive examination and welding activities

were performed appropriately:

5

(1)

Dye Penetrant Examination

Reactor Coolant System, Component ID # RCI TE0112 CD1, 1B Cold Leg

Thermowell, Report No. BOP-PT-23-069

Magnetic Particle Examination

Main Steam, Component ID # 04-071, S/G #2 Upper Key Support Lug Weld

@ 0 Degree Axis, Report No W-ISI-MT-23-001

Visual Examination

Component Cooling Water, Component ID # CCRR-00322, Rigid Restraint,

Report No. W-ISI-VT-23-009

Primary Containment (PC), Component ID # DS-5, Containment Dome Outer

Surface, Report No. W-CISI-VT23-001

Primary Containment (PC), Component ID # WS-13, Containment Liner Outer

Surface 352.8 degrees - 138 degrees Azimuth, Report No. W-CISI-VT23-003

Primary Containment (PC), Component ID # WS-01, Containment Liner Inner

Surface 0 degrees- 90 degrees Azimuth at - 4-foot Elevation, Report

No. W-CISI-VT23-006

Primary Containment (PC), Component ID # WS-10, Containment Liner Inner

Surface 90 degrees-180 degrees Azimuth at + 46-foot Elevation, Report

No. W-CISI-VT23-014

Ultrasonic Examination

Charging (CH), Component ID # 30-002, 2-inch Pipe to Elbow Weld, Report

No. W-ISI-UT-23-011

Charging (CH), Component ID # 30-018, Elbow to 2-inch Pipe Weld, Report

No. W-ISI-UT-23-015

Charging (CH), Component ID # 30-009, 2-inch Pipe to Tee Weld, Report

No. W-ISI-UT-23-013

Charging (CH), Component ID # 30-010, 2-inch Pipe to Tee Weld, Report

No. W-ISI-UT-23-014

Charging (CH), Component ID # 30-008, 2-inch Pipe to Pipe Weld, Report

No. W-ISI-UT-23-012

Welding Activities

Gas Tungsten Arc Weld

o

Reactor Coolant System, ID # RC ITE0112 DC1, Thermowell

Cap - Fillet Weld FW-1

Gas Tungsten Arc Weld

o

Safety Injection System, ID # SI MVAA303 A, Valve, Socket

Welds - FW-1 and SW-6

6

PWR Inservice Inspection Activities Sample - Vessel Upper Head Penetration Inspection

Activities (IP Section 03.02 (1 Sample)

The inspectors verified that the license conducted the following vessel upper head

penetration inspections and addressed any identified defects appropriately:

(1)

Visual examination, bare metal visual, reactor vessel closure head.

PWR Inservice Inspection Activities Sample - Boric Acid Corrosion Control Inspection Activities

(IP Section 03.03) (1 Sample)

The inspectors verified the licensee is managing the boric acid corrosion control program

(1)

Evaluation # 22-WF3-0029, Component ID # BAMMVAAA118B,

CR-WF3-22-5000

Evaluation # 22-WF3-0030, Component ID # SI MPMP0002A,

CR-WF3-22-5132

Evaluation # 22-WF3-0031, Component ID # SI MVAAA2031A,

CR-WF3-22-5146

Evaluation # 22-WF3-0032, Component ID # CVCIDPI0203,

CR-WF3-22-5403

Evaluation # 22-WF3-0033, Component ID # BAMMVAAA118B,

CR-WF3-22-6403

Evaluation # 22-WF3-0034, Component ID # CS MPMP0001B,

CR-WF3-22-6409

Evaluation # 22-WF3-0035, Component ID # FS MPMP0001B,

CR-WF3-22-6415

Evaluation # 22-WF3-0036, Component ID # CS MPMP0001A,

CR-WF3-22-6906

Evaluation # 22-WF3-0037, Component ID # SI MPMP0002A,

CR-WF3-22-6905

Evaluation # 22-WF3-0038, Component ID # BAMMVAAA141,

CR-WF3-22-6899

Evaluation # 22-WF3-0039, Component ID # FS MVAAA426,

CR-WF3- 22-6910

Evaluation # 23-WF3-0001, Component ID # FS MVAAA512,

CR-WF3-22-8036

Evaluation # 23-WF3-0002, Component ID # CS MPMP0002B,

CR-WF3-22-8060

Evaluation # 23-WF3-0003, Component ID # BM MPMP0009,

CR-WF3-22-8066

Evaluation # 23-WF3-0004, Component ID # BM MPMP0001,

CR-WF3-22-8069

Evaluation # 23-WF3-0005, Component ID # SI MVAAA119B,

CR-WF3-22-8076

Evaluation # 23-WF3-0006, Component ID # SI MVAAA205A,

CR-WF3-23-0064

Evaluation # 23-WF3-0007, Component ID # SI MPMP0001A.

CR-WF3-3-0180

Evaluation # 23-WF3-0008, Component ID # SI MVAAA2351,

7

CR-WF3- 23-1215

Evaluation # 23-WF3-0009, Component ID # CVCMVAAA189A,

CR-WF3-23-1700

Independent Boric Acid Walkdown, October 27, 2023

Boric Acid Walkdown with Boric Acid Engineer, October 28, 2023

PWR Inservice Inspection Activities Sample - Steam Generator Tube Inspection Activities

(Section 03.04) (1 Sample)

The inspectors verified that the licensee is monitoring the steam generator tube integrity

appropriately through a review of the results of the 100 percent full length eddy current

inspection of all tubes with bobbin coil probe. Four tubes in replacement steam generator 1

exhibited wear that exceeded the tube integrity criteria provided in the degradation

assessment (DA).

Steam Generator 1

1.

There were four tubes that required in situ pressure testing to support the condition

monitoring assessment based on the DA and Electric Power Research Institute in situ

pressure test guidelines. Additional discussion of these activities is included in an

unresolved item in the results section of this report.

Two tubes from steam generator 1 (R1 C112 and R1 C138) were tested over the

range of prescribed test pressures and successfully reached and maintained the

structural limit pressure test of 5500 psi. No tube leakage was measured at any test

pressure for these two tubes.

Two tubes from steam generator 1 (R1 C4 and R2 C35) were tested over the range

of prescribed test pressures. Tube R1 C4 was unable to reach the structural limit test

pressure as it experienced pop-through at 5243 psi. No leakage was measured in

this tube at lower test pressures prior to the pop-through. Tube location R2 C35 was

able to temporarily achieve the structural limit test pressure point at 5500 psi, but lost

leak tight integrity via pop-through after a combined 131 seconds above the target

pressure of 5500 psi. The combined 131 seconds at pressure was achieved by a

period of 41 seconds above the test target, then briefly dropping below 5500 psi

before being re-established above 5500 psi for 90 seconds prior to the pop through.

No tube leakage was observed at any test pressure below the structural limit test.

2.

No tube leakage was reported during this operating interval. The inspectors verified that

the licensee is monitoring the steam generator tube integrity appropriately through

a review of the examinations.

There were a total of 48 tubes plugged, including 27 tubes in steam generator 1 and

21 tubes in steam generator 2.

