ML22217A111

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000382/2022002
ML22217A111
Person / Time
Site: Waterford Entergy icon.png
Issue date: 08/09/2022
From: John Dixon
NRC/RGN-IV/DORS/PBD
To: Ferrick J
Entergy Operations
References
IR 2022002
Download: ML22217A111 (51)


See also: IR 05000382/2022002

Text

August 09, 2022

Mr. John Ferrick, Site Vice President

Entergy Operations, Inc

17265 River Road

Killona, LA 70057

SUBJECT: WATERFORD STEAM ELECTRIC STATION, UNIT 3 - INTEGRATED

INSPECTION REPORT 05000382/2022002

Dear Mr. Ferrick:

On June 30, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at

Waterford Steam Electric Station, Unit 3. On July 19, 2022, the NRC inspectors discussed the

results of this inspection with Mr. Matthew Lewis, General Manager of Plant Operations, and

other members of your staff. The results of this inspection are documented in the enclosed

report.

Eight findings of very low safety significance (Green) are documented in this report. Eight of

these findings involved violations of NRC requirements. We are treating these violations as

non-cited violations (NCVs) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violations or the significance or severity of the violations documented in this

inspection report, you should provide a response within 30 days of the date of this inspection

report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional

Administrator, Region IV; the Director, Office of Enforcement; and the NRC Resident Inspector

at Waterford Steam Electric Station, Unit 3.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a

response within 30 days of the date of this inspection report, with the basis for your

disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk,

Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; and the

NRC Resident Inspector at Waterford Steam Electric Station, Unit 3.

J. Ferrick 2

This letter, its enclosure, and your response (if any) will be made available for public inspection

and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document

Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public

Inspections, Exemptions, Requests for Withholding.

Sincerely,

Signed by Dixon, John

on 08/09/22

John L. Dixon, Jr., Chief

Projects Branch D

Division of Operating Reactor Safety

Docket No. 05000382

License No. NPF-38

Enclosure:

As stated

cc w/ encl: Distribution via LISTSERV

ML22217A111

Non-Sensitive Publicly Available

SUNSI Review

Sensitive Non-Publicly Available

OFFICE SRI:DRP/D RI:DRP/D BC:DORS/IPAT BC:DORS/EB1

NAME APatz/ADP AChilds/ACC AAgrawal/ARP VGaddy/VGG

DATE 08/05/2022 08/08/2022 08/08/2022 08/08/2022

OFFICE ABC:DORS/EB2 BC:DORS/RCB BC:DRS/OB ABC:DRSS/DIOR

NAME JDrake/JFD MHaire MSH HGepford/HJG Sanderson/SMG

DATE 08/05/2022 08/08/2022 08/08/2022 08/05/2022

OFFICE SPE:DORS/D BC:DORS/D

NAME ASanchez/AAS JDixon

DATE 08/08/2022 8/9/2022

U.S. NUCLEAR REGULATORY COMMISSION

Inspection Report

Docket Number: 05000382

License Number: NPF-38

Report Number: 05000382/2022002

Enterprise Identifier: I-2022-002-0007

Licensee: Entergy Operations, Inc

Facility: Waterford Steam Electric Station, Unit 3

Location: Killona, LA 70057

Inspection Dates: April 1, 2022 to June 30, 2022

Inspectors: D. Antonangeli, Health Physicist

B. Baca, Health Physicist

D. Childs, Resident Inspector

L. Flores, Technical Assistant

N. Greene, Senior Health Physicist

R. Kopriva, Senior Reactor Inspector

A. Patz, Senior Resident Inspector

A. Sanchez, Senior Project Engineer

E. Simpson, Health Physicist

C. Stott, Resident Inspector

J. Vera, Senior Resident Inspector

Approved By: John L. Dixon, Jr, Chief

Projects Branch D

Division of Operating Reactor Safety

Enclosure

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees

performance by conducting an integrated inspection at Waterford Steam Electric Station, Unit 3,

in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs

program for overseeing the safe operation of commercial nuclear power reactors. Refer to

https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Adequately Plan and Control Worker Exposures As Low As (is) Reasonably

Achievable (ALARA) During the Removal of Pressurizer Heaters Resulting in Worker

Uptakes.

Cornerstone Significance Cross-Cutting Report

Aspect Section

Occupational Green [P.5] - 71124.01

Radiation Safety NCV 05000382/2022002-02 Operating

Open/Closed Experience

The inspectors identified a finding of very low safety significance (Green) for the licensee

having unplanned and unintended occupational internal radiation exposure because of

deficiencies in the licensees work planning and work control program. Specifically, the

licensee failed to appropriately implement aspects of EN-RP-105, Radiological Work

Permits (RWP), to maintain doses ALARA. Four workers (two radiation protection technicians

and two contract workers) received an uptake of airborne radioactive material during the

removal of pressurizer heaters. The highest internal uptake was 13 mrem committed effective

dose equivalent (CEDE).

Failure to Follow Procedures with an Improper Entry into a High Radiation Area

Cornerstone Significance Cross-Cutting Report

Aspect Section

Occupational Green [H.11] - 71124.01

Radiation Safety NCV 05000382/2022002-01 Challenge the

Open/Closed Unknown

The inspectors reviewed a self-revealed Green non-cited violation of Technical Specification

6.8.1(a) for a worker's failure to follow procedures resulting in an improper entry to a high

radiation area. Specifically, on April 8, 2022, an operator worker received a dose rate alarm as

he entered into a high radiation area that he had not been made aware of the radiological

conditions and was not briefed for prior to entry.

Failure to Follow Procedures Regarding the Use of Lapel Air Sample Results

Cornerstone Significance Cross-Cutting Report

Aspect Section

Occupational Green [H.13] - 71124.03

Radiation Safety NCV 05000382/2022002-03 Consistent

Open/Closed Process

The inspectors identified a Green, non-cited violation of Technical Specification 6.8.1(a) for

the licensees failure to follow written radiation procedure, EN-RP-131, Air Sampling,

revision 17. Specifically, the licensee failed to follow section 5.1.12 for a lapel air sample

which indicated an intake could occur greater than four derived air concentration hours

(DAC-hrs) in an area that was not posted and controlled as an airborne radioactivity area.

2

This step required, in part, the licensee stop work; evacuate workers, collect grab samples,

and identify the source; inform workers in the area without respiratory protection that airborne

radioactivity was measured, and potential exposures would be evaluated; and if the conditions

causing the airborne radioactivity may still exist or are unknown, then immediately post and

control the area as an airborne radioactivity area.

Failure to Follow a Radiological Work Permit Requirement

Cornerstone Significance Cross-Cutting Report

Aspect Section

Occupational Green [H.5] - Work 71124.03

Radiation Safety NCV 05000382/2022002-04 Management

Open/Closed

The inspectors identified a Green, non-cited violation of Technical Specification 6.8.1(a) for

the licensees failure to follow radiation procedure, EN-RP-100, Radiation Worker

Expectations, revision 13, steps to follow the requirements set forth within a radiological work

permit (RWP). Specifically, workers failed to follow RWP 2022-0615, task 2, Removal of old

pressurizer heaters (includes cutting/grinding and all supporting activities), revision 2, which

required a continuous air monitor be located within the pressurizer cubicle during work

evolutions which have the potential for generating airborne activity.

Failure to Survey for an Airborne Radioactivity Area

Cornerstone Significance Cross-Cutting Report

Aspect Section

Occupational Green [H.14] - 71124.03

Radiation Safety NCV 05000382/2022002-05 Conservative

Open/Closed Bias

The inspectors identified a Green, non-cited violation of 10 Code of Federal Regulations

(CFR) 20.1501(a) for the licensees failure to reasonably evaluate surveys under the

circumstances to identify and post an airborne radioactivity area in accordance with

10 CFR 20.1902(d). Specifically, air sample survey WF3-AS-041722-0238, taken on April 17,

2022, was not evaluated under circumstances reasonable to determine the extent and

magnitude of airborne radioactivity levels which resulted in a failure to post and control an

airborne radioactivity area.

Inadequate Radiological Work Permit Procedure to Address Respirator Controls During Work

Activities.

Cornerstone Significance Cross-Cutting Report

Aspect Section

Occupational Green [H.14] - 71124.03

Radiation Safety NCV 05000382/2022002-06 Conservative

Open/Closed Bias

The inspectors identified a Green, non-cited violation of Technical Specification 6.8.1(a) for an

inadequate radiological work permit (RWP) procedure to address respirator controls during

work activities. Specifically, licensee procedure EN-RP-105, Radiological Work Permits,

revision 19, contained procedural steps outlining the process for removing respiratory controls

while an attachment to this procedure bypassed completion of an RWP revision and a total

effective dose equivalent (TEDE)/as low as (is) reasonably achievable (ALARA) evaluation

when changing respiratory protection controls.

3

Failure to Ensure Proper Phase Rotation for FLEX Equipment

Cornerstone Significance Cross-Cutting Report

Aspect Section

Mitigating Green [H.13] - 71152A

Systems NCV 05000382/2022002-07 Consistent

Open/Closed Process

A self-revealed Green finding and associated non-cited violation (NCV) of 10 CFR 50.155(c),

Mitigation of beyond-design-basis events, was identified when the licensee failed to ensure

equipment relied upon for the mitigation strategies for beyond-design basis external events

had the capability to perform the required functions. Specifically, the licensee failed to ensure

that required Diverse and Flexible Coping Strategies (FLEX) electrical receptacles had the

same electrical phase rotation as the FLEX N and N+1 core cooling pump motors such that

the core cooling pumps would operate as expected.

Inadequate Design of Differential Pressure Sensor Ambient Sensing Line

Cornerstone Significance Cross-Cutting Report

Aspect Section

Barrier Integrity Green None (NPP) 71153

NCV 05000382/2022002-08

Open/Closed

The inspectors reviewed a self-revealed Green finding and associated non-cited violation of

10 CFR Part 50, Appendix B, Criterion III, Design Control, when the licensee failed to

appropriately verify the adequacy of the shield building ventilation design. Specifically, a failed

stroke time test for shield building ventilation valve 114B on October 18, 2021, showed that an

ambient pressure sensing line failed to provide proper input since August 29, 2021. This

discovery revealed that train B of the shield building ventilation system and train B of the

controlled area ventilation system were inoperable for approximately 50 days. This condition

is prohibited by technical specifications and resulted in the issuance of a licensee event report

because the time these systems were inoperable exceeded the technical specification allowed

outage time.

Additional Tracking Items

None.

4

PLANT STATUS

Unit 3 entered the inspection period in power coast down at approximately 95 percent reactor

power. On April 2, 2022, the unit was shut down for refueling outage 24. On June 18, 2022, the

reactor was made critical following completion of the refueling outage and returned to full power

on June 23, 2022. On June 24, 2022, the unit experienced an unplanned trip due to the

automatic closing of main steam isolation valve 2. The plant was restarted on June 27, 2022,

and returned to full power on June 29, 2022, where it remained for the remainder of the

inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in

effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with

their attached revision histories are located on the public website at http://www.nrc.gov/reading-

rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared

complete when the IP requirements most appropriate to the inspection activity were met

consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection

Program - Operations Phase. The inspectors performed activities described in IMC 2515,

Appendix D, Plant Status, observed risk-significant activities, and completed onsite portions of

IPs. The inspectors reviewed selected procedures and records, observed activities, and

interviewed personnel to assess licensee performance and compliance with Commission rules

and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated readiness for seasonal extreme weather conditions prior to

the onset of seasonal extreme rain and wind for the following systems: component

cooling water, auxiliary component cooling water, startup transformers, and

emergency diesel generators on June 2, 2022.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (1 Sample)

The inspectors evaluated system configurations during partial walkdowns of the following

systems/trains:

(1) emergency feedwater system following a valid actuation of the system on

June 27, 2022

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the

safety injection system on May 6, 2022.

5

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a

walkdown and performing a review to verify program compliance, equipment functionality,

material condition, and operational readiness of the following fire areas:

(1) fire area RAB 19-001, elevation +21.00' component cooling water pump room A on

April 20, 2022

(2) fire area RAB 18-001, elevation +21.00' component cooling water heat exchanger

room A on May 14, 2022

71111.07A - Heat Exchanger/Sink Performance

Annual Review (IP Section 03.01) (1 Sample)

The inspectors evaluated readiness and performance of:

(1) component cooling water B heat exchanger on May 27, 2022.

71111.08P - Inservice Inspection Activities (PWR)

PWR Inservice Inspection Activities Sample (IP Section 03.01) (1 Sample)

(1) The inspectors verified that the reactor coolant system boundary, steam generator

tubes, reactor vessel internals, risk-significant piping system boundaries, and

containment boundary are appropriately monitored for degradation and that repairs

and replacements were appropriately fabricated, examined and accepted by

reviewing the following activities from April 7, 2022 to May 13, 2022:

03.01.a - Nondestructive Examination and Welding Activities.

Dye Penetrant Test Examination, Report No.: BOP-PT-22-012. Field Weld

FW-1 Seal Weld. Component ID: EFWMVAAA204A/B.

Ultrasonic Test Examination, Report No.: BOP-UT-22-001. Pipe to

Valve SI-512A. Component ID: SI-512A (ISI-V2507) FW-7. Safety Injection

System.

Ultrasonic Test Examination, Report No.: BOP-UT-22-002. Valve SI-512A to

Pipe. Component ID: SI-512A (ISI-C2507) FW-8. Safety Injection System.

Ultrasonic Test Examination, Report No.: W-ISI-UT-22-004. 4" Pip to Elbow

Weld. Component ID: 25-026, Reactor Coolant System.

Ultrasonic Test Examination, Report No.: W-ISI-UT-22-005. Elbow to 4: Pipe

Weld. Component ID: 25-027, Reactor Coolant System.

Ultrasonic Test Examination, Report No.: W-ISI-UT-22-001. Valve to 20" Pipe

Weld. Component ID: 45-008, Feedwater System.

Ultrasonic Test Examination, Report No.: W-ISI-UT-22-002. 20" Pipe to Valve

Weld. Component ID: 45-010, Feedwater System.

Ultrasonic Test Examination, Report No.: W-ISI-UT-22-003. Valve to 20" Pipe

Weld. Component ID: 46-006, Feedwater System.

6

Visual Test Examination - VT-1, Report No.: W-ISI-VT-22-028. Rigid Restraint

Attachment Weld. Component ID: FWRR-0283A, Emergency Feedwater

System.

Visual Test Examination - VT-3, Report No.: W-ISI-VT-22-029. Rigid Restraint.

Component ID: FWRR-0283, Emergency Feedwater System.

Radiograph Test Examination, Report No.: BOP-RT-22-001. Field Weld FW-7

Pipe to Valve SI-512A. Component ID: SI-512A. Safety Injection System.

Radiograph Test Examination, Report No.: BOP-RT-22-002. Field Weld FW-8

Valve SI-512A to Pipe. Component ID: SI-512A. Safety Injection System.