Problem Identification and Resolution. Review of in-service inspection items. (Inspection

Procedure 71152 - Problem Identification and Resolution). The inspector evaluated a

sample of 16 condition reports associated with in-service inspection activities. No

findings or violations of more than minor significance were identified.

8

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01)

(1 Sample)

(1)

The inspectors observed and evaluated licensed operator performance in the control

room during unit shutdown for refueling outage on October 13-14, 2023.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1)

The inspectors observed and evaluated a licensed operator exam in the simulator on

December 12, 2023.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (5 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following

structures, systems, and components remain capable of performing their intended function:

(1)

containment spray pump A following breaker failure on September 22, 2023

(2)

permanent temporary emergency diesel generator following failure of heating,

ventilation, and air conditioning system on November 27, 2023

(3)

shield building ventilation train B failures on December 13, 2023

(4)

controlled ventilation area system following identification of incorrect open and close

times in design basis calculations on December 14, 2023

(5)

essential services chilled water chiller AB following trip while in service for train A on

December 26, 2023

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the

following operability determinations and functionality assessments:

(1)

containment particulate-iodine-gas radiation monitor operability following restoration

of particulate channel only on October 2, 2023

(2)

shutdown cooling trains A and B following instrument air transients on October 15,

2023

(3)

low pressure safety injection train B following identification of condensation inside

minimum flow recirculation valve actuator on November 28, 2023

(4)

plant stack radiation monitoring following failures and maintenance of plant stack

particulate-iodine-gas and plant stack wide range gas monitor on November 30, 2023

(5)

engineered safety features actuation system trains A and B following identification of

no fire seals on December 13, 2023

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)

9

(1)

(Partial)

The inspectors evaluated refueling outage 25 activities from October 14, 2023, to the

end of the inspection period, December 31, 2023. The sample will be closed in a

future inspection report.

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system

operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (3 Samples)

(1)

startup transformer B following breaker repair on October 12, 2023

(2)

low pressure safety injection pump B following identification of condensation in

minimum flow valve on December 4, 2023

(3)

auxiliary component cooling water train B following modification implementation for

flow control valve on December 19, 2023

Surveillance Testing (IP Section 03.01) (4 Samples)

(1)

emergency diesel generator A safety injection actuation test with concurrent loss of

offsite power on October 18, 2023

(2)

N+1 FLEX diesel generator on November 14, 2023

(3)

auxiliary component cooling water train B on December 7, 2023

(4)

charging pump A for boron flowrate verification on December 14, 2023

Inservice Testing (IP Section 03.01) (2 Samples)

(1)

safety injection valve 307A, safety injection tank 1A fill/drain valve testing on

November 6, 2023

(2)

controlled ventilation area system train B on December 18, 2023

Containment Isolation Valve Testing (IP Section 03.01) (1 Sample)

(1)

leak rate test on containment isolation valve SI-407A, loop 2 shutdown cooling

suction outside containment isolation, on October 23, 2023

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 03.01) (1 Sample)

(1)

The inspectors evaluated how the licensee identifies the magnitude and extent of

radiation levels and the concentrations and quantities of radioactive materials and

how the licensee assesses radiological hazards.

Instructions to Workers (IP Section 03.02) (1 Sample)

10

(1)

The inspectors evaluated how the licensee instructs workers on plant-related

radiological hazards and the radiation protection requirements intended to protect

workers from those hazards.

Contamination and Radioactive Material Control (IP Section 03.03) (2 Samples)

The inspectors observed/evaluated the following licensee processes for monitoring and

controlling contamination and radioactive material:

(1)

surveys of potentially contaminated material leaving the radiologically controlled area

exit

(2)

workers exiting the reactor containment building during a refueling outage

Radiological Hazards Control and Work Coverage (IP Section 03.04) (3 Samples)

The inspectors evaluated the licensee's control of radiological hazards for the following

radiological work:

(1)

Move of the upper guide structure from the reactor vessel to the lower cavity using

radiation work permit (RWP) 2023-702.

(2)

Chemical sampling and engineering inspection on the reactor vessel head using

RWP 2023-0714.

(3)

Breach and disassembly of gaseous waste valve (NG MVAAA 230A) using

RWP 2023-0404.

High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (5 Samples)

The inspectors evaluated licensee controls of the following high radiation areas (HRAs) and

very high radiation areas (VHRAs):

(1)

(HRA) top of containment sump (+7' elevation in the reactor containment building)

(2)

(HRA) pre-concentrator filter cubicle A/B (-35' elevation in the reactor auxiliary

building [RAB])

(3)

(HRA) purification ion exchange (IX) room A/B (-4' elevation in the RAB)

(4)

(HRA) pre-concentrator IX room A/B (-4' elevation in the RAB)

(5)

(HRA) fuel pool and chemical volume control filter cubicles and their respective hoist

pendants (-4' elevation in the RAB)

Radiation Worker Performance and Radiation Protection Technician Proficiency

(IP Section 03.06) (1 Sample)

(1)

The inspectors evaluated radiation worker and radiation protection technician

performance as it pertains to radiation protection requirements.

71124.04 - Occupational Dose Assessment

Source Term Characterization (IP Section 03.01) (1 Sample)

(1)

The inspectors evaluated licensee performance as it pertains to radioactive source

term characterization.

11

External Dosimetry (IP Section 03.02) (1 Sample)

(1)

The inspectors evaluated how the licensee processes, stores, and uses external

dosimetry.

Internal Dosimetry (IP Section 03.03) (2 Samples)

The inspectors evaluated the following internal dose assessments:

(1)

NRC Form 5 and dose assessment information for four workers, dated

October 2, 2020

(2)

NRC Form 5 and dose assessment information for one worker, dated April 18, 2022

Special Dosimetric Situations (IP Section 03.04) (2 Samples)

The inspectors evaluated the following special dosimetric situations:

(1)

NRC Form 5 and dose information for four declared pregnant workers

(2)

NRC Form 5 and assessments for four workers using effective dose equivalent

monitoring for non-uniform radiation fields

71124.08 - Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, &

Transportation

Shipment Preparation (IP Section 03.04) (1 Sample)

(1)

The inspectors observed the preparation of radioactive shipment 23-1009 consisting

of two intermodal containers (ESUU200865 and ESUU200404) of dry active waste on

October 26, 2023.

OTHER ACTIVITIES - BASELINE

71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10) (1 Sample)

(1)

October 1, 2022, through September 30, 2023

BI02: RCS Leak Rate Sample (IP Section 02.11) (1 Sample)

(1)

October 1, 2022, through September 30, 2023

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)

(1)

April 1, 2021, through June 30, 2023

PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual

Radiological Effluent Occurrences Radiological Effluent Occurrences Sample (IP Section 02.16)

(1 Sample)

12

(1)

April 1, 2021, through June 30, 2023

71152A - Annual Follow-up Problem Identification and Resolution

Annual Follow-up of Selected Issues (Section 03.03) (3 Samples)

The inspectors reviewed the licensees implementation of its corrective action program

related to the following issues:

(1)

containment fan cooler train B failures on November 21, 2023

(2)

component cooling water flow deviations to high pressure safety injection pump, low

pressure safety injection pumps, and containment spray pumps on December 1, 2023

(3)

FLEX N and N+1 diesel generator starting battery failures on December 21, 2023

71152S - Semiannual Trend Problem Identification and Resolution

Semiannual Trend Review (Section 03.02) (1 Sample)

(1)

The inspectors reviewed the licensees corrective action program for potential

adverse trends in lead-acid battery performance that might be indicative of a more

significant safety issue. The inspectors observed a negative trend in performance and

longevity of flooded lead-acid battery performance. This observation is further

detailed in the results section of this report.