Phased Array Ultrasonic Test Examination of Previously Identified relevant

indications accepted for continued service. Report W-ISI-VE-22-001. 2" Drain

Nozzle to Safe-End Weld. Component ID: 07-009-WOL. Reactor Coolant

System.

Phased Array Ultrasonic Test Examination of Previously Identified relevant

indications accepted for continued service. Report W-ISI-VE-22-002. 2" Drain

Nozzle to Safe-End Weld. Component ID: 11-007-WOL. Reactor Coolant

System.

Welding associated with full replacement of the Safety Injection valve SI-512

A (ISI-V2507). Gas Tungsten Arc Welding. Work Order No. 527322-01. Field

Weld No. 7.

Welding associated with full replacement of the Safety Injection valve SI-512

A (ISI-V2507). Gas Tungsten Arc Welding. Work Order No. 527322-01. Field

Weld No. 8.

03.01.b - Pressurized-Water Reactor Vessel Upper Head Penetration Examination

Activities.

Visual Test Examination - Bare Metal Visual, Report No.: W-ISI-VT-22-042.

Reactor Vessel Closure Head RVCH CEDM Nozzles 1-87. Component

ID: 02-N-01X1 thru 02-N-87X1. Reactor Pressure Vessel.

Visual Test Examination - Bare Metal Visual, Report No.: W-ISI-VT-22-043.

Reactor Vessel Closure Head RVCH Vent Line. Component ID: 02-N2-01X1.

Reactor Pressure Vessel.

Visual Test Examination - Bare Metal Visual, Report No.: W-ISI-VT-22-044.

Reactor Vessel Closure Head RVCH CEDM Nozzles92-101. Component

ID: 02-N-92X1 thru 02-N-101X1. Reactor Pressure Vessel.

03.01.c - Pressurized-Water Reactor Boric Acid Corrosion Control Activities.

Boric Acid Evaluation No. 19-WF3-0004, Condition Report CR-WF3-2019-

00140

Boric Acid Evaluation No. 19-WF3-0012, Condition Report CR-WF3-2019-

01063

Boric Acid Evaluation No. 19-WF3-0019, Condition Report CR-WF3-2019-

03032

Boric Acid Evaluation No. 19-WF3-0020, Condition Report CR-WF3-2019-

03053

Boric Acid Evaluation No. 19-WF3-0021, Condition Report CR-WF3-2019-

03302

Boric Acid Evaluation No. 19-WF3-0022, Condition Report CR-WF3-2019-

03311

7

Boric Acid Evaluation No. 19-WF3-0023, Condition Report CR-WF3-2019-

04894

Boric Acid Evaluation No. 19-WF3-0025, Condition Report CR-WF3-2019-

06358

Boric Acid Evaluation No. 19-WF3-0026, Condition Report CR-WF3-2019-

06379

Boric Acid Evaluation No. 19-WF3-0028, Condition Report CR-WF3-2019-

06373

Boric Acid Evaluation No. 20-WF3-0001, Condition Report CR-WF3-2020-

01131

Boric Acid Evaluation No. 20-WF3-0016, Condition Report CR-WF3-2020-

04595

Boric Acid Evaluation No. 21-WF3-0001, Condition Report CR-WF3-2021-

00085

Boric Acid Evaluation No. 21-WF3-0020, Condition Report CR-WF3-2021-

05655

Boric Acid Evaluation No. 21-WF3-0022, Condition Report CR-WF3-2021-

05516

Boric Acid Evaluation No. 21-WF3-0026, Condition Report CR-WF3-2021-

05559

03.01.d - Pressurized-Water Reactor Steam Generator Tube Examination Activities.

Per the licensee's current requirement, they were not required to perform any

Steam Generator tube inspections this outage.

The licensee did install a modification to the Steam Generators feed rings to

reduce harmonic vortexing that they have experienced since the installation of

the replacement Steam Generators in 2013.

Problem Identification and Resolution. Review of Inservice Inspection items.

(Inspection Procedure 71152 - Problem Identification and Resolution)

The inspector evaluated a sample of 29 condition reports associated with

inservice inspection activities. No findings or violations of more than minor

significance were identified.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01)

(1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control

room during plant startup following a refueling outage on June 18-19, 2022.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated licensee simulator-based just-in-time training

for a reactor startup followed by training involving a rapid downpower with steam line

break inside containment on June 27, 2022.

8

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (1 Sample)

The inspectors evaluated the accuracy and completeness of risk assessments for the

following planned and emergent work activities to ensure configuration changes and

appropriate work controls were addressed:

(1) elevated Green risk while restarting Unit 3 and bringing reactor to 100 percent power

following unplanned main steam isolation valve closure from June 27 to 29, 2022

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (3 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the

following operability determinations and functionality assessments:

(1) shutdown cooling train operability following loss of auxiliary component cooling water

pump B on May 9, 2022

(2) emergency feedwater pump AB operability following surveillance with less than

allowed differential pressure on June 11, 2022

(3) auxiliary component cooling water pump B operability following identification of raised

bearing temperatures on June 18, 2022

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02)

(2 Samples)

The inspectors evaluated the following temporary or permanent modifications:

(1) auxiliary component cooling water pump B motor was replaced with the component

cooling water pump AB motor on June 5, 2022

(2) reactor coolant system 1B cold leg resistance temperature detector thermowell was

plugged and existing core operating limit supervisory system detector used for

safety-related inputs on June 19, 2022

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the following post-maintenance testing activities to verify system

operability and/or functionality:

(1) component cooling water pump B testing after relay maintenance performed on

May 19, 2022

(2) reactor coolant system integrity checks following leaks from core element drive vent

valves on May 28, 2022

(3) auxiliary component cooling water pump B testing following replacement with

component cooling water pump AB on June 5, 2022

9

(4) engineered safety features actuation system testing for steam generator isolation

after relay replacement on June 27, 2022

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated refueling outage 24 activities from April 2 to June 20, 2022.

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance testing activities to verify system operability

and/or functionality:

Surveillance Tests (other) (IP Section 03.01) (3 Samples)

(1) emergency diesel generator B surveillance test on May 12, 2022

(2) control elements drop testing on June 18, 2022

(3) main turbine electronic and physical trip testing on June 19, 2022

Inservice Testing (IP Section 03.01) (1 Sample)

(1) main steam isolation valves A and B inservice test on April 2, 2022

Containment Isolation Valve Testing (IP Section 03.01) (1 Sample)

(1) leak rate test containment isolation valve, LRT-109, at penetration 63 and blind flange

on May 14, 2022

FLEX Testing (IP Section 03.02) (1 Sample)

(1) FLEX N+1 diesel generator 3-year preventative maintenance and 2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> run loaded

at 360 KW on May 11, 2022

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated how the licensee identifies the magnitude and extent of

radiation levels and the concentrations and quantities of radioactive materials and

how the licensee assesses radiological hazards.

Instructions to Workers (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated how the licensee instructs workers on plant-related

radiological hazards and the radiation protection requirements intended to protect

workers from those hazards.

10

Contamination and Radioactive Material Control (IP Section 03.03) (3 Samples)

The inspectors observed/evaluated the following licensee processes for monitoring and

controlling contamination and radioactive material:

(1) licensee surveys of potentially contaminated material leaving the radiological

controlled area.

(2) workers exiting containment and the radiologically controlled area during the refueling

outage.

(3) licensee surveys of potentially contaminated material leaving containment.

Radiological Hazards Control and Work Coverage (IP Section 03.04) (5 Samples)

The inspectors evaluated the licensee's control of radiological hazards for the following

radiological work:

(1) radiation work permit (RWP) 2022-0606, Minor Maintenance Activities

(2) RWP 2022-0610, Erect/Dismantle Scaffolding in the Reactor Containment Building

(3) RWP 2022-0635, Radiography including Radiation Protection Boundary Guards

(4) RWP 2022-0805, Tours and Inspections Outside the Reactor Containment Building

(5) RWP 2022-0708, Remove and Replace InCore Instruments (ICIs)

High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (5 Samples)

The inspectors evaluated licensee controls of the following high radiation areas and very

high radiation areas:

(1) spent resin tank room

(2) lock on cable for Tri-Nuke filter in the spent fuel building, +46' fuel handling building

(3) pre-concentrator filter cubicles

(4) fuel pool filter cubicle

(5) keys controlled at the access to the radiologically controlled areas by radiation

protection for high radiation areas and locked high radiation areas

Radiation Worker Performance and Radiation Protection Technician Proficiency

(IP Section 03.06) (1 Sample)

(1) The inspectors evaluated radiation worker and radiation protection technician

performance as it pertains to radiation protection requirements.

71124.03 - In-Plant Airborne Radioactivity Control and Mitigation

Permanent Ventilation Systems (IP Section 03.01) (2 Samples)

The inspectors evaluated the configuration of the following permanently installed ventilation

systems:

(1) control room ventilation system emergency filtration unit train A

(2) controlled ventilation areas filter unit train B

11

Temporary Ventilation Systems (IP Section 03.02) (1 Sample)

The inspectors evaluated the configuration of the following temporary ventilation systems:

(1) high efficiency particulate air filter setup for the cutting, grinding, and welding

associated with RWP 2022-0627

Use of Respiratory Protection Devices (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated the licensees use of respiratory protection devices.

Self-Contained Breathing Apparatus for Emergency Use (IP Section 03.04) (1 Sample)

(1) The inspectors evaluated the licensees use and maintenance of self-contained

breathing apparatuses.

71124.06 - Radioactive Gaseous and Liquid Effluent Treatment

Walkdowns and Observations (IP Section 03.01) (4 Samples)

The inspectors evaluated the following radioactive effluent systems during walkdowns:

(1) reactor main condenser evacuation system

(2) turbine gland sealing system

(3) discharge structure to the Mississippi River

(4) reactor gaseous waste management system

Sampling and Analysis (IP Section 03.02) (3 Samples)

Inspectors evaluated the following effluent samples, sampling processes and compensatory

samples:

(1) weekly liquid effluent sampling of the circulating water discharge outfall

(2) weekly sampling of dry cooling tower sump No. 2 outfall

(3) weekly turbine building/yard oil separator outfall

Dose Calculations (IP Section 03.03) (2 Samples)

The inspectors evaluated the following dose calculations:

(1) cumulative dose and dose rate summary for gaseous effluent release associated with

gaseous effluent release permit No. W3GB2019-005

(2) cumulative doses details for liquid effluent release associated with liquid effluent

release permit No. W3LB2019-009

Abnormal Discharges (IP Section 03.04) (1 Sample)

The inspectors evaluated the following abnormal discharges:

(1) There were no abnormal discharges identified during the inspection period.

12

71124.07 - Radiological Environmental Monitoring Program

Environmental Monitoring Equipment and Sampling (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated environmental monitoring equipment and observed

collection of environmental samples.

Radiological Environmental Monitoring Program (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the implementation of the licensees radiological

environmental monitoring program.

GPI Implementation (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated the licensees implementation of the Groundwater

Protection Initiative program to identify incomplete or discontinued program elements.

There were no incomplete or discontinued program elements identified.

OTHER ACTIVITIES - BASELINE

71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 02.04) (1 Sample)

(1) Unit 3 (April 1, 2021, through March 30, 2022)

MS06: Emergency AC Power Systems (IP Section 02.05) (1 Sample)

(1) Unit 3 (April 1, 2021, through March 30, 2022)

MS07: High Pressure Injection Systems (IP Section 02.06) (1 Sample)

(1) Unit 3 (April 1, 2021, through March 30, 2022)

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)

(1) Unit 3 (January 1, 2021, through March 31, 2022)

PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual

Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample

(IP Section 02.16) (1 Sample)

(1) Unit 3 (January 1, 2021, through March 31, 2022)

13

71152A - Annual Follow-up Problem Identification and Resolution

Annual Follow-up of Selected Issues (Section 03.03) (1 Sample)

The inspectors reviewed the licensees implementation of its corrective action program

related to the following issues:

(1) phase rotation reversal of AB FLEX core cooling pump power receptacle on

May 5, 2022

71153 - Follow Up of Events and Notices of Enforcement Discretion

Personnel Performance (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated the licensee response to an unplanned closure of main

steam isolation valve 2 and main feed isolation valve 2 and licensees performance

on June 24, 2022.

INSPECTION RESULTS

Failure to Adequately Plan and Control Worker Exposures As Low As (is) Reasonably

Achievable (ALARA) During the Removal of Pressurizer Heaters Resulting in Worker

Uptakes.

Cornerstone Significance Cross-Cutting Report

Aspect Section

Occupational Green [P.5] - 71124.01

Radiation Safety NCV 05000382/2022002-02 Operating

Open/Closed Experience

The inspectors identified a finding of very low safety significance (Green) for the licensee

having unplanned and unintended occupational internal radiation exposure because of

deficiencies in the licensees work planning and work control program. Specifically, the

licensee failed to appropriately implement aspects of EN-RP-105, Radiological Work

Permits (RWP), to maintain doses ALARA. Four workers (two radiation protection

technicians and two contract workers) received an uptake of airborne radioactive material

during the removal of pressurizer heaters. The highest internal uptake was 13 mrem

committed effective dose equivalent (CEDE).

Description: On April 18, 2022, two radiation protection technicians and two contract workers

(laborers) received uptakes from airborne radioactive materials during the replacement of

pressurizer heaters. The uptakes occurred as the pressurizer heaters were removed and

transported from the pressurizer shroud, through the shroud openings (several windows and

a door), and out through the pressurizer cubicle to a shielded storage container. During a

previous shift of this work evolution, a survey of the pressurizer shroud and two removed

heaters confirmed the Alpha Level 2, high contamination area conditions of the work area

(WF3-2204-00608). Two of the four laborers, those inside the pressurizer shroud and

removing the pressurizer heaters from the pressurizer, were wearing powered air purifying

respirators. The other workers, those outside the shroud but inside the pressurizer cubicle,

were not in powered air purifying respirators. The two laborers, outside pressurizer shroud,

did not enter the shroud. A radiation protection technician, providing job coverage, partially

entered the shroud as they surveyed the old pressurizer heaters being removed and were

placed into transport sleeves. Another radiation protection technician entered the high

14

contamination area of the pressurizer cubicle to remove radioactive trash at the end of the

job. These workers were identified with personnel contamination when exiting the

radiologically controlled area. The workers were sent for a whole body count to determine if

the workers received uptakes of radioactive material. The four workers working inside the

cubicle, but outside the shroud, received unintended uptakes of unanticipated airborne

radioactive material.

The licensees procedures required the creation of plans to minimize the exposure to workers

and to use radiological data and lessons learned from previous work.

Procedure EN-RP-105, Radiological Work Permits (RWP), revision 19, step 5.3.7 of the

RWP Planning Process states, in part, the licensee is to perform more rigorous planning for

work where contamination levels and the type of work to be performed results in a higher

potential for workers to be exposed to airborne alpha radioactivity during the work by:

  • Using relevant job history files
  • Understanding the physical characteristics and limitations of the work area
  • Planning for minimizing or eliminating spread of alpha contamination
  • Planning for minimizing or eliminating generation of airborne radioactivity

The inspectors compared the ALARA plans and results for the 2015 and 2022 pressurizer

heater replacement evolution and their associated radiological surveys. The inspectors were

unable to identify in either ALARA plan a specific plan or controls for the workers outside of

the shroud to minimize their exposures from the spread of alpha contamination when items

were removed from the shroud and any unanticipated alpha airborne radioactivity area.

The prior work history in the 2015 ALARA post-job review identified the contamination inside

of the shroud as an Alpha Level 2, high contamination area and an alpha airborne radiation

area. The plan provided no additional protective measures to the workers not working directly

inside the shroud, even though the removed pressurizer heaters were passed through the

openings of the shroud for transport out of the cubicle. The air sampler for the pressurizer

heater removal evolution was located near the work area inside the shroud. While a high

efficiency particulate air (HEPA) unit provided an engineering control through one shroud

opening to reduce the spread of airborne contamination, there were other large openings in

the shroud to the pressurizer cubicle and other areas above and below the pressurizer

shroud. These openings were present through which airborne radioactivity could spread. The

RWP was planned with misting, wetting, decontamination, and wrapping as critical steps to

reduce contamination levels and minimize the airborne hazard. In addition, the ALARA plan

and RWP considered the dose rates from the old pressurizer heaters to have the largest

impact on worker exposures. Dose rates on contact with the pressurizer heaters ranged from

80 millirem per hour (mR/hr) to 2,600 mR/hr and 30 mR/hr to 700 mR/hr at a foot. Therefore,

RWP 2015-0615 specified the old pressurizer heaters were to be removed from the

pressurizer cubicle as soon as practical while the additional measures to reduce exposure to

contamination (wetting, wrapping, etc.), seen as increasing exposure time to the higher dose

rates of the pressurizer heaters, were not used though planned.

The removed heaters were transported from under the shroud in capped polyvinyl chloride

sleeves to reduce the spread of alpha contamination and function as a carrying tool to move

the heaters to their storage location. The potential for contamination spread from the

transport sleeves was considered low. On November 13, 2015, a worker was documented

with facial contamination from transporting an old pressurizer heater in a transport sleeve and

15

the event was determined to not be attributed to poor radiation worker behavior (CR-WF3-

2015-08222). In response to this facial contamination, face shields were instituted for the

workers outside the shroud. No additional protective measures were considered for workers

not directly interfacing with the reactor coolant system boundary.

The 2022 ALARA plan was similar to the 2015 ALARA plan and evaluated the exposures for

the workers inside the shroud to the current and postulated radiological conditions as they

interfaced directly with reactor coolant system components. As in the 2015 ALARA plan, the

workers outside the shroud would not be interfacing with the reactor coolant system boundary

and their risk to additional hazards, such as exposures to alpha contamination and alpha

airborne radioactivity, was considered minimal. These workers had no specified protective

measures to minimize their exposure to alpha contamination or alpha airborne radioactivity

areas other than protective clothing for high contamination areas in the ALARA plan or RWP.

Similarly, in the 2015 ALARA plan and RWP, it directed the use of a HEPA hose to contain

radioactive material as the pressurizer heaters were removed from the pressurizer to

minimize contamination and powered air purifying respirators for the workers inside the

shroud. The air sampler for the pressurizer heater removal evolution was located near the

work area inside the shroud and the continuous air monitor placed outside the pressurizer

cubicle door.

For the current heater removal evolution, a survey of the first two removed heaters and

shroud areas supported an Alpha Level 2, high contamination area posting (WF3-2204-

00608) and the prior shift of pressurizer heater removals, air sample WF3-AS-041722-0238

indicated an airborne radioactivity area within the shroud at 0.518 derived air concentration

(DAC). An airborne radioactivity area is designated at 0.3 DAC. During the heater removal

which resulted in the four worker uptakes, air sample WF3-AS-041822-0303 indicated an

airborne radioactivity area inside the shroud of 5.4 DAC (2.62 DAC-beta/gamma and 2.78

DAC-alpha).

In addition, the dose rates of the removed heaters were known to affect the continuous air

monitor (an AMS-4) and challenge its ability to provide accurate air sample results. The

current dose rates for the pressurizer heaters in 2022 ranged from 120 mR/hr on contact to

2,400 mR/hr on contact. This situation led to the continuous air monitor being placed outside

the pressurizer cubicle door and created the inability to adequately assess or alert workers to

the changing airborne conditions in the pressurizer cubicle so they could minimize their dose.

The operating experience and lessons learned from the 2015 facial contamination event and

the resulting protective measures were not carried forward to the 2022 pressurizer heater

replacement in RWP 2022-0615. Further, no assessment was made for the potential

migration of airborne radioactivity from inside the shroud through the shroud openings into

the pressurizer cubicle. In the 2015 or 2022 ALARA plans, the plans and control measures

did not adequately inform or reduce the pressurizer cubicle workers exposure to the spread

of alpha contamination or airborne radioactivity. The licensee failed to learn from their

previous experience and include this in the 2022 pressurizer heater replacement.

Corrective Actions: The licensee entered the issue into their corrective action program to

evaluate the ALARA planning and control measures for the pressurizer replacement activities

for all personnel involved.

Corrective Action References: CR-WF3-2022-02805 and CR-WF3-2022-04924

16

Performance Assessment:

Performance Deficiency: The failure to adequately plan to control worker exposures ALARA

is a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor

because it was associated with the Program and Process attribute of the Occupational

Radiation Safety cornerstone and adversely affected the cornerstone objective to ensure the

adequate protection of the worker health and safety from exposure to radiation from

radioactive material during routine civilian nuclear reactor operation. Specifically, the failure to

plan and control worker exposures ALARA during the pressurizer heater removal evolution

resulted in unplanned internal dose with the highest CEDE of 13 mrem. In addition,

Inspection Manual Chapter 0612, appendix E, example 6.h states a performance deficiency is

more than minor if the performance deficiency resulted in inadequately controlled radiological

conditions such that the worker received or was likely to receive greater than 10 mrem CEDE.

Significance: The inspectors assessed the significance of the finding using IMC 0609

Appendix C, Occupational Radiation Safety SDP. The inspectors determined the finding to

be of very low safety significance (Green) because it was: (1) not associated with as low as

reasonably achievable (ALARA) planning or work controls, (2) there was no overexposure,

(3) there was no substantial potential for an overexposure, and (4) the ability to assess dose

was not compromised.

Cross-Cutting Aspect: P.5 - Operating Experience: The organization systematically and

effectively collects, evaluates, and implements relevant internal and external operating

experience in a timely manner. Operating experience is used to support daily work functions

with emphasis on the possibility that it could happen here, or it could happen again.

Specifically, the licensee failed to learn from their own history when planning this work and

include the lessons learned from 2015 in the 2022 pressurizer heater replacement evolution.

Enforcement:

Violation: Technical Specification 6.8.1(a) requires, in part, that written procedures shall be

established, implemented, and maintained covering applicable procedures recommended in

NRC Regulatory Guide 1.33, revision 2, appendix A, dated February 1978. Section 7.e of

Regulatory Guide 1.33, appendix A, requires radiation protection procedures for the

implementation of an ALARA program. The licensee established procedure EN-RP-105,

Radiological Work Permits, revision 19, to implement the ALARA program.

Procedure EN-RP-105, step 5.3.7. states, in part, the licensee is to perform more rigorous

planning for work where contamination levels and the type of work to be performed results in

a higher potential for workers to be exposed to airborne alpha radioactivity.

Contrary to the above, on April 18, 2022, the licensee failed to implement procedure

EN-RP-105 to perform more rigorous planning for work where contamination levels and the

type of work to be performed results in a higher potential for workers to be exposed to

airborne alpha radioactivity. Specifically, the ALARA planning and controls for the workers in

the pressurizer cubicle were inadequate, which resulted in the uptakes to two laborers and

two radiation protection technicians during the 2022 pressurizer heater replacement

evolution.

17

Enforcement Action: This violation is being treated as a non-cited violation, consistent with

Section 2.3.2 of the Enforcement Policy.

Failure to Follow Procedures with an Improper Entry into a High Radiation Area

Cornerstone Significance Cross-Cutting Report

Aspect Section

Occupational Green [H.11] - 71124.01

Radiation Safety NCV 05000382/2022002-01 Challenge the

Open/Closed Unknown

The inspectors reviewed a self-revealed Green non-cited violation of Technical Specification

6.8.1.a for a worker's failure to follow procedures resulting in an improper entry to a high

radiation area. Specifically, on April 8, 2022, an operator worker received a dose rate alarm

as he entered into a high radiation area that he had not been made aware of the radiological

conditions and was not briefed for prior to entry.

Description: On April 8, 2022, an operator worker entered a high radiation area (HRA) on the

4-foot elevation of the reactor containment building while logged onto radiation work

permit (RWP) 2022-0702, "Reactor Disassembly Activities," task 5. The individual entered the

reactor containment building tasked to secure the shutdown cooling vacuum priming when

required. Instead, as the operator entered the area, he was called by another worker to

observe the local reactor coolant system (RCS) level. Observing the RCS level required the

worker to climb a ladder to the reactor containment building sump platform. This area was

posted and controlled as an HRA, and the posting stated a requirement for a briefing by

radiation protection (RP) prior to entry. The change in work scope was not discussed or

authorized by RP prior to entry on the sump platform; thus, the worker was not briefed on the

radiological dose rates for entry. Upon ducking beneath the HRA barrier and posting and

traversing the ladder to the top of the sump platform, the operator received a dose rate alarm

on the alarming self-reading dosimeter (SRD) of 355 millirem per hour. This alarm was based

on a dose rate setpoint of 302 millirem per hour on his SRD. The dose rates the worker was

briefed for by RP for his assigned job were less than HRA conditions, based on

Survey WF3-2204-00087, dated April 3, 2022.

Procedure EN-RP-100, "Radiation Worker Expectations," revision 13, section 5.3, requires, in

part, that individuals with access to radiologically controlled areas (RCAs): [3] have no entry

to areas above seven feet without prior permission from RP; [6] observe and obey

radiological postings; [7] shall read, understand, and obey the RWP; and [9] know the

radiological conditions in their planned work area AND travel paths. Section 5.5[15] of

EN-RP-100 states, "If you receive an SRD dose rate alarm, THEN (a) back out of the affected

area, (b) notify others in the work area, and (c) immediately contact RP for direction."

RWP 2022-0702 instructed the worker to stop work if a dose rate alarm is received that is not

anticipated/discussed in the job brief. It then instructs the worker to place the job in a safe

condition, inform co-workers, exit the area, and notify RP. Discussions with RP while onsite,

informed the NRC that RP instructed the worker to immediately leave the RCA once they

were alerted to his dose rate alarm. However, the worker did not leave the RCA until

approximately 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> later based on the SRD histogram reviewed.

Additionally, attachment 8 to EN-RP-101, "Access Controls for Radiologically Controlled

Areas," revision 16, requires, in part, workers entering a HRA to (1) be logged onto an RWP

that allows access to the area, (2) be briefed and knowledgeable of radiological conditions in

the work area and travel path, and (3) only enter areas they have been briefed on.

18

Therefore, the NRC determined that the worker failed to comply with licensee procedures by

failing to obey the HRA radiological posting, traversing a ladder and path to an area with

radiological conditions he was not briefed for, not following the RWP he logged onto, and

failing to leave the area and the RCA immediately as instructed by RP.

Corrective Actions: The licensee assessed this issue and implemented multiple immediate

corrective actions, which included restricting the worker's access to the RCA, coaching, and

requiring a reverse brief from radiation workers to include scope of work, radiological

conditions, and travel paths to the work location.

Corrective Action References: CR-WF3-2022-02217

Performance Assessment:

Performance Deficiency: The failure to follow a licensee's procedural requirements for entry

into an HRA was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor

because it was associated with the Program & Process attribute of the Occupational

Radiation Safety cornerstone and adversely affected the cornerstone objective to ensure the

adequate protection of the worker health and safety from exposure to radiation from

radioactive material during routine civilian nuclear reactor operation. Specifically, the failure to

follow requirements involving radiological controls had the potential to increase the worker's

dose. The failure to follow procedural requirements by making an improper entry into an HRA

for which the worker was not briefed resulted in an increase to worker exposure of radiation

dose rates greater than the general area dose rates for which the worker was briefed.

Significance: The inspectors assessed the significance of the finding using IMC 0609

Appendix C, Occupational Radiation Safety SDP. The inspectors determined the finding to

be of very low safety significance (Green) because it was: (1) not associated with as low as

reasonably achievable (ALARA) planning or work controls, (2) there was no overexposure,

(3) there was no substantial potential for an overexposure, and (4) the ability to assess dose

was not compromised.

Cross-Cutting Aspect: H.11 - Challenge the Unknown: Individuals stop when faced with

uncertain conditions. Risks are evaluated and managed before proceeding. Specifically, the

worker failed to stop, contact RP, and assess the radiological conditions for the change in

work scope, as required, prior to entry on the sump platform. The worker was not briefed for

the dose rates in this area and was therefore unaware of the radiological hazard.

Enforcement:

Violation: Technical Specification 6.8.1(a) requires, in part, the written procedures be

established, implemented, and maintained covering the applicable RP procedures

recommended in appendix A to Regulatory Guide 1.33, section 7.e(1), for access control to

radiation areas including a radiation work permit system. The licensee established procedure

EN-RP-101, "Access Controls for Radiologically Controlled Areas," in part, to control access

to radiation areas which includes requirements for following a radiation work permit system.

Attachment 8 to EN-RP-101, revision 16, requires, in part, workers entering a HRA to (1) be

logged onto an RWP that allows access to the area, (2) be briefed and knowledgeable of

radiological conditions in the work area and travel path, and (3) only enter areas they have

19

been briefed on.

Contrary to the above, on April 8, 2022, a worker failed to implement and follow procedure

EN-RP-101 for entry into a HRA. Specifically, a worker failed to follow attachment 8, which

required the worker to follow the RWP that allows access to the work area, be briefed and

knowledgeable of radiological conditions in the work area and travel path, and only enter

areas they have been briefed for. As a result, the worker received a dose rate alarm on the

assigned SRD and failed to exit the RCA immediately as instructed by RP.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with

Section 2.3.2 of the Enforcement Policy.

Failure to Follow Procedures Regarding the Use of Lapel Air Sample Results

Cornerstone Significance Cross-Cutting Report

Aspect Section

Occupational Green [H.13] - 71124.03

Radiation Safety NCV 05000382/2022002-03 Consistent

Open/Closed Process

The inspectors identified a Green, non-cited violation of Technical Specification 6.8.1(a) for

the licensees failure to follow written radiation procedure, EN-RP-131, Air Sampling,

revision 17. Specifically, the licensee failed to follow section 5.1.12 for a lapel air sample

which indicated an intake could occur greater than four derived air concentration hours

(DAC-hrs) in an area that was not posted and controlled as an airborne radioactivity area.