INSPECTION RESULTS

Unresolved Item

(Open)

Steam Generator 1 In-Situ Tube Pressure Testing Failures.

URI 05000382/2023004-01

71111.08P

Description: The inspectors identified an unresolved item (URI) associated with the licensees

failure to meet the steam generator tube integrity performance criterion in technical

specification (TS) 6.5.9.b.1, Steam Generator Program. Specifically, Waterford 3s Steam

Generator Program structural integrity performance criterion includes retaining a safety factor

of 3.0 against burst under normal steady state full power operation primary to secondary

pressure differential and a safety factor of 1.4 against burst applied to the design basis

accident primary to secondary pressure differentials. The licensee extended the inspection

interval for the tube inspections from three cycles to four based on NRC approval of

TSTF-577 (Technical Specification Task Force), Revised Frequencies for Steam Generator

Tube Inspections and reevaluation of the refueling outage 21 (2017) operational

assessment. During the Unit 3 refueling outage 25 four tubes failed to meet the condition

monitoring criteria.

Technical specification 6.5.9, Steam Generator Program, requires that a program be

established and implemented to ensure that steam generator tube integrity is maintained.

Pursuant to TS 6.5.9, tube integrity is maintained when the steam generator performance

criteria are met. There are three steam generator performance criteria: structural integrity,

accident induced leakage, and operational leakage. Meeting the steam generator

performance criteria provides reasonable assurance of maintaining tube integrity at normal

and accident condition. TS 6.5.9 also states that the Steam Generator Program shall include

provisions for steam generator tube plugging criteria. Tubes found by in-service inspection to

contain flaws with a depth equal to or exceeding 40 percent on the nominal tube wall

13

thickness shall be plugged.

In steam generator 1, there were four tubes identified as having flaws that exceeded the

condition monitoring structural limit at the tube support plates. Eddy current testing and sizing

was performed, and the structural equivalent flaw parameters were calculated. The structural

equivalent parameters were compared to the condition monitoring limit curve and determined

that deficiencies existed. Since the tube performance criteria were not met analytically, in-situ

pressure testing of the four tubes was required. Other than the four tubes in-situ pressure

tested, all other tubes satisfied performance criteria analytically. In steam generator 2, the

tube performance criteria were satisfied analytically.

Two of the four tubes in-situ pressure tested in steam generator 1 failed to meet Structural

Integrity Performance Criterion. The examination results were also used, together with outage

repairs (i.e., tube plugging), to demonstrate that the performance criteria would be met for

upcoming cycles 26 through 27.

Upon completion of the tube examinations of pre and post pressure testing, +Point and Array

probe data confirmed that flaws in steam generator 1, tube Row 1 (R1) - Column 4 (C4) and

in tube R2-C35 had failed and burst. The inspectors reviewed condition report

CR-WF3-2023-17005 which provides additional information and a causal evaluation.

The event was reported as an 8-hour, non-emergency notification per 10CFR72(b)(3)(ii)9A)

as a degraded condition for not meeting the performance criteria for steam generator

structural integrity in accordance with TS 6.5.9.b.1, Steam Generator Program, due to two

tube failures in steam generator 1. Event notification56834 was reported to NRC

operations center on November 5, 2023.

The licensees apparent cause analysis and EN 56834 identified that the vendor used

non-conservation assumptions in the revised operational assessment to extend the

inspection interval. Additional inspection is required to determine if there is a performance

deficiency associated with this issue.

Planned Closure Actions: The NRC staff will review the available information, including a

pending vendor causal evaluation, to determine if any performance deficiencies exist and

identify any possible regulatory outcomes.

Licensee Actions: The licensee has placed the information into their corrective action

program and will have the document reviews and corrective actions developed in

January 2024.

Corrective Action References: Condition Reports CR-WF3-2023-17220 and

CR-WF3-2023-17005.

Failure to Follow ALARA Planning and Control Procedures Resulting in Unplanned Dose

Cornerstone

Significance

Cross-Cutting

Aspect

Report

Section

Occupational

Radiation Safety

Green

NCV 05000382/2023004-02

Open/Closed

[H.4] -

Teamwork

71124.01

14

The inspectors identified a Green finding associated with a non-cited violation (NCV) of

Technical Specification (TS) 6.8.1.a for a failure to follow as low as reasonably achievable

(ALARA) planning and control procedures during the refueling outage 24 (2022). Specifically,

the licensee's planning or radiological controls did not prevent unplanned dose for two

separate work activities conducted during the refueling outage.

Description: During refueling outage 24 (2022), the licensee performed work activities under

RWP 2022-0512, "1RE24 Steam Generator 1 and 2 Feedring Mod," and RWP 2022-0615,

"1RE24 Remove/Replace Pressurizer Heater." The accrued dose for each of these activities

exceeded the planned dose estimate by 64 percent due to issues that NRC deemed were

preventable or reasonably foreseeable. This presented two examples for a failure to follow

ALARA planning and control procedures. These issues involved changing radiological

conditions, delays in staging materials needed for work, inaccurate person-hours from various

teams, and uncoordinated resources.

The first example is relative to RWP 2022-0512, "1RE24 Steam Generator 1 and 2 Feedring

Mod," revision 2, which addressed the radiological work with the steam generators and the

feedring. While conducting this work, multiple issues occurred. The steam generator design

for installation was a new design to the site. The new design had higher u-tubes relative to

the feedwater injection area than the previous steam generators installed. The licensee

determined that the new design required more shielding for the foreign object search and

retrieval activities, so they added more magnetic tungsten shielding. However, this additional

shielding was not as effective as planned relative to the body positioning of the workers in

that the licensee did not account for the larger plane source of the steam generators. The

workers were exposed to higher than planned levels of radiation resulting in the additional

dose. The actual dose for this task significantly increased the planned dose due to various

issues identified during the review of the work activity.

Some of these issues were:

There was difficulty with the torquing of bolts, in which multiple bolts were

over-torqued and had to be addressed. The NRC deemed this as a human

performance error and therefore preventable. NRC gave no credit for this additional

dose.

There were delays in staging material due to improper planning for the needed

resources. For instance, the polar crane hook was unavailable when needed to stage

materials. NRC deemed this as a human performance error and preventable. NRC

gave no credit for this additional dose.

Teams involved with the work activity underestimated activities and resources

needed. For instance, the project team underestimated resources needed to assist

the containment coordinator. NRC deemed this as a human performance error and

preventable. NRC gave no credit for this additional dose.

The licensee used surveys from mockup activities during the pre-outage phase and

subsequently, the radiological levels increased. However, the licensee failed to

confirm the new radiological conditions and properly address the changing

radiological conditions in their planning phase prior to work. NRC deemed this as a

human performance error and preventable. NRC gave no credit for this additional

dose.