This step required, in part, the licensee stop work; evacuate workers, collect grab samples,

and identify the source; inform workers in the area without respiratory protection that airborne

radioactivity was measured, and potential exposures would be evaluated; and if the

conditions causing the airborne radioactivity may still exist or are unknown, then immediately

post and control the area as an airborne radioactivity area.

Description: On April 17, 2022, during refueling outage 24, workers were cutting welds in

preparation for removing the pressurizer heaters from the bottom of the pressurizer. The work

was conducted in the pressurizer shroud, inside the pressurizer cubicle, on the 21-foot

elevation of containment. The workers were partially cutting the welds that connected the

pressurizer heaters to the pressurizer heater sleeves. This allowed the heaters to be easily

removed during the next portion of the work activity. As part of the radiological work permit

requirements, the workers wore lapel air samplers to monitor potential internal exposures in

the work area.

The NRC inspectors reviewed lapel air sample WF3-AS-041722-0246 taken on

April 17, 2022. This lapel air sample was from a workers breathing zone when they worked in

the pressurizer cubicle. The lapel air sample was collected at 2:40 pm, analyzed, and initially

assigned a dose of 13.94 mrem or 5.58 DAC-hrs. The lapel air sample was counted on an

iSolo alpha/beta counting system at 9:06 pm which was a 6 hour6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and 26 minutes delay from

the sample collection time. The sample was counted again after 13 hours1.50463e-4 days <br />0.00361 hours <br />2.149471e-5 weeks <br />4.9465e-6 months <br /> post collection

resulting in 12.78 mrem or 5.11 DAC-hrs. The sample was counted on an instrument (iSolo)

that compensated for and corrected the results for radon daughters, i.e., performs radon

discrimination.

According to the licensees procedure, EN-RP-131, Air Sampling, section 5.1.12, it stated, in

part, if a lapel air sample results indicated an intake could occur at greater than 4 DAC-hrs, in

20

an area that is not posted and controlled as an airborne radioactivity area, and radon

discriminating analysis was complete then:

Stop work,

Evacuate workers from the affected area, collect grab samples to determine if

airborne concentrations are sustained, and to identify the source if unknown,

Inform workers in the area without respiratory protection that airborne radioactivity

was measured, and potential exposures will be evaluated, and

If the conditions causing the airborne radioactivity may still exist or are unknown, then

immediately post and control the area as an airborne radioactivity area.

Procedure EN-RP-131, attachment 4, was used to document the results of lapel air samples.

For lapel air sample WF3-AS-041722-0246, the box was checked in attachment 4 stating that

the net activity was less than an activity corresponding to 10 mrem committed effective dose

equivalent (CEDE), or 4 DAC-hrs, and no further action was required. However, the sample

results indicated 13.94 mrem exposure at the initial count time with 6.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> delay post

collection and 12.78 mrem after 13 hours1.50463e-4 days <br />0.00361 hours <br />2.149471e-5 weeks <br />4.9465e-6 months <br /> post collection, which are both greater than

10 mrem CEDE.

In addition, procedure EN-RP-131, step 5.2.8 provided instructions on how to analyze a lapel

air sample. The instructions focused strictly on the internal dose assessment to a worker

based on the sample results. This step did not reference back or make note of step 5.1.12 to

use the lapel air sample results to post and control an airborne radioactivity area. The

separation of this information in the analysis and decision-making sections led workers to not

recognize occurrences when lapel air sample results indicated an airborne radioactivity area

and that additional actions were required.

The license failed to follow procedure steps to stop work; evacuate the workers, obtain grab

samples, and identify the source; inform the workers in the area without respiratory protection

that airborne radioactivity was measured, and potential exposures will be evaluated; and post

and control the area as an airborne radioactivity area.

Corrective Actions: The licensee has entered the performance deficiency into their corrective

action program to determine appropriate actions.

Corrective Action References: CR-WF3-2022-04922

Performance Assessment:

Performance Deficiency: The failure to follow procedures regarding the use of lapel air

sample results was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor

because it was associated with the Program & Process attribute of the Occupational

Radiation Safety cornerstone and adversely affected the cornerstone objective to ensure the

adequate protection of the worker health and safety from exposure to radiation from

radioactive material during routine civilian nuclear reactor operation. Specifically, the licensee

did not follow their procedure to stop work; evacuate the workers, obtain grab samples, and

identify the source; inform the workers in the area without respiratory protection that airborne

radioactivity was measured, and potential exposures will be evaluated; and post and control

the area as an airborne radioactivity area. Additionally, the finding was similar to Inspection

21

Manual Chapter 0612, Power Reactor Inspection Reports - Examples of Minor Issues,

appendix E, example 6(h). This example states a performance deficiency was more than

minor if the performance deficiency results in a failure of radiological controls that could result

or resulted in an exposure equal to or greater than 10 mrem CEDE. In this case, the failure to

follow procedural steps after receiving lapel air sample results greater than 4 DAC-hrs

(10 mrem CEDE), resulted in workers being in an unknown airborne radioactivity area with

exposures greater than 10 mrem CEDE, specifically 13.94 mrem and 12.78 mrem CEDE.

Significance: The inspectors assessed the significance of the finding using IMC 0609

Appendix C, Occupational Radiation Safety SDP. The inspectors determined the finding had

very low safety significance (Green) because: (1) it was not associated with ALARA planning

and work controls, (2) it was not an overexposure, (3) there was no substantial potential for

overexposure, and (4) the ability to assess dose was not compromised.

Cross-Cutting Aspect: H.13 - Consistent Process: Individuals use a consistent, systematic

approach to make decisions. Risk insights are incorporated as appropriate. Specifically, the

procedure had disjointed analysis and decision-making sections which did not allow a worker

to consistently process lapel air samples which may require decisions for stopping work,

evacuating workers, providing additional sampling, informing workers of the airborne

radioactivity areas, and resulting exposures, and posting and controlling airborne radioactivity

areas when the criteria was reached.

Enforcement:

Violation: Technical Specifications 6.8.1(a) requires, in part, that written procedures shall be

established, implemented, and maintained covering the procedures recommended in

Regulatory Guide 1.33, revision 2, appendix A, dated February 1978. Regulatory Guide 1.33,

appendix A, section 7.e. requires procedures for Airborne Radioactivity Monitoring. The

licensee established procedure EN-RP-131, Air Sampling, revision 17, to provide standard

instructions for obtaining radiological air samples and for determining the concentration of

airborne particulate, iodine, tritium, and noble gas radioactivity.

Procedure EN-RP-131, Air Sampling, revision 17, section 5.1.12 states, in part, that if lapel

air sample results indicated an intake could occur at greater than 4 DAC-hrs, in an area that

is not posted and controlled as an airborne radioactivity area, and radon discriminating

analysis was complete, the licensee will: stop work; evacuate workers from the affected area,

collect grab samples to determine if airborne concentrations are sustained and to identify the

source if unknown; inform workers in the area without respiratory protection that airborne

radioactivity was measured and potential exposures will be evaluated; and if the conditions

causing the airborne radioactivity may still exist or are unknown, then immediately post and

control the area as an airborne radioactivity area.

Contrary to the above, on April 17, 2022, the licensee failed to follow procedure EN-RP-131,

Air Sampling, revision 17, section 5.1.12, when lapel air sample results indicated an intake

could occur at greater than 4 DAC-hrs, in an area that is not posted and controlled as an

airborne radioactivity area, and radon discrimination was complete. Specifically, the licensee

did not stop work; evacuate workers from the affected area, collect grab samples to

determine if airborne concentrations are sustained, and to identify the source if unknown;

inform workers in the area without respiratory protection that airborne radioactivity was

measured and potential exposures will be evaluated; and if the conditions causing the

airborne radioactivity may still exist or are unknown, then immediately post and control the

area as an airborne radioactivity area.

22

Enforcement Action: This violation is being treated as a non-cited violation, consistent with

Section 2.3.2 of the Enforcement Policy.

Failure to Follow a Radiological Work Permit Requirement

Cornerstone Significance Cross-Cutting Report

Aspect Section

Occupational Green [H.5] - Work 71124.03

Radiation Safety NCV 05000382/2022002-04 Management

Open/Closed

The inspectors identified a Green, non-cited violation of Technical Specification 6.8.1(a) for

the licensees failure to follow radiation procedure, EN-RP-100, Radiation Worker

Expectations, revision 13, steps to follow the requirements set forth within a radiological work

permit (RWP). Specifically, workers failed to follow RWP 2022-0615, task 2, Removal of old

pressurizer heaters (includes cutting/grinding and all supporting activities), revision 2, which

required a continuous air monitor be located within the pressurizer cubicle during work

evolutions which have the potential for generating airborne activity.

Description: On April 18, 2022, during refueling outage 24, two pipefitters (laborers) and two

radiation protection technicians were contaminated during the removal of pressurizer heaters.

The primary pressurizer heater removal work took place inside the pressurizer shroud, in the

pressurizer cubicle, on the 21-foot elevation of containment. This work was conducted under

the requirements of RWP 0615, task 2. Two laborers, located inside the shroud, removed the

pressurizer heaters, placed them in transport sleeves, then passed them through an opening

in the shroud to two additional laborers inside the cubicle. These two laborers then passed

the pressurizer heaters from the pressurizer cubicle to other workers for storage. The

laborers inside the shroud wore powered air purifying respirators while the rest of the workers

wore standard anticontamination apparel.

Upon removing the J-1 pressurizer heater from its location, a blackish sludge came out of the

hole with some of the material landing on a laborer. Due to the remaining dose margin and

the presence of the unknown sludge, the radiation protection technician decided to stop the

job and have everyone exit the area.

When the workers attempted to exit the radiologically controlled area, the workers performing

work in the pressurizer cubicle alarmed the personnel contamination monitors. The workers

were sent for whole body counts to identify any intake of radioactive material to the workers.

Unknown to the workers while they were removing the pressurizer heaters, airborne

radioactivity levels had increased in the pressurizer cubicle. As a result, four workers, those

working in the pressurizer cubicle, received intakes of airborne radioactive material.

NRC inspectors reviewed the event and identified an RWP 0615, task 2 requirement was not

met. Specifically, the licensee did not implement the requirement that a continuous air

monitor be in the pressurizer cubicle during work evolutions which have the potential for

generating airborne activity. The location of the continuous air monitor during the activity was

outside the pressurize cubicle near the entranceway to the cubicle. This location was not

representative of the actual work area and did not allow the continuous air monitor to alert

workers of changing airborne radioactivity levels within the cubicle.

Corrective Actions: The licensee entered the issue into the corrective action program to

determine appropriate actions.

23

Corrective Action References: CR-WF3-2022-04924, CR-WF3-2022-03171

Performance Assessment:

Performance Deficiency: The failure to follow a radiological work permit requirement was a

performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor

because it was associated with the Human Performance attribute of the Occupational

Radiation Safety cornerstone and adversely affected the cornerstone objective to ensure the

adequate protection of the worker health and safety from exposure to radiation from

radioactive material during routine civilian nuclear reactor operation. Specifically, workers

within the pressurizer cubicle received unintended internal exposures from unanticipated

airborne radioactive material. Additionally, the finding was similar to Inspection Manual

Chapter 0612, Power Reactor Inspection Reports - Examples of Minor Issues, appendix E,

example 6(h). This example states that a performance deficiency was more than minor if it

results in a failure of radiological controls which could result or resulted in an exposure equal

to or greater than 10 mrem committed effective dose equivalent (CEDE). In this case, the

failure to have the continuous air monitor located in the work area resulted in a workers

unintended exposure of 13 mrem CEDE.

Significance: The inspectors assessed the significance of the finding using IMC 0609

Appendix C, Occupational Radiation Safety SDP. The inspectors determined the finding had

very low safety significance (Green) because: (1) it was not associated with ALARA planning

and work controls, (2) it was not an overexposure, (3) there was no substantial potential for

overexposure, and (4) the ability to assess dose was not compromised.

Cross-Cutting Aspect: H.5 - Work Management: The organization implements a process of

planning, controlling, and executing work activities such that nuclear safety is the overriding

priority. The work process includes the identification and management of risk commensurate

to the work and the need for coordination with different groups or job activities. Specifically,

the possibility of generating airborne radioactivity was an identified risk for this work and a

continuous air monitor in operation was required within the associated RWP to protect the

workers within the cubicle and mitigate this risk. However, upon execution of the RWP, this

requirement was not met.

Enforcement:

Violation: Technical Specifications 6.8.1(a) requires, in part, that written procedures shall be

established, implemented, and maintained covering applicable procedures recommended in

NRC Regulatory Guide 1.33, revision 2, appendix A, dated February 1978. Regulatory

Guide 1.33, appendix A, section 7.e. requires procedures for Access Control to Radiation

Areas Including a Radiation Work Permit (RWP) System. The licensee established

procedure EN-RP-100, Radiation Worker Expectations, revision 12, which established basic

radiation protection requirements and expectations for radiation workers engaged in

radiological work that included the use of radiological work permits.

Procedure EN-RP-100, section 5.3 states, in part, the RWP shall be read, understood, and

obeyed when workers are to enter a radiologically controlled area. The workers were

assigned RWP 2022-0615, task 2, Removal of old pressurizer heaters (includes

cutting/grinding and all supporting activities), revision 2, which required a continuous air

monitor be located in the pressurizer cubicle during work evolutions that have the potential for

24

generating airborne activity.

Contrary to the above, on April 18, 2022, workers failed read, understand, and obey the

RWP 2022-0615, task 2, revision 2 requirement to locate a continuous air monitor in the

pressurizer cubicle during work evolutions that had the potential for generating airborne

radioactivity. Specifically, there was no continuous air monitor in the cubicle to alert workers

of a generated airborne radioactivity area when removing the pressurizer heaters from the

pressurizer. This resulted in a worker receiving an unintended exposure of 13 mrem CEDE.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with

Section 2.3.2 of the Enforcement Policy.

Failure to Survey for an Airborne Radioactivity Area.

Cornerstone Significance Cross-Cutting Report

Aspect Section

Occupational Green [H.14] - 71124.03

Radiation Safety NCV 05000382/2022002-05 Conservative

Open/Closed Bias

The inspectors identified a Green, non-cited violation of 10 CFR 20.1501(a) for the licensees

failure to reasonably evaluate surveys under the circumstances to identify and post an

airborne radioactivity area in accordance with 10 CFR 20.1902(d). Specifically, air sample

survey WF3-AS-041722-0238, taken on April 17, 2022, was not evaluated under

circumstances reasonable to determine the extent and magnitude of airborne radioactivity

levels which resulted in a failure to post and control an airborne radioactivity area.

Description: On April 17, 2022, during Waterford-3s refueling outage, pipefitters were

conducting work to prepare for the removal of heaters from the bottom of the pressurizer.