During the job, the licensee experienced retrieval of foreign material on the secondary

side of the steam generators. NRC determined this was an emergent issue that was

not preventable or foreseeable. NRC gave additional dose credit in the amount of

208 millirem.

15

Based on the above information reviewed, the NRC determined that an additional

208 millirem may be added to the licensee's initial dose estimate of 3.656 rem, resulting in a

new NRC revised dose estimate of 3.864 rem. When comparing this to the actual accrued

dose of the RWP (6.352 rem), NRC determined that the actual collective dose exceeded the

revised dose estimate by approximately 64 percent.

The second example is relative to RWP 2022-0615, "1RE24 Remove/Replace Pressurizer

Heater," revision 6, which addressed the radiological work to remove and replace the

pressurizer heaters. While conducting this work, the licensee had trouble in various aspects

of the activity. The three primary issues involved: (1) higher dose rates on the instrument

lines requiring more shielding, (2) removing the packaging of the new heater equipment, and

(3) more time needed to remove the heaters due to issues with the type of respiratory

equipment used.

The details of these three issues included:

The licensee surveyed the instrument lines prior to work and identified additional

shielding was needed to protect workers from unintended dose. NRC gave additional

dose credit in the amount of 132 millirem for adding shielding for this activity.

The licensee had difficulty removing the type of packaging used on the new heater

equipment, which seemed to have crystallized, and there was also wire meshing that

proved difficult to remove. NRC gave additional dose credit in the amount of 372

millirem.

The licensee chose to use a Pureflo respirator hood, described as a loose-fitting,

all-in-one powered air purifying respirator (PAPR). Workers experienced fogging of

these PAPRs that slowed down work significantly. However, NRC determined that the

time estimate used for removal of each heater was inadequate and underestimated.

The licensee estimated the removal of ten heaters at approximately 36 minutes per

heater but needed about 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> per heater. Partial credit for additional dose was

given due to unforeseen conditions of the PAPRs fogging resulting in slower work

performance, but not for the general underestimation of man-hours needed for each

heater removal. As a result, NRC gave additional dose credit in the amount of 724

millirem. NRC added this additional dose to the initial dose estimate, which generally

allowed about one additional man-hour for the removal of each heater.

Based on the above information reviewed, the NRC determined that a total of 1.228 rem

(132 millirem + 372 millirem + 724 millirem) in additional dose may be credited to the

licensee's initial dose estimate of 3.262 rem, resulting in a new NRC revised dose estimate of

4.490 rem. When comparing this to the actual accrued dose of the RWP (7.383 rem), NRC

determined that the actual collective dose exceeded the revised dose estimate by

approximately 64 percent.

As the inspectors reviewed the ALARA procedure, EN-RP-110, Step 4.0[8], the following

steps were not consistently followed in RWPs 2022-0512 and 2022-0615:

[8] Planning and Scheduling / Outage Groups: Responsibilities include the following:

Providing accurate worksite person-hours and accurate work locations for ALARA

Planning purposes.

16

o

In NRC's review, the worksite person hours for removal and replacement of

the pressurizer heaters and the steam generator activities were not accurate

for planning purposes to maintain doses ALARA

Providing detailed work plans to allow for ALARA Planning to designate adequate

radiological controls.

o

During NRC's review, in RWP 2022-0615, there were no written plans for

sequence and steps of the pressurizer heater removal. Poor planning resulted

in not maintaining doses ALARA. In RWP 2022-0512, the ALARA planning

phase did not account for the larger plane source of the new steam generator

design resulting in challenges with radiological exposures. Also, in the

planning of this RWP, the surveys used were from the mockup during the pre-

outage phase. When the radiological conditions changed, the licensee failed to

adjust the planned dose estimate to account for the higher dose rates during

the outage.

Coordinating scheduling of work with radiation protection (RP) personnel to assure

work is completed in a manner and sequence that supports the ALARA Program.

o

In NRC's review, there were examples of licensee groups not coordinating

activities, such as delays in staging material needed to conduct the work and

informal work plans. Activities and resources needed for work within the RCA

were not coordinated and accounted for appropriately. In the post-outage

review of RWP 2022-0512, the licensee deemed the delays in

staging/de-staging as the largest percentage of unproductive RWP person-

hours. In the post-outage review of RWP 2022-0615, the licensee stated that

the RP technicians supporting the activity did not have good firsthand

knowledge of the project scope and equipment being used which challenged

effective team building. Also, informal discussions between the project team

and RP staff for removal of the pressurizer heaters, in RWP 2022-0615,

resulted in uncertainty regarding the sequence and steps of execution.

Therefore, NRC determined that multiple procedural steps were missed during the planning

of these two work activities, RWP 2022-0512 and RWP 2022-0615, which resulted in

unplanned dose to workers and challenging ALARA principles.

Corrective Actions: The licensee addressed the deficiencies identified during the work activity

in their ALARA package post-job reviews. They also documented the failure to maintain

doses ALARA for these work activities in a new condition report for assessment of applicable

corrective actions.

Corrective Action References: CR-WF3-2023-16870

Performance Assessment:

Performance Deficiency: The licensee failed to follow ALARA planning procedures and did

not properly plan the scope of work activities.

Screening: The inspectors determined the performance deficiency was more than minor

because it was associated with the Program & Process attribute of the Occupational

Radiation Safety cornerstone and adversely affected the cornerstone objective to ensure the

adequate protection of the worker health and safety from exposure to radiation from

17

radioactive material during routine civilian nuclear reactor operation. Additionally, the finding

was similar to Example 6(i) in Appendix E to Inspection Manual Chapter 0612, Power

Reactor Inspection Reports - Examples of Minor Issues. This example states that an issue is

more than minor if it results in a collective dose greater than 5 person-Rem, and the actual

dose accrued exceeds the estimated dose by greater than 50 percent. Specifically, the actual

dose accrued for each work activity exceeded 5 rem and both exceeded the revised dose

estimate, as determined by the NRC, by 64 percent.

Significance: The inspectors assessed the significance of the finding using IMC 0609

Appendix C, Occupational Radiation Safety SDP. The inspectors determined the finding had

very low safety significance (Green) because: (1) it was associated with ALARA planning and

work controls; and (2) the licensees latest 3-year rolling average collective dose was less

than 135 person-Rem.

Cross-Cutting Aspect: H.4 - Teamwork: Individuals and work groups communicate and

coordinate their activities within and across organizational boundaries to ensure nuclear

safety is maintained. Specifically, the licensee failed to implement the process of planning

work activities with proper communication and coordination from each workgroup involved to

include person-hour estimates, resources, and formal work steps needed for the job activities.

This resulted in delays in staging material needed, inaccurate person-hours needed to

perform work activities, and uncoordinated resources needed for work activities.

Enforcement:

Violation: Technical Specification 6.8.1.a requires, in part, that written procedures shall be

established, implemented, and maintained covering the procedures recommended in

Regulatory Guide 1.33, Appendix A, Revision 2, dated February 1978. Section 7(e) of

Appendix A requires radiation protection procedures. Licensee Procedure EN-RP-110,

ALARA Program, revision 14, described the planning and scheduling responsibilities for

outage groups, which included providing accurate work site person-hours, providing detailed

work plans to allow ALARA planning to designate adequate radiological controls, and

coordinating scheduling of work with Radiation Protection personnel to support ALARA.