This work was taking place within the pressurizer shroud, inside the pressurizer cubicle, on

the 21-foot elevation of containment. The workers were partially cutting the welds that

connected the pressurizer heaters to their heater sleeves. This job allowed the welds to be

broken in a later work activity so that the pressurizer heaters could be removed from the

pressurizer.

In association with this job, the inspectors identified air sample survey WF3-AS-041722-0238,

taken on April 17, 2022, was not evaluated in a reasonable time period to post the area as an

airborne radioactivity area and inform workers of the conditions. The air sample was collected

from 9:15 a.m. to 10:40 a.m. The sample was counted on an iSolo alpha/beta counting

system at 12:16 p.m., an hour and 36 minutes after its collection. The resulting count

determined a total derived air concentration (DAC) for beta/alpha airborne radioactivity of 0.8.

This value is roughly 2.5 times over the threshold for posting an airborne radioactivity area at

0.3 DAC.

Licensee procedure EN-RP-131, Air Sampling, revision 17, contained the requirements for

posting of airborne radioactivity areas in accordance with 10 CFR 20.1902(d). Section 5.1.12

of this procedure stated, in part, that if air sample results indicate total airborne concentration

greater than or equal to 0.3 DAC, in an area that is not posted and controlled as an airborne

radioactivity area, the licensee will post and control the area as an airborne radioactivity area.

The sample was counted on an instrument (iSolo) that compensated and corrected the

activity for radon daughter products, i.e., discriminated radon from the total activity.

Procedure EN-RP-304, Operation of Counting Equipment, revision 6, section 6.3.8, step 8,

25

stated if a sample count time is within six hours of the sample stop time, then the

compensated value may be used. However, the licensee attributed the initial high count to

radon daughter products with no documented justification or discussion for this conclusion.

The licensee decided to conduct follow-up counts to factor out the radon daughter products.

They conducted additional counts at 7.3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> and 17.3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> post collection of the sample.

The resulting counts were a total DAC of 0.657 and 0.518, respectively. Neither of these

results are below the threshold for posting an airborne radioactivity area. The licensee

attributed these results to radon daughter products and did not consider the counting

equipment discriminated radon daughter from the resulting activity.

Because the licensee did not evaluate this survey in a timely manner, the area was not

posted as an airborne radioactivity area in accordance with 10 CFR 20.1902(d), work

continued within the location, and workers were not informed of the changing radiological

conditions.

Corrective Actions: The licensee entered the performance deficiency into their corrective

action program to determine appropriate actions.

Corrective Action References: CR-WF3-2022-03296, CR-WF3-2022-03297, CR-WF3-2022-

04921

Performance Assessment:

Performance Deficiency: Failure to evaluate a survey as required by 10 CFR 20.1501(a) in

the work area of the pressurizer cubicle to identify and post an airborne radioactivity area in

accordance with 10 CFR 20.1902(d) was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor

because it was associated with the Program & Process attribute of the Occupational

Radiation Safety cornerstone and adversely affected the cornerstone objective to ensure the

adequate protection of the worker health and safety from exposure to radiation from

radioactive material during routine civilian nuclear reactor operation. This resulted in workers

unknowingly being exposed to an unidentified airborne radioactivity area and receiving

additional unintended exposures.

Significance: The inspectors assessed the significance of the finding using IMC 0609

Appendix C, Occupational Radiation Safety SDP. The inspectors determined the finding had

very low safety significance (Green) because: (1) it was not associated with ALARA planning

and work controls, (2) it was not an overexposure, (3) there was no substantial potential for

overexposure, and (4) the ability to assess dose was not compromised.

Cross-Cutting Aspect: H.14 - Conservative Bias: Individuals use decision making-practices

that emphasize prudent choices over those that are simply allowable. A proposed action is

determined to be safe in order to proceed, rather than unsafe in order to stop. Specifically,

individuals involved in the counting of the air sample assumed radon daughter products were

contributing to the results instead of recognizing the equipment used compensated for radon

daughters. This caused the licensee to not identify and post the area as an airborne

radioactivity area.

Enforcement:

26

Violation: Title 10 CFR 20.1501(a), states in part, each licensee shall make or cause to be

made surveys of areas that may be necessary for the licensee to comply with the regulations

in this part and are reasonable under the circumstances to evaluate the magnitude and extent

of radiation levels and the potential radiological hazards of the radiation levels and residual

radioactivity detected.

Title 10 CFR 20.1902(d) states, in part, the licensee shall post each airborne radioactivity

area with a conspicuous sign bearing the radiation symbol and the words "Caution, Airborne

Radioactivity Area." The licensee implemented 10 CFR 20.1902(d) requirements through

procedure EN-RP-131, Air Sampling, revision 17. Section 5.1.12 stated, in part, that if air

sample results indicate total airborne concentration greater than or equal to 0.3 DAC, in an

area that is not posted and controlled as an airborne radioactivity area, the licensee will post

and control the area as an airborne radioactivity area.

Contrary to the above, on April 17, 2022, the licensee failed to make or cause to be made

surveys of areas that may be necessary for the licensee to comply with the regulations in this

part and are reasonable under the circumstances to evaluate the magnitude and extent of

radiation levels and the potential radiological hazards of the radiation levels and residual

radioactivity detected. Consequently, the licensee failed to post and control an airborne

radioactivity area when air sample results indicated a total airborne concentration of greater

than or equal to 0.3 DAC.

Specifically, air sample survey WF3-AS-041722-0238 was taken and the counting of the

sample was delayed such that the results were not evaluated for over 58 hours6.712963e-4 days <br />0.0161 hours <br />9.589947e-5 weeks <br />2.2069e-5 months <br /> while work

continued within the area. This resulted in a failure to post and control this area as an

airborne radioactivity area.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with

Section 2.3.2 of the Enforcement Policy.

Inadequate Radiological Work Permit Procedure to Address Respirator Controls During Work

Activities.

Cornerstone Significance Cross-Cutting Report

Aspect Section

Occupational Green [H.14] - 71124.03

Radiation Safety NCV 05000382/2022002-06 Conservative

Open/Closed Bias

The inspectors identified a Green, non-cited violation of Technical Specification 6.8.1(a) for

an inadequate radiological work permit (RWP) procedure to address respirator controls

during work activities. Specifically, licensee procedure EN-RP-105, Radiological Work

Permits, revision 19, contained procedural steps outlining the process for removing

respiratory controls while an attachment to this procedure bypassed completion of an RWP

revision and a total effective dose equivalent (TEDE)/as low as (is) reasonably achievable

(ALARA) evaluation when changing respiratory protection controls.

Description: On April 17, 2022, during the refueling outage, workers were performing

preparatory work for the removal of the pressurizer heaters from the bottom of the

pressurizer. This job was performed in the pressurizer shroud, inside the pressurizer cubicle,

on the 21-foot elevation of containment. The workers were to partially cut the welds that

connected the heaters to their heater sleeves.

27

The inspectors reviewed RWP 2022-0615, task 2, Removal of Old Pressurizer Heaters

(includes cutting/grinding and all supporting activities), revision 2, and its supporting

documentation, such as surveys and TEDE/ALARA evaluations. TEDE/ALARA evaluation

number 2022-0615-02, Removal of Old Pressurizer Heater, required the use of powered air

purifying respirators (PAPRs) during the work performed on this task with potential airborne

radioactivity levels approaching 0.38 derived air concentrations. However, documentation

showed that during the weld cutting for this job, the workers did not wear PAPRs. The

licensee used procedure EN-RP-105, attachments 5, RWP Field Change, to document their

in-field change decision to remove respirator use for this job.

Procedure EN-RP-105, step 5.7.1, described the scope of RWP field changes and stated, in

part, that an RWP field change may be used to change protective requirements on a case-by-

case basis for a particular entry or specific evolution within the job (for example, allowing

scaffold builders to wear double gloves instead of double protective clothing when supporting

a valve rebuild). Inspectors reviewed the in-field change document and noted that the

respiratory protection requirement was removed for the entire length of the weld cutting job

and was not changed for a specific portion of the job., e.g., setting up the cutting equipment

at the cut location.

Procedure EN-RP-105, attachment 5, was internally inconsistent with section 5.7 of the

procedure which described the scope of in-field changes. Specifically, attachment 5 included

language that stated ALARA/Supervisor approval is required for field changes involving:

changing respiratory protection requirements and changing the TEDE/ALARA evaluations.

This specific language in attachment 5 created a new criterion, new allowance, to the in-field

change process which was not contained in section 5.7.1 of the procedure.

In addition, procedure EN-RP-105, step 5.8.1, RWP Revision, stated, in part, the licensee

was to revise RWPs for conditions involving changes in work scope which make the RWP

controls insufficient and which do not meet the criteria for a field change as described in

section 5.7, and for changes in radiological protective requirements for the duration of the job.

These two criteria indicated a revision to the RWP was required for a change in respiratory

protection requirements; specifically relaxing the requirement to wear PAPRs for the duration

of the cutting job.

Further, step 5.8.2.d, stated, if respiratory protection requirements are changed, then

perform a TEDE/ALARA evaluation according to procedure EN-RP-503, Selection, Issue and

Use of Respiratory Protection Equipment. This procedural step was to ensure workers were

adequately protected for changes of respirator requirements within a work area. The in-field

change did not reflect a reevaluated TEDE/ALARA evaluation to relax the respiratory

requirement for workers to use PAPRs.

After reviewing procedure EN-RP-105, Radiological Work Permit, the inspectors determined

the procedural steps 5.7.1, 5.8.1, and 5.8.2.d conflicted with attachment 5. The language in

attachment 5 of the procedure allowed workers to understand the relaxing of respiratory

requirements was an acceptable action that could be performed in the field without additional

required actions. Due to this inconsistency, a worker did not adhere to the other procedural

steps, such as performing an RWP revision and a TEDE/ALARA evaluation, when removing

respiratory protection controls for a job. These steps are important to ensure workers are

adequately protected while maintaining their doses ALARA within the work area.

28

Corrective Actions: The licensee has entered the performance deficiency into their corrective

action program to determine appropriate actions.

Corrective Action References: CR-WF3-2022-04923

Performance Assessment:

Performance Deficiency: Inadequate RWP procedure to address respirator controls during

work activities was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor

because it was associated with the Program & Process attribute of the Occupational

Radiation Safety cornerstone and adversely affected the cornerstone objective to ensure the

adequate protection of the worker health and safety from exposure to radiation from

radioactive material during routine civilian nuclear reactor operation. The inconsistent process

within procedure EN-RP-105 created performance gaps when evaluating, assessing, and

controlling worker exposures from unintended and unanticipated sources and maintaining

doses ALARA.

Significance: The inspectors assessed the significance of the finding using IMC 0609

Appendix C, Occupational Radiation Safety SDP. The inspectors determined the finding had

very low safety significance (Green) because: (1) the performance deficiency was associated

with ALARA planning or work controls and (2) the average collective dose was less than

135 person-rem for the pressurized-water reactor.

Cross-Cutting Aspect: H.14 - Conservative Bias: Individuals use decision making-practices

that emphasize prudent choices over those that are simply allowable. A proposed action is

determined to be safe in order to proceed, rather than unsafe in order to stop. Specifically,

field changes were made to radiological controls for a job via an in-field change form with

multiple levels of supervisory approval that did not question if the decision to remove

respiratory protection might require a more rigorous process or if other procedural steps

applied to this decision (RWP revision and TEDE/ALARA evaluation).

Enforcement:

Violation: Technical Specifications 6.8.1(a), requires, in part, that written procedures shall be

established, implemented, and maintained covering applicable procedures recommended in

NRC Regulatory Guide 1.33, revision 2, appendix A, dated February 1978. Appendix A,

section 7.e. requires procedures for Access Control to Radiation Areas Including a Radiation

Work Permit (RWP) System. The licensee established procedure EN-RP-105, Radiological

Work Permits, revision 19, to implement a radiological work permit system.

Procedure EN-RP-105, step 5.8.1, RWP Revision, stated, in part, the licensee was to revise

RWPs for conditions involving changes in work scope which make the RWP controls

insufficient and which do not meet the criteria for a field change as described in section 5.7,

and for changes in radiological protective requirements for the duration of the job. In addition,

step 5.8.2.d, stated, if respiratory protection requirements are changed, then perform a

TEDE/ALARA evaluation according to procedure EN-RP-503, Selection, Issue and Use of

Respiratory Protection Equipment.

Procedure EN-RP-105, attachment 5, stated, in part, ALARA/Supervisor approval is required

for field changes involving: changing respiratory protection requirements and changing the

TEDE/ALARA evaluations.

29

Contrary to the above, on April 17, 2022, the use of procedure EN-RP-105, attachment 5,

which was internally inconsistent, resulted in the licensees failure to follow the requirements

in procedure EN-RP-105, step 5.8.1, RWP Revision, for a revision to RWPs for conditions

involving changes in work scope which make the RWP controls insufficient and which do not

meet the criteria for a field change as described in section 5.7, and for changes in radiological

protective requirements for the duration of the job. In addition, step 5.8.2.d, required that if

respiratory protection requirements are changed, then perform a TEDE/ALARA evaluation

according to procedure EN-RP-503, Selection, Issue and Use of Respiratory Protection

Equipment. Specifically, workers used attachment 5 to change respiratory protection

requirements in the field without adhering to additional requirements within the procedure

such as performing an RWP revision and reassessing the associated TEDE/ALARA

evaluation.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with

Section 2.3.2 of the Enforcement Policy.

Failure to Ensure Proper Phase Rotation for FLEX Equipment

Cornerstone Significance Cross-Cutting Report

Aspect Section

Mitigating Green [H.13] - 71152A

Systems NCV 05000382/2022002-07 Consistent

Open/Closed Process

A self-revealed Green finding and associated non-cited violation (NCV) of 10 CFR 50.155(c),

Mitigation of beyond-design-basis events, was identified when the licensee failed to ensure

equipment relied upon for the mitigation strategies for beyond-design basis external events

had the capability to perform the required functions. Specifically, the licensee failed to ensure

that required Diverse and Flexible Coping Strategies (FLEX) electrical receptacles had the

same electrical phase rotation as the FLEX N and N+1 core cooling pump motors such that

the core cooling pumps would operate as expected.

Description: As part of the licensees Phase 2 strategies as required by NRC Order

EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies

for Beyond-Design-Basis External Events, the licensee committed to the guidance described

in NEI 12-06, Diverse and Flexible Coping Strategies (FLEX) Implementation Guide,

revision 0. NRC Order EA-12-049 has since been codified by 10 CFR 50.155(c), Mitigation

of beyond-design-basis events.

Specifically for FLEX core cooling capabilities, the licensee developed strategies that

incorporate the use of the permanently installed charging pumps along with FLEX N and N+1

core cooling pumps. The FLEX N core cooling pump is permanently mounted on the -35

elevation of the reactor auxiliaries building. The FLEX N+1 core cooling pump is stored in the

FLEX N+1 building in the owner-controlled area of the site. Either pump can be implemented

to provide water to either the reactor coolant system (RCS) or to a steam generator.