Contrary to the above, during refueling outage 24 in the spring of 2022, the licensee failed to

implement their ALARA program procedures for planning and controlling two work activities.

Specifically, for two RWPs-2022-0512 and -2022-0615, the licensee failed to provide

accurate work site person-hours, failed to provide detailed work plans for the pressurizer

heater removals or account for the larger plane source of the new steam generator design,

and failed to coordinate work activities and resources resulting in delays in staging materials

and unavailable resources. This resulted in not maintaining doses ALARA for workers during

these activities.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with

Section 2.3.2 of the Enforcement Policy.

Failure to Maintain FLEX Equipment Starting Batteries

Cornerstone

Significance

Cross-Cutting

Aspect

Report

Section

Mitigating

Systems

Green

NCV 05000382/2023004-03

Open/Closed

[H.12] - Avoid

Complacency

71152A

18

The inspectors reviewed a self-revealed Green finding and associated NCV of 10 CFR

50.155(b)(1), which states, in part, strategies and guidelines to mitigate beyond -design-basis

events from natural phenomena must be capable of being implemented site-wide and must

include maintaining or restoring core cooling capabilities. Specifically, from approximately

February 14 to May 16, 2023, the licensee failed to ensure the starting batteries for the

FLEX N and N+1 diesel generators had sufficient capacity to perform their required

functions.

Description: As part of the licensees phase 2 strategies as required by NRC

Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation

Strategies for Beyond-Design-Basis External Events, the licensee committed to the guidance

described in NEI 12-06, Diverse and Flexible Coping Strategies (FLEX) Implementation

Guide, revision 0. NRC Order EA-12-049 has since been codified by 10 CFR 50.155,

Mitigation of beyond-design-basis events.

Specifically for FLEX AC power supply, the licensee developed mitigating strategies that

utilize a FLEX N diesel generator as a 480V power supply that can be hooked up into a safety

bus. A FLEX N+1 diesel generator was stored outside the protected area as a backup that

can be brought into the protected area and connected into a safety bus. These two diesel

generators are the only dedicated means of providing 480V power for a beyond-design-basis

station blackout event. The diesel generators are started by a set of two commercial 8D

batteries for each generator.

On May 6, 2023, power was lost for 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> to the FLEX N+1 building which maintains the

FLEX N+1 diesel generator starting battery charge. On May 13, 2023, the licensee was

performing weekly rounds when it was identified the control panel of the FLEX N+1 diesel

generator had no power. The capacity of the batteries was too low to restart the battery

charger to provide the float charge. The batteries would not have had the capacity to start the

FLEX N+1 diesel generator if needed. On May 14, 2023, the degraded starting batteries were

replaced with the charged and ready set of spare FLEX starting batteries.

On May 16, 2023, the licensee removed power to the FLEX N diesel generator for 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> for

maintenance. The power was reconnected 24 minutes later, and the licensee attempted to

start the FLEX N diesel. However, the generator failed to start due to degraded capacity of

the starting battery. In both failures, the cause was a starting battery that had degraded

capacity. Because there was a set of ready spare batteries that would be able to be changed

out in an actual event, the function of the FLEX AC power supply was not considered fully

lost. All FLEX functions could still be completed within the time allotted.

The licensee makes plans to replace the starting batteries on a 4-year frequency. No tests

are performed specifically on the batteries to ensure their capacity is adequate beyond

performing a start of the FLEX N and FLEX N+1 diesel generators every six months. Both

sets of starting batteries were purchased and installed in May 2020. There is no expected

lifetime of the battery provided by the manufacturer. The warranty on the batteries is for 6

months with a pro-rated replacement that extends until 30 months of life. As evidenced by the

failure to start of the diesel generators, the capacity of these starting batteries was degraded

beyond the ability to start the FLEX diesel generators.

The date on which the starting batteries had degraded to no longer be functional is unable to

be determined with accuracy. The degradation mechanism is not able to be identified on the

licensee weekly or monthly checks of the equipment. The previous successful surveillances

that started the FLEX N and N+1 diesel generators were on November 15, 2022. The

19

inspectors assume the degradation occurred halfway from the last successful surveillance to

when both FLEX diesel generators were repaired. This date was determined to be

February 14, 2023.

Corrective Actions: The licensee replaced the starting batteries for both FLEX N and

FLEX N+1 diesel generators. After the initial replacement, the licensee performed another

replacement with longer-lasting absorbed glass-mat batteries. Additionally, the licensee

implemented preventive maintenance to perform monthly battery load testing for the FLEX N

and FLEX N+1 diesel generator starting batteries.

Corrective Action References: CR-WF3-2023-13265, CR-WF3-2023-13293

Performance Assessment:

Performance Deficiency: The licensee failed to maintain mitigation strategies for beyond-

design basis external events.

Screening: The inspectors determined the performance deficiency was more than minor

because it was associated with the Equipment Performance attribute of the Mitigating

Systems Cornerstone and adversely affected the cornerstone objective to ensure the

availability, reliability, and capability of systems that respond to initiating events to prevent

undesirable consequences. Specifically, the licensee failed to maintain the FLEX N and

FLEX N+1 diesel generator batteries so their respective generators could start and provide

power in accordance with the licensee mitigating strategies.

Significance: The inspectors assessed the significance of the finding using IMC 0609

Appendix A, The Significance Determination Process (SDP) for Findings At-Power. Using

Exhibit 2, Mitigating Systems Screening Questions, Section E, the inspectors determined

the finding to be of very low safety significance (Green), because the performance deficiency

was associated with equipment not solely purposed for spent fuel pool instrumentation or for

containment venting, but it was associated with equipment credited in a Phase 2 FLEX

strategy such that all FLEX functions could still be completed in accordance with existing

plant procedures within the time allotted.

Cross-Cutting Aspect: H.12 - Avoid Complacency: Individuals recognize and plan for the

possibility of mistakes, latent issues, and inherent risk, even while expecting successful

outcomes. Individuals implement appropriate error reduction tools. The licensee failed to

recognize and plan for the possibility of starting batteries to degrade faster than their service

life and result a loss of ability of the FLEX diesels to start.

Enforcement:

Violation: 10 CFR 50.155(b)(1), states, in part, strategies and guidelines to mitigate

beyond-design-basis events from natural phenomena must be capable of being implemented

site-wide and must include maintaining or restoring core cooling capabilities.

Contrary to the above, from approximately February 14 to May 16, 2023, the licensee failed

to maintain mitigation strategies for beyond-design basis external events. Specifically, the

licensee failed to maintain the FLEX N and FLEX N+1 diesel generator batteries so their

respective generators could start and provide power in accordance with the licensee

mitigating strategies.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with

Section 2.3.2 of the Enforcement Policy.

20

Observation: Flooded Lead-Acid Battery Performance

71152S

The inspectors reviewed the licensees corrective action program for potential adverse trends

in lead-acid battery performance that might be indicative of a more significant safety issue.