One of the licensees strategies for core cooling includes powering one FLEX core cooling

pump and one charging pump using a FLEX diesel generator through a permanently installed

charging pump circuit. One of the two FLEX diesel generators would provide power into an

existing 480V safety-related bus. The AB swing bus would be aligned to the powered bus.

The two busses would then separately power the charging pump and the FLEX core cooling

pump. In this situation, the FLEX core cooling pump would not have worked because the AB

30

receptacle was wired incorrectly and provided electricity with a reverse phase rotation.

During installation of FLEX equipment in 2015, the licensee tested the FLEX electrical

receptacles that are routed from the charging pump breakers. One individual tested FLEX

receptacles A and B while another individual tested the AB receptacle. All receptacles were

signed off as passing the phase rotation test, but when the FLEX N core cooling pump was

energized by the B FLEX receptacle the pump turned counterclockwise, or backwards from

the required direction for the pump to work properly. The licensee then swapped leads on the

FLEX N core cooling pump which then passed the rotation test on November 25, 2015.

On March 29, 2020, the licensee performed a rotation check of the FLEX N+1 core cooling

pump when also powered from the B receptacle; the pump rotated in the wrong direction. The

licensee then swapped the leads for the FLEX N+1 core cooling pump ensuring that it would

also rotate in the correct direction when plugged into the B FLEX receptacle, exactly like the

FLEX N core cooling pump.

On June 1, 2021, the licensee powered the FLEX N core cooling pump from the AB

receptacle and again the pump spun in the reverse direction. The licensee found through

troubleshooting that the FLEX A and B electrical receptacles as well as the FLEX N and N+1

core cooling pumps were all wired opposite from the initial installation requirements; however,

they all worked correctly when used together. The FLEX AB electrical receptacle was still

installed in accordance with initial installation requirements and would therefore cause

reverse rotation. On June 2, 2021, the licensee swapped the leads for the FLEX AB

receptacle to bring all the FLEX receptacles and FLEX core cooling pumps in alignment so

they would all work properly when used together.

Per the licensees FLEX strategy requirements for FLEX fluid and electrical connections

found in Technical Requirements Manual (TRM) 3.13.3, Table 3.13-2, FLEX Connections

that Directly Perform a FLEX Mitigation Strategy for the Key Safety Functions, the FLEX AB

electrical receptacle, FLEXEDSC31AB-4C1, is required in Modes 1 through 4 along with

either the FLEX B receptacle for the primary connection point or the FLEX A receptacle for

the secondary connection point. Note 2 of Table 3.13-2 states that FLEX AB electrical

receptacle is required to be operable to support the core cooling strategy and is not

dependent upon which FLEX core cooling pump power source has been selected for FLEX

implementation.

From November 25, 2015, until March 29, 2020, only the FLEX N core cooling pump would

have rotated correctly when powered by the FLEX A or B electrical receptacles from the

charging pump breakers. For this period, the FLEX N+1 core cooling pump would only have

rotated correctly if using the FLEX AB receptacle. From March 29, 2020, until June 2, 2021,

FLEX N and N+1 core cooling pumps would have rotated correctly and performed their

function when powered by the FLEX A and B receptacles, but not when powered by the AB

receptacle.

Corrective Actions: The licensee swapped the leads for FLEX electrical receptacle AB so the

phase rotation matched FLEX receptacles A and B as well as FLEX N and N+1 core cooling

pump motors. The licensee updated drawings to reflect the new phase rotation of the

receptacles and pump motors that matched what was installed. The licensee also performed

an extent of condition to verify the phase rotation of all three FLEX electrical receptacles from

the charging pump electrical junction boxes as well as the phase rotation of the FLEX N and

31

N+1 core cooling pump motors to ensure they would work together. The licensee also verified

the phase rotation of the FLEX N and N+1 diesel generators.

Corrective Action References: CR-WF3-2021-02879

Performance Assessment:

Performance Deficiency: The licensee failed to ensure equipment relied upon for the

mitigation strategies for beyond-design basis external events had sufficient capability to

perform the required functions.

Screening: The inspectors determined the performance deficiency was more-than-minor

because it was associated with the design control attribute of the mitigating systems

cornerstone and adversely affected the cornerstone objective to ensure the availability,

reliability, and capability of systems that respond to initiating events to prevent undesirable

consequences. Specifically, the licensee failed to ensure that required FLEX electrical

receptacles had the same electrical phase rotation as the FLEX N and N+1 core cooling

pump motors such that the core cooling pumps would operate as expected.

Significance: The inspectors assessed the significance of the finding using NRC Inspection

Manual Chapter 0609 Appendix A, The Significance Determination Process (SDP) for

Findings At-Power. Using Exhibit 2, Mitigating Systems Screening Questions, Section E,

the inspectors determined the finding to be of very low safety significance (Green), because

the performance deficiency was associated with equipment not solely purposed for spent fuel

pool instrumentation or for containment venting, but it was associated with equipment

credited in a Phase 2 FLEX strategy such that all FLEX functions could still be completed in

accordance with existing plant procedures within the time allotted.

Cross-Cutting Aspect: H.13 - Consistent Process: Individuals use a consistent, systematic

approach to make decisions. Risk insights are incorporated as appropriate. Specifically, the

leads for FLEX N core cooling pump were swapped after it spun backwards during the initial

bump check in 2015. The licensee did not ensure the use of a systematic process was used

during installation of equipment or during troubleshooting unexpected as-found conditions.

Enforcement:

Violation: Title 10 CFR 50.155(b)(1), states, in part, strategies and guidelines to mitigate

beyond-design-basis events from natural phenomena must be capable of being implemented

site-wide and must include maintaining or restoring core cooling capabilities.

Title 10 CFR 50.155(c), states, in part, equipment relied on for the mitigation strategies and

guidelines required by paragraph (b)(1) of this section must have sufficient capability to

perform the functions to perform the functions required by paragraph (b)(1).

Contrary to the above, from November 25, 2015, until June 2, 2021, the licensee failed to

ensure equipment relied upon for restoring core cooling capabilities had sufficient capability

to perform the required functions. Specifically, the licensee failed to ensure that required

FLEX electrical receptacles had the same electrical phase rotation as the FLEX N and N+1

core cooling pump motors such that the core cooling pumps would operate as expected.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with

Section 2.3.2 of the Enforcement Policy.

32

Inadequate Design of Differential Pressure Sensor Ambient Sensing Line

Cornerstone Significance Cross-Cutting Report

Aspect Section

Barrier Integrity Green None (NPP) 71153

NCV 05000382/2022002-08

Open/Closed

The inspectors reviewed a self-revealed Green finding and associated non-cited violation of

10 CFR Part 50, Appendix B, Criterion III, Design Control, when the licensee failed to

appropriately verify the adequacy of the shield building ventilation design. Specifically, a

failed stroke time test for shield building ventilation valve 114B on October 18, 2021,

discovered that an ambient pressure sensing line failed to provide proper input since

August 29, 2021. This discovery revealed that train B of the shield building ventilation system

and train B of the controlled area ventilation system were inoperable for approximately

50 days. This condition is prohibited by technical specifications and resulted in the issuance

of a licensee event report because the time these systems were inoperable exceeded the

technical specification allowed outage time.

Description: The shield building ventilation system is an engineered safety feature charcoal

filtration system and is not normally in operation. It is designed to maintain the shield building

to reactor building annulus in a -8.0 INWC (inches water column) negative pressure and

preclude any contaminated air leakage through the shield building during a design basis

accident that causes a safety injection actuation signal. Shield building ventilation system air

is filtered through high efficiency particulate air filters and charcoal beds to reduce the

radiological dose to the general public. The shield building ventilation system has two basic

flow paths used for two phases of operation: the exhaust phase and the recirculation phase.

The shield building ventilation system shifts between the exhaust and recirculation phases of

operation to maintain vacuum using input from the ambient pressure sensing line until the

safety injection actuation signal is removed.

The controlled area ventilation system is an engineered safety feature charcoal filtration

system, and it is designed to maintain select rooms in the reactor auxiliary building at a

negative pressure. Select rooms include the A and B safeguards rooms, the -4 and -35 wing

areas, the shutdown heat exchanger rooms, the A and B valve galleries, and the -4 reactor

auxiliary building pipe penetration area. Controlled area ventilation system air is filtered

through high efficiency particulate air filters and charcoal beds to reduce the radiological dose

to the general public during a design basis accident. The controlled area ventilation system

uses ambient differential pressure to control damper positions to regulate the amount of

makeup air allowed into the suction of the air handling units.

On August 29, 2021, high winds and rain during Hurricane Ida allowed water intrusion into an

ambient pressure sensing line that provides input into differential pressure sensors

SBVIDPT5054B (shield building ventilation annulus to ambient differential pressure) and

HVRIDPT5272B (-4 reactor auxiliary building pipe penetration to ambient differential

pressure). Although not identified at the time, past plant computer data point trends indicate

that the erratic pressure readings began the day Hurricane Ida passed over Waterford 3. This

condition was only discovered on October 18, 2021, when the licensee was troubleshooting a

failed valve stroke time test. These differential pressure data points are not observed on a

regular basis.

After this condition was discovered, the licensee declared the shield building ventilation

33

system inoperable and entered technical specification 3.7.7 on October 18, 2021, at 0200.

Later the next day, it was discovered the suspect ambient sensing line also provides ambient

pressure input to HVRIDPT5272B and the controlled area ventilation system was declared

inoperable at 1000 on October 19, 2021. The sensing line was purged with air to remove the

water and post-maintenance testing was performed on both systems. Operability was

restored to the controlled area ventilation system at 2128 on October 19, 2021, and

operability was restored to the shield building ventilation system at 0316 on October 21,

2021. Shield building ventilation system train B and controlled area ventilation system train B

were inoperable for approximately 50 days; this period of inoperability exceeded their 7-day

allowed outage time in technical specification 3.7.7. Licensee Event Report 50-382/2021-003-

00, Non-Compliance with Technical Specifications due to Failed Ambient Pressure Input, was

submitted to the NRC on December 16, 2021.

Corrective Actions: The licensee plans to modify the subject sensing line to eliminate the

potential for water intrusion. The licensee also plans to generate a new calculated computer

point that compares the opposite train differential pressure transmitter SBVIDPT5054A with

SBVIDPT5054B values which will alarm in the control room when the error between these

two points exceeds a reasonable value continuously for a selected period of time.

Additionally, preventive maintenance will be revised to include draining the ambient sensing

line.

Corrective Action References: CR-WF3-2021-5760

Performance Assessment:

Performance Deficiency: The inspectors determined that the licensee failed to appropriately

verify the adequacy of a pressure sensing line design that impacts shield building and

controlled area ventilation was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor, and

therefore a finding, because it was associated with the Design Control attribute of the Barrier

Integrity cornerstone and adversely affected the cornerstone objective to provide reasonable

assurance that physical design barriers protect the public from radionuclide releases caused

by accidents or events. Specifically, the licensee failed to recognize that the design of the

ambient sensing line allowed it to fill with water and prevent train B of the shield building

ventilation system and train B of the controlled area ventilation system from being able to

perform their designed functions.

Significance: The inspectors assessed the significance of the finding using IMC 0609

Appendix A, The Significance Determination Process (SDP) for Findings At-Power.

Specifically, using Exhibit 3, Barrier Integrity Screening Questions, the inspectors

determined that this finding is of very low safety significance (Green), because the finding

only represented a degradation of the radiological barrier function provided for the control

room, auxiliary building, reactor building, or spent fuel pool.

Cross-Cutting Aspect: Not Present Performance. No cross-cutting aspect was assigned to

this finding because the inspectors determined the finding did not reflect present licensee

performance.

Enforcement:

Violation: Title 10 CFR Part 50, Appendix B, Criterion III, Design Control, requires, in part,

that design control measures shall be established to assure that applicable regulatory

34

requirements and the design bases are correctly translated into specifications, drawings,

procedures, and instructions.

Contrary to the above, prior to October 19, 2021, the licensee failed to ensure that the

ambient pressure sensing line in question was adequately designed to assure that applicable

regulatory requirements and the design bases are correctly translated into specifications,

drawings, procedures, and instructions to ensure that the installed equipment was protected

from inclement weather within the design bases. Specifically, the licensee failed to ensure

that the sensing line was protected against water intrusion and retention during periods of

severe inclement weather. This failure resulted in a condition prohibited by technical

specifications and an associated licensee event report because the time these systems were

inoperable exceeded the technical specification allowed outage time.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with

Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On June 16, 2022, the inspectors presented the radiation safety inspection results to Mr.

J. Ferrick, Site Vice President, and other members of the licensee staff.

On June 23, 2022, the inspectors presented the inservice inspection results to

Mr. J. Ferrick, Site Vice President and other members of the licensee staff.

On June 24, 2022, the inspectors presented the radiation safety inspection results to Mr.

J. Ferrick, Site Vice President, and other members of the licensee staff.

On July 19, 2022, the inspectors presented the integrated inspection results to

Mr. M. Lewis, General Manager of Plant Operations, and other members of the licensee

staff.

35

DOCUMENTS REVIEWED

Inspection Type Designation Description or Title Revision or

Procedure Date

71111.01 Procedures EN-FAP-EP-010 Severe Weather Response 9

71111.01 Procedures OP-901-521 Severe Weather and Flooding 338

71111.04 Miscellaneous SD-SI Safety Injection 19

71111.04 Procedures OP-009-003 Emergency Feedwater 312

71111.04 Procedures OP-009-008 Safety Injection System 47

71111.05 Fire Plans RAB 18-001 Component Cooling Water Heat Exchanger A 9

71111.05 Fire Plans RAB 19-001 Component Cooling Water Pump A 8

71111.05 Procedures EN-DC-161 Control of Combustibles 24

71111.07A Miscellaneous W3-DBD-004 Component Cooling Water Auxiliary Component Cooling 306

Water

71111.07A Work Orders 52944799

71111.08P Corrective Action Condition Reports CR-WF3-2022-02400, CR-WF3-2022-02459,

Documents CR-WF3-2022-02468, CR-WF3-2022-02472,

CR-WF3-2022-02644, CR-WF3-2022-02658,

CR-WF3-2022-02665, CR-WF3-2022-02682,

CR-WF3-2022-01929, CR-WF3-2022-01949,

CR-WF3-2022-01977, CR-WF3-2022-01978,

CR-WF3-2022-01979, CR-WF3-2022-01993,

CR-WF3-2022-02011, CR-WF3-2022-02012,

CR-WF3-2022-02013, CR-WF3-2022-02014,

CR-WF3-2022-02015, CR-WF3-2022-02016,

CR-WF3-2022-02017, CR-WF3-2022-02030,

CR-WF3-2022-02057, CR-WF3-2022-02755,

CR-WF3-2022-02768, CR-WF3-2022-02823,

CR-WF3-2022-02444, CR-WF3-2022-02633,

CR-WF3-2022-02801

71111.08P Drawings E-2803, IC-1130 Safety Injection, Dravo Corporation, Pipe Fabrication 7

Division

71111.08P Drawings E-3029LW3CC43 Essential Cooling Water, Dravo Corporation, Pipe 6

Fabrication Department

71111.08P Drawings E-3029LW3CC51 Essential Cooling Water, Dravo Corporation, Pipe 6

Fabrication Division

36

Inspection Type Designation Description or Title Revision or

Procedure Date

71111.08P Engineering DECP REPLACE SI-512A WITH A SWING CHECK VALVE 0

Changes 0000083354

71111.08P Engineering EC 0000081552 Disposition of Active Leak Indications Found on Reactor 000

Changes

71111.08P Engineering EC 000073452 Steam Generator Feedring Modification (Child SG1 - 0

Changes Feedring)

71111.08P Engineering EC 000073453 Steam Generator Feedring Modification (Child SG2 - 0

Changes Feedring)

71111.08P Engineering EC-0000083354 Replace SI-512A with a Swing Check Valve 0

Changes

71111.08P Miscellaneous CEP-PT-001 ASME Section XI Pressure Test (PT) Program, Entergy 311

Nuclear Engineering Programs

71111.08P Miscellaneous Code Case N- Alternative Examination Requirements for PWR Reactor 03/03/2016

729-6 Vessel Upper Heads with Nozzles having Pressure-

Retaining Partial-Penetration Welds,Section XI, Division 1

71111.08P Miscellaneous EN-DC-319 Boric Acid Corrosion Control Program (BACCP) 12

71111.08P Miscellaneous EPID L-2018- WATERFORD STEAM ELECTRIC STATION, UNIT 3- 10/18/2018

LLR-0025 PROPOSED ALTERNATIVE TO ASME CODE, SECTION

XI, REGARDING CHARGING PIPE VISUAL INSPECTION

(EPID L-2018-LLR-0025)

71111.08P Miscellaneous Purchase Order: Certified Material Test Report, Welding Rods, ER308/308L, 06/05/2012

10323632 GTAW, 3/32 inch diameter, Austenitic Steel Rod.

71111.08P Miscellaneous Purchase Order: Certified Material Test Report - Welding Rod, ER308/308L, 10/17/2017

10323632 GTAW, 1/8 inch diameter, Austenitic Steel

71111.08P Miscellaneous SEP-BAC-WF3- Waterford 3 Boric Acid Corrosion Control Program (BACC) 003

001 Program Section

71111.08P Miscellaneous SEP-CISI-104 Program Section for ASME Section XI, Division 1 WF3 5

Containment Inservice Inspection Program

71111.08P Miscellaneous SEP-ISI-104 Program Section for ASME Section XI, Division 1 WF3 11

Inservice Inspection Program

71111.08P Miscellaneous SEP-PT-WF3-001 Waterford 3 Inservice Inspection Pressure Testing (PT) 000

Program Section

71111.08P Miscellaneous W3F1-2008-0060 Request for Alternative W3-\Sl-006, Proposed Alternative to 09/18/2008

Extend the Second 10-Year lnservice Inspection Interval for

37

Inspection Type Designation Description or Title Revision or

Procedure Date

Reactor Vessel Internal Weld Examinations Waterford

Steam Electric Station, Unit 3, Docket No. 50-382, License

No. NPF-38

71111.08P Miscellaneous W3F1-2009-0006 RAJ Response to Request for Alternative W3-ISl-006 To 03/19/2009

Extend the Second 10 Year AMSE Code ISI and License

Amendment Request, NPF-38-280 To Support Request for

Alternative W3-ISl-006, Waterford Steam Electric Station,

Unit 3 (Waterford 3), Docket No. 50-382, License No.

NPF-38

71111.08P Miscellaneous W3F1-2010-0002 Request for NRC Alternative to ASME IWE-5521 Regarding 02/09/2010

Post Repair Testing of Waterford 3s Steel Containment

Vessel Opening Waterford Steam, Electric Station, Unit 3,

Docket No. 50-382, License No. NPF-38

71111.08P Miscellaneous W3F1-2011-0041 Request for Alternative to ASME IWE-5221 Regarding Post 07/27/2011

Repair Testing of Waterford 3s Steel Containment Vessel

Opening Waterford Steam Electric Station, Unit 3, Docket

No. 50-382

71111.08P Miscellaneous W3F1-2013-0044 Waterford 3 Request for Alternative W3-ISI-023, ASME 09/26/2013

Code Case N-770-1 Successive Examinations, Waterford

Steam Electric Station, Unit 3/ Docket No. 50-382, License

No. NPF-38

71111.08P Miscellaneous W3F1-2018-0008 Request for NRC Alternative to ASME IWA-5211 Regarding 02/20/2018

Charging Pipe Visual Inspection, Relief Request W3-ISI-030,

Waterford Steam Electric Station, Unit 3 (Waterford 3),

Docket No. 50-382, License No. NPF-38

71111.08P Miscellaneous W3F1-2018-0067 Response to NRC Request for Additional Information 11/19/2018

Regarding Request for Alternative to ASME Code Case

N-770-2, Successive Examinations, Relief Request

W3-ISI-031

71111.08P Miscellaneous W3F1-2019-0017 Closure of Commitment Associated with Inservice Inspection 02/14/2019

Program Alternative WF3-RR-19-1 for Application of

Dissimilar Metal Weld Full Structural Weld Overlay -

Reactor Coolant System Cold Leg Drain Nozzles

71111.08P Miscellaneous Work Order: Single Weld Datasheet (Weld Traveler) for Valve SI-512A 04/20/2022

38

Inspection Type Designation Description or Title Revision or

Procedure Date

528322-01, Map (ISI-V2507), Field Weld FW-7, EC 83354

No. WF3-

528322-01-01

71111.08P Miscellaneous Work Order: Single Weld Datasheet (Weld Traveler) for Valve SI-512A 04/20/2022

528322-01, Map (ISI-V2507), Field Weld FW-8

No. WF3-

5273220-01-01

71111.08P NDE Reports BOP-VE-19-002 Nozzle to Safe-End Circumferential Weld - Weld Overlay 02/07/2019

71111.08P NDE Reports BOP-VE-19-003 Nozzle to Safe-End Circumferential Weld - Weld Overlay 02/07/2019

71111.08P NDE Reports BOP-VE-19-004 Safe End to 2" Pipe Weld - Weld Overlay 02/07/2019

71111.08P NDE Reports BOP-VE-19-005 Safe-End to 2" Pipe Weld - Weld Overlay 02/07/2019

71111.08P NDE Reports BOP-VT-19-005 Reactor Vessel Closure Head Control Element Drive 02/02/2019

Mechanism Nozzles

71111.08P NDE Reports BOP-VT-21-004 Socket Weld CCW Line 3CC1 1/2-46 09/14/2021

71111.08P NDE Reports ISI-VT-17-132 Reactor Vessel Closure Head Control Element Drive 05/15/2017

Mechanism Nozzles 1-87

71111.08P Procedures CEP-BAC-001 Boric Acid Corrosion Control (BACC) Program Plan 2

71111.08P Procedures CEP-NDE-0100 Administration and Control of NDE, Entergy Nuclear 16

Engineering Programs

71111.08P Procedures CEP-NDE-0404 Manual Ultrasonic Examination of Ferritic Piping Welds 9

(ASME XI)

71111.08P Procedures CEP-NDE-0423 Manual Ultrasonic Examination of Austenitic Piping Welds 9

(ASME XI)

71111.08P Procedures CEP-NDE-0493 Manual Ultrasonic Examination of Reactor Coolant Pump 4

Flywheel

71111.08P Procedures CEP-NDE-0641 Liquid Penetrant Examination (PT) for ASME Section XI 9

71111.08P Procedures CEP-NDE-0901 VT-1 Examination, Entergy Nuclear Engineering Programs 6

71111.08P Procedures CEP-NDE-0902 VT-2 Examination, Entergy Nuclear Engineering Programs 10

71111.08P Procedures CEP-NDE-0903 VT-3 Examination, Entergy Nuclear Engineering Programs 6

71111.08P Procedures CEP-NDE-0955 Visual Examination (VE) of Bare-Metal Surfaces, Entergy 308

Nuclear Engineering Programs

71111.08P Procedures CEP-WP-002, Welding Procedure, Specification WPS-SS-8/8-B, Manual 0

Gas Tungsten Arc Welding (GTAW) of P-No. 8 stainless

steels

39

Inspection Type Designation Description or Title Revision or

Procedure Date

71111.08P Procedures CEP-WP-GWS-1 General Welding Standard, ASME/ANSI 6

71111.08P Procedures CEP-WP-IGP-1 Internal Gas Purging 1

71111.08P Procedures EPRI-WOL-PA-1 Procedure for Manual Phased Array Ultrasonic Examination 4

of Weld Overlaid Similar and Dissimilar Metal Welds

71111.08P Procedures EPRI-WOL-PA-1, Procedure for Manual Phased Array Ultrasonic Examination 09/12/2014

Table 1 of Weld Overlaid Similar and Dissimilar Metal Welds

71111.08P Procedures EPRI-WOL-PA-1, Procedure for Manual Phased Array Ultrasonic Examination 09/12/2014

Table 2 of Weld Overlaid Similar and Dissimilar Metal Welds

71111.08P Procedures LMT-07-PAUT- Performance of Phased Array Instrument Screen Height and 1

005 Amplitude Control Linearity Checks

71111.08P Procedures LMT-08-EPRI- Procedure for Manual Phased Array Ultrasonic Examination 0

WOL-1 of Weld Overlaid Similar and Dissimilar Metal Welds

71111.08P Procedures LMT-08-PAUT- 5 Performance of Phased Array Instrument Screen Height and 0

Amplitude Control Linearity Checks

71111.08P Procedures LMT-21-PAUT- Encoded Phased Array Ultrasonic Examination of Small 0

029 Bore Austenitic and Ferritic Socket Welds (= 2.0 OD NPS)

71111.08P Procedures PQR 107 Procedure Qualification Record - Manual Gas Tungsten & 1

Shielded Metal Arc Welding

71111.08P Procedures PQR-170 Procedure Qualification Record - Manual Gas Tungsten & 1

Shielded Metal Arc Welding

71111.08P Self-Assessments LO-HQNLO- 2022 Welding Program Assessment 02/17/2022

2021-19

71111.08P Self-Assessments LO-WLO-2021- Pre-NRC RF24 ISI Activities Self-Assessment Report 10/14/2021