The inspectors observed a negative trend in performance and longevity of flooded lead-acid

battery performance. In addition to the FLEX N and FLEX N+1 starting battery issues detailed

in the IP 71152A section, the inspectors identified five other battery failures in 2023:

CR-WF3-2023-01793: The starting batteries for the non-safety permanently-installed

temporary emergency diesel generator were degraded and unable to perform their

function.

CR-WF3-2023-14593: The starting batteries for the security diesel generator were

degraded and unable to perform their function.

CR-WF3-2023-15322: The starting battery for the portable ultimate heat sink

replenishment pump were below the required voltage.

CR-WF3-2023-15407: The starting battery for the diesel-driven dry cooling tower

sump pump was degraded and unable to perform its function.

CR-WF3-2023-15858: The starting batteries for diesel-driven fire pump A were

degraded and unable to perform their function.

These five diesel generators are considered non-safety but perform important functions

for the site. The licensee documented the NRC concern about a negative trend in

performance in CR-WF3-2023-15830 and performed an analysis of the issue. The

corrective actions included replacement of the batteries and a reconsideration of the

preventive maintenance strategies. No findings of significance were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On October 27, 2023, the inspectors presented the occupational radiation safety

inspection results to Joseph Sullivan, Site Vice President, and other members of the

licensee staff.

On November 2, 2023, the inspectors presented the radiation inspection results to

Joseph Sullivan, Site Vice President, and other members of the licensee staff.

On November 30, 2023, the inspectors presented the inservice inspection results to

Joseph Sullivan, Site Vice President, and other members of the licensee staff.

On January 24, 2024, the inspectors presented the integrated inspection results to

Joseph Sullivan, Site Vice President, and other members of the licensee staff.

21

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.01

Engineering

Evaluations

W3F1-2015-0042

Flood Hazard Reevaluation Report

07/21/2015

71111.01

Procedures

OP-901-521

Severe Weather and Flooding

342

71111.04

Corrective Action

Documents

CR-WF3-YYYY-

NNNN

2022-04265, 2022-06268, 2023-16951

71111.04

Miscellaneous

W3-DBD-010

Containment Cooling HVAC and Related Systems

301

71111.04

Miscellaneous

W3-DBD-011

Electrical Distribution (AC portion)

302

71111.04

Procedures

OP-006-001

Plant Distribution System (7KV, 4KV, and SSD) System

346

71111.04

Procedures

OP-008-003

Containment Cooling System

303

71111.04

Work Orders

00580779, 00580781

71111.05

Fire Plans

RAB 16-001

Emergency Diesel Generator Room 3A

12

71111.05

Fire Plans

RAB 1E-001

Cable Vault

11

71111.05

Fire Plans

RAB 5-001

Electrical Penetration Room B

10

71111.05

Fire Plans

RAB 6-001

Electrical Penetration Room A

10

71111.05

Fire Plans

RAB 8C-001

Switchgear Room AB

12

71111.05

Fire Plans

RAB 9-001

Auxiliary Control Panel Room

9

71111.05

Fire Plans

RCB-001

RCB General Area

12

71111.07A

Miscellaneous

W3-DBD-4

Component Cooling Water Auxiliary Component Cooling

Water Design Basis Document

307

71111.07A

Work Orders

52586237, 53000031

71111.08P

Corrective Action

Documents

CR-WF3-YYYY-

NNNNN

2022-01969, 2022-02400, 2022-02472, 2022-02656,

2022-02665, 2022-02915, 2022-03207, 2022-03855,

2022-04131, 2022-04850, 2022-05025, 2022-05227,

2022-05244, 2022-05355, 2022-08116, 2023-01326,

2023-01346, 2023-01565, 2023-16490, 2023-16753,

2023-16755, 2023-16971, 2023-91568, 2023-01568,

2023-01632

71111.08P

Corrective Action

Documents

Resulting from

Inspection

CR-WF3-YYYY-

NNNNN

2023-16714, 2023-16720, 2023-16883, 2023-16938,

2023-16966, 2023-16971, 2023-16985, 2023-16990,

2023-17005, 2023-17042, 2023-17043, 2023-17044,

2023-17058, 2023-17070, 2023-17219, 2023-17220,

2023-17259, 2023-17278, 2023-376

22

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.08P

Drawings

S/G 32 Hot Primary Face, Hardware Repair Status Pre-

3R25-10/23 - S/G 32 Hot Leg

08/11/2023

71111.08P

Drawings

02-9367763-E-

000

S/G 31 Cold Primary Face, Hardware Repair Status Pre-

3R25-10/23 - S/G 31 Cold Leg

08/11/2023

71111.08P

Drawings

02-9367764-E-

000

S/G 31 Hot Primary Face, Hardware Repair Status Pre-

3R25-10/23 - S/G 31 Hot Leg

08/11/2023

71111.08P

Drawings

02-9367765-E-

000

S/G 32 Cold Primary Face, Hardware Repair Status Pre-

3R25-10/23 - S/G 32 Cold Leg

08/11/2023

71111.08P

Drawings

6660E03

Replacement Steam Generator Waterford 3 Water Level Vs.

Span

2

71111.08P

Drawings

H33760-1201,

Sheet 1 of 4

Rosemount Engineering Company, Certified Configuration

Drawing - Sensor, Temperature Platinum Resistance Type

C

71111.08P

Engineering

Changes

EC# 0000084109

Waterford 3 - Steam Generator Strategic Plan Document

Plan Per EN-DC-317, Para 7.13

000

71111.08P

Engineering

Changes

EC-0054070627

ASME Section XI VT-3 examination of rigid strut support

FWRR-0017 under WO-554302

71111.08P

Miscellaneous

Certificate of

Calibration No.

20846-502

Parker Research Corporation, TB-10 Magnetic Weight Lift

Test Bar

04/12/2007

71111.08P

Miscellaneous

LA191736

SOCOTEC WF3 Feedwater Piping Monitoring for RSG Flow

Diverter Modification

001

71111.08P

Miscellaneous

PQR 344

Procedure Qualification Record, Manual Gas tungsten Arc

Welding (GTAW)

1

71111.08P

Miscellaneous

PQR 456

Procedure Qualification Record, Manual Gas Tungsten &

Shielded Metal Arc Welding (GTAW and SMAW)

0

71111.08P

Miscellaneous

WPS-NI-43/43-B

Manual Gas Tungsten Arc Welding (GTWA) of P-No.43

nickel alloys, in all positions, for all joint types, fillets and

repairs using F-No. 43 filler metal, without Postweld Heat

Treatment (PWHT).

0

71111.08P

NDE Reports

BOP-PT-23-069

1B Cold Leg Thermowell, Component ID: RCI TE0112 CD1

11/04/2023

71111.08P

NDE Reports

PT-VT-22-031

Bolted Connection RC MRCT0001 (RV Studs)

04/15/2022

71111.08P

NDE Reports

PT-VT-22-039

S/G System - RCB/Outside D-Rings

06/24/2022

71111.08P

NDE Reports

W-CISI-VT 22-

002

Inner Moisture Between Col. 19 and Col. 21 (Approx.)

04/27/2022

23

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.08P

NDE Reports

W-CISI-VT22-007

Inner Moisture Barrier Between Col. 11 and Col. 13

(Approx.)

04/27/2022

71111.08P

NDE Reports

W-CISI-VT22-013

Moisture Barrier Inside Annulus 0 degrees to 103 degrees

azimuth.

04/27/2022

71111.08P

NDE Reports

W-CISI-VT22-014

Moisture Barrier Inside Annulus 103 degrees to 256 degrees

Azimuth

04/27/2022

71111.08P

NDE Reports

W-CISI-VT22-015

Moisture Barrier Inside Annulus 256 degrees to 360 degrees

Azimuth

04/27/2022

71111.08P

NDE Reports

W-ISI-VT-22-009

ASME Section XI VT-3 examination of rigid strut support

FWRR-0017 under WO-554302. A loose lock nut was not in

the proper location according to design drawing FWRR-117

SH 1 of 3 and the Bergen-Paterson Pipe Support Corp.

10/30/2023

71111.08P

Procedures

CEP-BAC-001

Boric Acid Corrosion Control (BACC) Program Plan

2

71111.08P

Procedures

CEP-NDE-0400

Ultrasonic Examination

9

71111.08P

Procedures

CEP-NDE-0404

Manual Ultrasonic Examination of Ferritic Piping Welds

(ASME XI)

9

71111.08P

Procedures

CEP-NDE-0407

Straight Beam Ultrasonic Examination of Bolts and Studs

(ASME XI)

6

71111.08P

Procedures

CEP-NDE-0423

Manual Ultrasonic Examination of Austenitic Piping Welds

(ASME XI)

9

71111.08P

Procedures

CEP-NDE-0641

Liquid Penetrant Examination (PT) for ASME Section XI

10

71111.08P

Procedures

CEP-NDE-0731

Magnetic Particle Examination (MT) for ASME Section XI

7

71111.08P

Procedures

CEP-NDE-0901

VT-1 Examination

6

71111.08P

Procedures

CEP-NDE-0902

VT-2 Examination

10

71111.08P

Procedures

CEP-NDE-0903

VT-3 Examination

8

71111.08P

Procedures

CEP-NDE-0965

Visual Welding Inspection ASME, ANSI B31-1

7

71111.08P

Procedures

CEP-PT-0001

ASME Section XI Pressure Test (PT) Program

313

71111.08P

Procedures

CEP-RR-001

ASME Section XI Repair/Replacement Program

320

71111.08P

Procedures

CEP-SG-002

Steam Generator Secondary Side Examinations and

Maintenance

5

71111.08P

Procedures

CEP-WP-GWS-1

General Welding Standard ASME/ANSI

8

71111.08P

Procedures

EN-DC-319

Boric Acid Corrosion Control Program (BACCP)

13

71111.08P

Procedures

EN-DC-328

Entergy Nuclear Welding Program

008

71111.08P

Procedures

EN-DC-342

Entergy Repair/Replacement Program

004

24

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.08P

Procedures

EN-DC-351

Inservice Inspection Program Duties and Responsibilities

007

71111.08P

Procedures

EN-LI-102

Corrective action Program

049

71111.08P

Procedures

SEP-BAC-WF3-

001

Waterford 3 Boric Acid Corrosion Control Program (BACCP)

Program Section

4

71111.08P

Procedures

SEP-ISI-104

Program Section For ASME Section XI, Division 1 WF3

Inservice Inspection Program

14

71111.08P

Procedures

SEP-ISI-104

Program Section for ASME Section X, Division 1 WF3

Inservice Inspection Program

14

71111.08P

Procedures

SEP-PT-WF3-

001

Waterford 3 Inservice Inspection Pressure Testing (PT)

Program Section

001

71111.08P

Procedures

SEP-SG-WF3-

001

Waterford -3 (W3/WF3) Steam Generator Program

4

71111.08P

Self-Assessments LO-HQNLO-

2021-19

2022 Welding Program Assessment

02/17/2022

71111.08P

Self-Assessments LO-WLO-2022-

0060-CA

Pre-NRC RF25 ISI Activities Self -Assessment Report

08/08/2023

71111.08P

Self-Assessments LO-WLO-2022-

0060-CA-3

Pre-NRC RF25 ISI Activities Self-Assessment Report

08/08/2023

71111.08P

Work Orders

WO No.

572188-24, 589604-15

71111.11Q

Procedures

EN-OP-115

Conduct of Operations

31

71111.11Q

Procedures

OP-010-005

Plant Shutdown

345

71111.11Q

Procedures

OP-901-311

Loss of Train B Safety Bus

313

71111.11Q

Procedures

OP-901-521

Severe Weather and Flooding

343

71111.11Q

Procedures

OP-902-001

Reactor Trip Recovery

21

71111.11Q

Procedures

OP-902-003

Loss of Offsite Power / Loss of Forced Circulation Recovery

11

71111.12

Corrective Action

Documents

CR-WF3-YYYY-

NNNN

2022-06818, 2023-01910, 2023-01944, 2023-13294,

2023-13313, 2023-13331, 2023-14317, 2023-14967,

2023-16596, 2023-13943, 2023-14310, 2023-14314

71111.12

Corrective Action

Documents

Resulting from

Inspection

CR-WF3-YYYY-

NNNN

2024-00169

01/10/2024

71111.12

Engineering

Changes

EC 54051011

Engineering Change

09/14/2023

25

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.12

Miscellaneous

TD G080.0095

General Electric Switchgear Magne Blast Breakers

6

71111.12

Procedures

EN-DC-205

Maintenance Rule Monitoring

9

71111.12

Procedures

ME-004-115

4.16/6.9 kV G.E. Magne-Blast Breaker Overhaul

6, 9

71111.12

Procedures

OP-903-094

ESFAS Subgroup Relay Test - Operating

35

71111.12

Work Orders

00517244, 00586519, 52790255, 52805142, 54034973,

54038818

71111.15

Corrective Action

Documents

CR-WF3-YYYY-

NNNN

2023-16283, 2023-16372, 2023-16376, 2023-17876,

2023-15594

71111.15

Engineering

Changes

EC 54056366

Engineering Change

0

71111.15

Procedures

OP-009-005

Shutdown Cooling

45

71111.15

Procedures

OP-901-511

Instrument Air Malfunction

20

71111.15

Corrective Action

Documents

CR-WF3-YYYY-

NNNN

2023-17399

71111.24

Corrective Action

Documents

CR-WF3-YYYY-

NNNNN

2019-01293, 2023-18027, 2017-03359, 2017-04081,

2018-00948,

71111.24

Engineering

Changes

EC 54093486

ACC-127B Input to Operability CR-23-18244/18245

12/21/2023

71111.24

Engineering

Changes

EC 72080

Use of instrumentation for ACCW System Flow Balance

PE-004-024

05/12/2017

71111.24

Procedures

FSG-005

Initial Assessment and FLEX Equipment Staging

15

71111.24

Procedures

OP-903-003

Charging Pump Operability Check

315

71111.24

Procedures

OP-903-052

Controlled Ventilation Area System Operability Check

15

71111.24

Procedures

OP-903-096

Boron Flowrate Verification

11

71111.24

Procedures

OP-903-115

Train A Integrated Emergency Diesel

59

71111.24

Procedures

OP-903-121

Safety Systems Quarterly IST Valve Tests

36

71111.24

Procedures

PE-004-024

ACCW & CCW System Flow Balance

310

71111.24

Procedures

STA-001-004

Local Leak Rate Test (LLRT)