0033 CA-2

71111.08P Work Orders 527322 EC 83354 - REPLACE VALVE SI-512A 04/08/2022

71111.11Q Procedures EN-TQ-100 Operations Training Program Description 1

71111.11Q Procedures OP-010-003 Plant Startup 360

71111.11Q Procedures OP-010-003 Power Operations 341

71111.11Q Procedures OP-901-220 Loss of Condenser Vacuum 305

71111.11Q Procedures OP-901-221 Secondary System Transient 11

71111.11Q Procedures OP-902-000 Standard Post Trip Actions 17

71111.13 Corrective Action CR-WF3-YYYY- 2022-04969

Documents NNNN

Resulting from

40

Inspection Type Designation Description or Title Revision or

Procedure Date

Inspection

71111.13 Procedures OP-010-003 Plant Startup 361

71111.13 Procedures OP-010-004 Power Operations 341

71111.15 Corrective Action CR-WF3-YYYY- 2022-03704, 2022-04112, 2022-04542, 2022-04759

Documents NNNN

71111.15 Engineering EC 93200 Input for Emergency Feedwater Pump AB Differential 06/11/2022

Changes Pressure

71111.15 Engineering EC-92951 Availability of Shutdown Cooling in Modes 5 & 6 05/11/2022

Changes

71111.18 Corrective Action CR-WF3-YYYY- 2022-3704, 2022-4283, 2022-4299, 2022-4314

Documents NNNN

71111.18 Engineering EC 91881 Substitute Core Protection Calculator D RTD Input 03/02/2022

Changes

71111.18 Engineering EC 92952 Temporary Plug for Thermowell 05/17/2022

Changes

71111.18 Engineering EC 93024 Extend EC-91881 until Refuel 25 06/16/2022

Changes

71111.18 Engineering EC 93139 ACCEMTR3B-6 Motor Comparison and Evaluation 06/05/2022

Changes

71111.18 Work Orders 580731

71111.19 Procedures OP-903-033 Cold Shutdown IST Valve Tests 060

71111.19 Procedures OP-903-050 Component Cooling Water and Auxiliary Component Cooling 44

Water Pump and Valve Operability Test

71111.19 Procedures OP-903-092 Main Steam Isolation Actuation Signal Test 302

71111.19 Procedures OP-903-095 ESFAS Subgroup Relay Test - Shutdown 016

71111.19 Work Orders 581904, 581916, 580585

71111.20 Procedures EN-OP-119 Protected Equipment Postings 16

71111.20 Procedures EN-OU-108 Shutdown Safety Management Program (SSMP) 11

71111.20 Procedures OP-010-005 Plant Shutdown 341

71111.20 Procedures OP-010-006 Outage Operations 340

71111.20 Work Orders 52945451, 52962777, 572188

71111.22 Corrective Action CR-WF3-YYYY- 2022-03491, 2022-03799, 2022-1852

Documents NNNN

41

Inspection Type Designation Description or Title Revision or

Procedure Date

71111.22 Procedures OP-903-033 Cold Shutdown IST Valve Tests 59

71111.22 Procedures OP-903-092 Main Steam Isolation Actuation Signal Test 302

71111.22 Procedures OP-903-116 Train B Integrated Emergency Diesel Generator/Engineering 56

Safety Features Test

71111.22 Procedures SEP-APJ-005 Waterford 3 Primary Containment Leakage Rate Testing 10

71111.22 Procedures STA-001-004 Local Leak Rate Test (LLRT) 319

71111.22 Procedures STA-001-006 Leak Rate Testing 305

71111.22 Work Orders 52952716, 52951975

71124.01 Corrective Action CR-WF3-YYYY- 2021-00608, 2021-00636, 2021-01493, 2021-03064,

Documents XXXX 2021-04681, 2021-04685, 2021-04952, 2021-05400,

2021-06456

71124.01 Corrective Action CR-WF3-YYYY- 2022-00556, 2022-01496, 2022-01953, 2022-02217,

Documents XXXX 2022-02542

71124.01 Corrective Action CR-WF3-YYYY- 2022-03170, 2022-03171, 2022-03174, 2022-03226,

Documents XXXX 2022-03290, 2022-03293, 2022-03295, 2022-03296,

Resulting from 2022-03297, 2022-03298, 2022-04917, 2022-04918,

Inspection 2022-04920, 2022-04921, 2022-04922, 2022-04923,

2022-04924

71124.01 Miscellaneous Nuclear Daily Report 04/12/2022

71124.01 Miscellaneous Hot Spot Tracking Log 04/13/2022

71124.01 Miscellaneous Attachment 5 to LHRA/VHRA Key Log 04/12/2022

EN-RP-101

71124.01 Miscellaneous HP-SM-076 +46 Fuel Handling Building Spent Fuel Pool Inventory 03/24/2022

71124.01 Procedures EN-RP-100 Radiation Worker Expectations 12

71124.01 Procedures EN-RP-101 Access Control for Radiologically Controlled Areas 15

71124.01 Procedures EN-RP-102 Radiological Control 7

71124.01 Procedures EN-RP-104 Personnel Contamination Events 11

71124.01 Procedures EN-RP-105 Radiological Work Permits 19

71124.01 Procedures EN-RP-106 Radiological Survey Documentation 7

71124.01 Procedures EN-RP-110 ALARA Program 14

71124.01 Procedures EN-RP-121 Radioactive Material Control 17

71124.01 Procedures EN-RP-123 Radiological Controls for Highly Radioactive Objects 1

71124.01 Procedures EN-RP-143 Source Control 14

42

Inspection Type Designation Description or Title Revision or

Procedure Date

71124.01 Radiation WF3-2203-00161 +15 OA - Low Level Radwaste Storage Building 03/22/2022

Surveys

71124.01 Radiation WF3-2204-00087 -4 Reactor Containment Building 04/03/2022

Surveys

71124.01 Radiation WF3-2204-00206 Refuel 24 RP Bi-Weekly Survey +21 Reactor Containment 04/06/2022

Surveys Building

71124.01 Radiation WF3-2204-00209 Bi-Weekly -4 Reactor Containment Building 04/06/2022

Surveys

71124.01 Radiation WF3-2204-00234 -11 Reactor Containment Building Overhead Scaffold 04/07/2022

Surveys Support

71124.01 Radiation WF3-2204-00367 -4 Reactor Containment Building 04/11/2022

Surveys

71124.01 Radiation WF3-2204-00385 +21 Reactor Containment Building Pressurizer 04/11/2022

Surveys

71124.01 Radiation Work RWP 2021-0002 Operations Personnel to Perform Various Activities in 1

Permits (RWPs) Radiologically Controlled Areas

71124.01 Radiation Work RWP 2021-0054 Safety Injection Tank Sampling, Personnel/Escape Interlock 1

Permits (RWPs) Door Tests, Minor Maintenance, Inspections and Valve-Line

Ups, Radiation Protection Job Coverage into posted Locked

High Radiation Areas

71124.01 Radiation Work RWP 2022-0610 Erect/Dismantle Scaffolding in the Reactor Containment 0

Permits (RWPs) Building

71124.01 Radiation Work RWP 2022-0627 Maintenance Valve Work Inside the Reactor Containment 0

Permits (RWPs) Building

71124.01 Radiation Work RWP 2022-0635 Radiography including Radiation Protection Boundary 0

Permits (RWPs) Guards

71124.01 Radiation Work RWP 2022-0702 Reactor Disassembly Activities 0

Permits (RWPs)

71124.01 Radiation Work RWP 2022-0708 Remove and Replace ICIs 0

Permits (RWPs)

71124.01 Radiation Work RWP 2022-0805 Tours and Inspections Outside the Reactor Containment 0

Permits (RWPs) Building

71124.01 Self-Assessments LO-WLO-2021- Radiological Hazard Assessment and Exposure Controls (IP 11/29/2021

00019 71124.01)

43

Inspection Type Designation Description or Title Revision or

Procedure Date

71124.03 Corrective Action CR-WF3-YYYY- 2021-00537, 2021-00657, 2021-02666, 2021-04975,

Documents XXXX 2021-05769, 2021-05898, 2021-06399, 2021-07131

71124.03 Corrective Action CR-WF3-YYYY- 2022-00421

Documents XXXX

71124.03 Miscellaneous Inspection and Maintenance of Respiratory Protection 03/10/2021

Equipment - March 2021

71124.03 Miscellaneous Inspection and Maintenance of Respiratory Protection 01/27/2022

Equipment - January 2022

71124.03 Miscellaneous Inspection and Maintenance of Respiratory Protection 12/30/2021

Equipment - December 2021

71124.03 Miscellaneous Watford 3 Personnel- FireHawk Respirator Qualifications 03/23/2022

71124.03 Miscellaneous EN-RP-502, Annual Respiratory Protection Equipment Inventory & 12/12/2021

Attachment 9.5 Inspection - 2021

71124.03 Miscellaneous EN-RP-503, Total Effective Dose Equivalent/ALARA Evaluation for RWP 12/31/2021

Attachment 9.11 2022-0615

71124.03 Miscellaneous EN-RP-503, Total Effective Dose Equivalent/ALARA Evaluation for RWP 12/31/2021

Attachment 9.12 2022-0627

71124.03 Miscellaneous EN-RP-503, Annual Respiratory Protection Equipment Inventory & 12/12/2021

Attachment 9.5 Inspection - Security 2021

71124.03 Procedures EN-RP-131 Air Sampling 17

71124.03 Procedures EN-RP-203 Dose Assessment 10

71124.03 Procedures EN-RP-501 Respiratory Protection Program 7

71124.03 Procedures EN-RP-502 Inspection and Maintenance of Respiratory Protection 10

Equipment

71124.03 Procedures EN-RP-502-01 FireHawk M7 SCBA 3

71124.03 Procedures EN-RP-502-03 AirHawk II SCBA 0

71124.03 Procedures EN-RP-503 Selection, Issue and Use of Respiratory Protection 8

Equipment

71124.03 Procedures EN-RP-504 Breathing Air 4

71124.03 Procedures EN-RP-505 PortaCount Respirator Fit Testing 9

71124.03 Procedures HP-002-603 Inspection and Use of Control Room EBA Filtration Panel 12

71124.03 Procedures MM-003-045 Control Room Air Conditioning System Surveillance 316

71124.03 Procedures MM-003-046 Controlled Ventilation Area System Surveillance 311

71124.03 Procedures MM-007-034 RAB Normal Ventilation System Exhaust Filter Test 4

44

Inspection Type Designation Description or Title Revision or

Procedure Date

71124.03 Radiation WF3-2204-00447 +46 foot elevation- Reactor Containment Building - survey 04/13/2022

Surveys performed for welders to grind out and remove RCSV-3184,

RCSV-1017, RCSV-1014, & RCSV-1015

71124.03 Radiation WF3-2204-00468 +46 foot elevation- Reactor Containment Building- survey of 04/13/2022

Surveys pipe tent on south west wall of cavity

71124.03 Radiation WF3-2204-00481 +46 foot elevation- Reactor Containment Building - survey 04/13/2022

Surveys performed to down post fire protection tent

71124.03 Radiation WF3-2204-00489 +46 foot elevation - Reactor Containment Building - survey 04/13/2022

Surveys performed for completion of grinding before weld of new

valves for RCS line takes place

71124.03 Radiation WF3-AS-041322- Air sample for RWP 2022-0627 during the removal & grind 04/13/2022

Surveys 0103 out valve: RCISV 1014, RCISV 1015, RCISV 1017

71124.03 Radiation WF3-AS-041322- Air sample for RWP 2022-0627 during grind out valves: RC- 04/13/2022

Surveys 0105 1014, RC-1015, RC-1017, RC-3184

71124.03 Radiation WF3-AS-041322- Air sample for RWP 2022-0627 during removal/replace RC 04/13/2022

Surveys 0110 valves

71124.03 Radiation WF3-AS-041722- Pzr Room - cut out heaters 04/17/2022

Surveys 0238

71124.03 Radiation WF3-AS-041722- Lapel air sample data 04/17/2022

Surveys 0246

71124.03 Radiation WF3-AS-042222- Validation of A/S PZR Cut out heater 04/22/2022

Surveys 0581

71124.03 Radiation Work RWP 2022-0615 Refuel 24 - Remove/Replace Pressurizer Heaters 0, 1, 2, 3, 4,

Permits (RWPs) 5

71124.03 Radiation Work RWP 2022-0627 Refuel 24 - Maintenance Valve Work inside the Reactor 0

Permits (RWPs) Containment Building

71124.04 Calculations Internal Dose Assessment Models for 2 worker uptakes 04/27/2022

71124.04 Calculations Internal Dose Assessment Model for 2 worker uptakes 04/21/2022

71124.04 Miscellaneous Whole Body Counts for 8 workers 04/19/2022

71124.04 Miscellaneous Whole Body Counts for 5 workers 04/20/2022

71124.04 Miscellaneous Whole Body Counts for 4 workers 04/21/2022

71124.04 Miscellaneous Whole Body Counts for 3 workers 04/22/2022

71124.04 Miscellaneous Whole Body Counts for 1 worker 04/23/2022

71124.04 Miscellaneous Whole Body Counts for 2 workers 04/24/2022

45

Inspection Type Designation Description or Title Revision or

Procedure Date

71124.04 Miscellaneous Apex-InVivo Nuclide Library Report: STDNPPNA.NLB -

Basic NaI NPP and PeakSearch.NLB (STDNPPGE.NLB) -

Basic GE NPP

71124.04 Miscellaneous Whole Body Counts for 8 workers 04/18/2022

71124.04 Miscellaneous LIMS L95908 Teledyne Brown Engineering - Environmental Services: 05/05/2022

Report of Analysis

71124.06 Calculations EN-RW-104, 10 CFR Part 61 Waste Stream Screening and Evaluation 03/22/2021

Attachment 9.1

71124.06 Corrective Action Condition Report 2019-07276, 2019-08771, 2020-00424, 2020-01397,

Documents (CR-WF3-XXXX- 2020-01459, 2020-01747, 2020-01806, 2020-02513,

XXXXX) 2020-03066, 2020-03450, 2020-05459, 2020-05891,

2020-06860, 2021-01378, 2021-02435, 2021-03399,

2021-03399, 2021-04183, 2021-04525, 2021-05562,

2021-05563, 2021-06329, 2021-06506, 2022-00374,

2022-01581, 2022-02066, 2022-02145

71124.06 Miscellaneous Annual Dose Summary for 2019, 2020, and 2021 N/A

71124.06 Miscellaneous Annual Release Summary for 2019, 2020, and 2021 N/A

71124.06 Procedures CE-002-016 Maintaining Gaseous Waste Management System 310

71124.06 Procedures CE-002-018 Monitoring Liquid Waste Management 007

71124.06 Procedures CE-003-300 Preparation of Liquid Samples for Radiological Chemical 013

Analysis

71124.06 Procedures CE-003-509 Routine Filter Replacement and Grab Sampling on 309

Particulate Iodine Gas Monitors and Wide Range Gas

Monitors

71124.06 Procedures CE-003-510 Technical Specification Action Statement Compliance 014

71124.06 Procedures CE-003-512 Liquid Radioactive Waste Release Permit (Manual) 002

71124.06 Procedures CE-003-513 Gaseous Radioactive Waste Release Permit (Manual) 304

71124.06 Procedures CE-003-514 Liquid Radioactive Waste Release Permit 304

71124.06 Procedures CE-003-515 Gaseous Radioactive Waste Release Permit 305

71124.06 Procedures CE-003-700 General Grab Sampling Techniques 319

71124.06 Procedures UNT-005-014 Offsite Dose Calculation Manual 308

71124.06 Self-Assessments QA-2/6-2021-W3- Quality Assurance Audit Report: Combined Chemistry, 10/05/2021

1 Effluents, and Environmental Monitoring

71124.07 Corrective Action Condition Report 2019-07315, 2019-07322, 2019-08536, 2019-08995,

46

Inspection Type Designation Description or Title Revision or

Procedure Date

Documents (CR-WF3-XXXX- 2020-00249, 2020-01272, 2020-02019, 2020-03175,

XXXXX) 2020-04335, 2020-06097, 2020-06639, 2020-07123,

2021-00851, 2021-00958, 2021-02095, 2021-03665,

2021-03668, 2021-04115, 2021-04534, 2022-00086,

2022-00306, 2022-03045, 2022-04529

71124.07 Miscellaneous Energy Nuclear / Waterford-3 Station Groundwater 06/12/2019

Protection Plan

71124.07 Miscellaneous 2020 Land Use Census Data 10/12/2020

71124.07 Miscellaneous Annual Quality Assurance Status Report 03/16/2022

71124.07 Miscellaneous CR-WF3-2020- 10 CFR 50.75(g)(1) Leak/Spill Record - West Side of 10/24/2020

06097 Service Building Warehouse

71124.07 Miscellaneous CR-WF3-2021- 10 CFR 50.75(g)(1) Leak/Spill Record - Fire Protection Pit 07/08/2021

03668 17

71124.07 Miscellaneous W3F1-2020-0025 2019 Annual Radiological Environmental Operating Report 04/27/2020

71124.07 Miscellaneous W3F1-2020-0026 2019 Annual Radioactive Effluent Release Report 04/27/2020

71124.07 Miscellaneous W3F1-2021-0036 2020 Annual Radiological Environmental Operating Report 04/29/2021

71124.07 Miscellaneous W3F1-2021-0037 2020 Annual Radioactive Effluent Release Report 04/29/2021

71124.07 Miscellaneous W3F1-2022-0027 2021 Annual Radioactive Effluent Release Report 04/26/2022

71124.07 Miscellaneous W3F1-2022-0028 2021 Annual Radiological Environmental Operating Report 04/28/2022

71124.07 Procedures CE-003-522 Meteorological Data Collection and Processing 7

71124.07 Procedures CE-003-523 Meteorological Monitoring Program 2

71124.07 Procedures EN-CY-108 Monitoring of Nonradioactive Systems 7

71124.07 Procedures EN-CY-111 Radiological Groundwater Protection Program 12

71124.07 Procedures EN-CY-127 Land Use Census 2

71124.07 Procedures EN-CY-130 Radiological Environmental Monitoring Program 0

71124.07 Procedures EN-CY-132 Annual Radiological Environmental Operating Report 1

71124.07 Procedures EN-RP-113 Response to Contaminated Spills/Leaks 11

71124.07 Procedures OP-903-001 Technical Specification Surveillance Logs 98

71124.07 Procedures UNT-005-014 Offsite Dose Calculation Manual 309

71124.07 Procedures UNT-005-014 Offsite Dose Calculation Manual 308

71124.07 Self-Assessments LO-HQNLO- Groundwater Protection Program Self-Assessment 10/27/2021

2021-00024

71124.07 Self-Assessments LO-WLO-2021- Pre-NRC Assessment of Radiation Safety Inspection Criteria 11/03/2021

47

Inspection Type Designation Description or Title Revision or

Procedure Date

00018

71124.07 Work Orders WF3-398323-01 EM MTWR0001-A, Primary Met Tower 09292015

71124.07 Work Orders WF3-52977514- Calibrate Primary Met Tower IAW MI-003-395 01/27/2022

01/02

71151 Procedures EN-LI-114 Regulatory Performance Indicator Process 19

71152A Corrective Action CR-WF3-YYYY- 2021-02879

Documents NNNN

71152A Drawings G309 Phasing and Voltage Vector Diagram 4

71152A Engineering EC 41846 Isolated Phase Bus Transition 02/07/2013

Changes

71152A Work Orders 52910298, 563568, 563628, 563629, 563631

48