320

71111.24

Work Orders

53013043, 54002710, 00586332, 53017375, 54067505,

54085552, 00474102, 00495521, 00502714, 00517264,

00518612

71124.01

ALARA Plans

RWP 2022-0512

1RE24 Steam Generator 1 and 2 Feedring Mod

2

71124.01

ALARA Plans

RWP 2022-0615

1RE24 Remove/Replace Pressurizer Heater

6

26

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71124.01

Corrective Action

Documents

CR-WF3-YYYY-

XXXXX

2022-01953, 2023-00421, 2022-03390, 2022-06963,

2023-00518, 2023-01766, 2023-01234, 2022-02542,

2022-07912, 2023-00114, 2023-16348, 2023-16474,

71124.01

Corrective Action

Documents

Resulting from

Inspection

CR-WF3-YYYY-

XXXXX

2023-16870, 2023-16872, 2023-16893

71124.01

Procedures

EN-RP-100

Radiation Worker Expectations

14

71124.01

Procedures

EN-RP-101

Access Control for Radiologically Controlled Areas

17

71124.01

Procedures

EN-RP-102

Radiological Control

008

71124.01

Procedures

EN-RP-110

ALARA Program

14

71124.01

Procedures

EN-RP-121

Radioactive Material Control

19

71124.01

Procedures

EN-RP-141-01

Job Coverage Using Remote Monitoring Technology

8

71124.01

Procedures

EN-RP-152

Conduct of Radiation Protection

008

71124.01

Procedures

HPI-001-123

Plant Conditions and Radiological Concerns

010

71124.01

Radiation

Surveys

WF3-2301-00269

RAB -4 Purification Ion Exchangers

01/24/2023

71124.01

Radiation

Surveys

WF3-2308-00181

RAB -35 Spent Resin Tank Pump Room / Waste

Condensate IX

08/22/2023

71124.01

Radiation

Surveys

WF3-2309-00144

RAB -35 Boric Acid Pre-Concentrator Filters

09/14/2023

71124.01

Radiation

Surveys

WF3-2309-00185

FHB +46 Fuel Handling Area

09/18/2023

71124.01

Radiation

Surveys

WF3-2309-00225

RAB -4 Center Wing

09/23/2023

71124.01

Radiation

Surveys

WF3-2309-00251

Radwaste Solidification Building

09/26/2023

71124.01

Radiation

Surveys

WF3-2310-00066

RAB -4 Flash Tank / Purification Filter Area

10/05/2023

71124.01

Radiation Work

Permits (RWPs)

2022-0623

REFUEL 24 - Perform miscellaneous contaminated system

valve work in the Regen Hx Room including all support

activities, troubleshooting, walkdowns, tagouts, tours and

inspections.

01

71124.01

Radiation Work

2022-0641

REFUEL 24 - Emergent Dose added Inside the Reactor

00

27

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Permits (RWPs)

Containment Building.

71124.01

Radiation Work

Permits (RWPs)

2023-0404

REFUEL 25 - Plant Maintenance Valve Work on

Contaminated and Clean System Valves outside the Reactor

Containment Building.

00

71124.01

Radiation Work

Permits (RWPs)

2023-0702

REFUEL 25 - Disassembly of Reactor Head and All

Associated Work Activities.

02

71124.01

Radiation Work

Permits (RWPs)

2023-0714

REFUEL 25 - Cleaning of the Reactor Head Surface.

Includes all supporting activities and Bare Metal Inspections.

00

71124.01

Self-Assessments LO-WLO-2022-

0051 CA-00004

Radiological Hazard Assessment and Exposure Controls

08/21/2023

71124.04

Corrective Action

Documents

CR-WF3-YYYY-

NNNN

2020-01981, 2020-02198, 2020-03232, 2020-07014,

2021-00302, 2021-02028, 2022-01780, 2022-01921,

2022-03253, 2022-07004, 2023-01604, 2023-15043,

2023-16119

71124.04

Miscellaneous

Evaluation of DLR/SRD Discrepancies and DLRs Not

Returned for Processing

06/30/2020

71124.04

Miscellaneous

Evaluation of DLR/SRD Discrepancies and DLRs Not

Returned for Processing

07/10/2022

71124.04

Miscellaneous

NRC Annual Dose Report (REIRS)

2022

71124.04

Miscellaneous

15403

Dose Assessment from PCE

10/02/2020

71124.04

Miscellaneous

56286

Dose Assessment from PCE

10/02/2020

71124.04

Miscellaneous

57700

Dose Assessment from PCE

10/02/2020

71124.04

Miscellaneous

64832

Dose Assessment from PCE

10/02/2020

71124.04

Miscellaneous

92905

Dose Assessment from PCE

04/18/2022

71124.04

Procedures

EN-RP-122

Alpha Monitoring

10

71124.04

Procedures

EN-RP-201

Dosimetry Administration

5

71124.04

Procedures

EN-RP-203

Dose Assessment

10

71124.04

Procedures

EN-RP-204

Special Monitoring Requirements

11

71124.04

Procedures

EN-RP-204-01

Effective Dose Equivalent (EDEX) Monitoring

3

71124.04

Procedures

EN-RP-205

Prenatal Monitoring

5

71124.04

Procedures

EN-RP-206

Dosimeter of Legal Record Quality Assurance

7

71124.04

Procedures

EN-RP-208

Whole Body Counting/In-Vitro Bioassay

7

71124.04

Self-Assessments LO-WLO-2022-

00051

Occupational Dose Assessment

10/05/2023

28

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71124.04

Self-Assessments QA-14/15-2021-

W3-01

Quality Assurance Audit: Combined Radiation Protection

and Radwaste

10/25/2021

71124.08

Shipping Records

RSN#: 23-1009

Shipment consisting of two 20-foot intermodal containers

(ESUU200404 and ESUU200865) of dry active waste,

UN2912, radioactive material, low specific activity (LSA-I)

10/26/2023

71152A

Corrective Action

Documents

CR-WF3-YYYY-

NNNN

2022-01874, 2022-03111, 2022-06393, 2022-06647,

2022-06852, 2023-15179, 2023-15245, 2023-16237

71152A

Corrective Action

Documents

Resulting from

Inspection

CR-WF3-YYYY-

NNNN

2023-14746, 2023-14747, 2023-14895, 2023-15933,

2023-15424

71152A

Work Orders

53005507, 53022055, 53022177, 53005391, 54003998

71152S

Corrective Action

Documents

CR-WF3-YYYY-

NNNN

2023-01793, 2023-01911, 2023-14593, 2023-15322,

2023-15407, 2023-15858, 2023-16043

71152S

Corrective Action

Documents

Resulting from

Inspection

CR-WF3-YYYY-

NNNN

2023-15830