November 01, 2022
John Ferrick
Site Vice President
Entergy Operations, Inc.
17265 River Road
Killona, LA 70057
SUBJECT: WATERFORD STEAM ELECTRIC STATION, UNIT 3 INTEGRATED INSPECTION
REPORT 05000382/2022003
Dear John Ferrick:
On September 30, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an
inspection at Waterford Steam Electric Station, Unit 3. On October 18, 2022, the NRC
inspectors discussed the results of this inspection with you and other members of your staff.
The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection
and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document
Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public
Inspections, Exemptions, Requests for Withholding.
Sincerely,
John L. Dixon, Jr., Chief
Projects Branch D
Division of Operating Reactor Safety
Docket No. 05000382
License No. NPF-38
Enclosure:
As stated
cc w/ encl: Distribution via LISTSERV
Signed by Dixon, John
on 11/01/22
SUNSI Review
ASanchez
Non-Sensitive
Sensitive
Publicly Available
Non-Publicly Available
OFFICE
SRI:DORS/D
RI:DORS/D
SPE:DORS/D
BC:DORS/D
NAME
APatz
AChilds
ASanchez
JDixon
DATE
10/27/2022
11/01/2022
10/31/2022
11/01/2022
Enclosure
U.S. NUCLEAR REGULATORY COMMISSION
Inspection Report
Docket Number:
05000382
License Number:
Report Number:
Enterprise Identifier:
I-2022-003-0007
Licensee:
Entergy Operations, Inc.
Facility:
Waterford Steam Electric Station, Unit 3
Location:
Killona, LA 70057
Inspection Dates:
July 1, 2022, to September 30, 2022
Inspectors:
D. Childs, Resident Inspector
T. Farina, Senior Operations Engineer
A. Patz, Senior Resident Inspector
Approved By:
John L. Dixon, Jr., Chief
Projects Branch D
Division of Operating Reactor Safety
2
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees
performance by conducting an integrated inspection at Waterford Steam Electric Station, Unit 3,
in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the
NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer
to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
3
PLANT STATUS
Unit 3 began the inspection period at rated thermal power and remained at or near rated
thermal power for the inspection period.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in
effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with
their attached revision histories are located on the public website at http://www.nrc.gov/reading-
rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared
complete when the IP requirements most appropriate to the inspection activity were met
consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection
Program - Operations Phase. The inspectors performed activities described in IMC 2515,
Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of
IPs. The inspectors reviewed selected procedures and records, observed activities, and
interviewed personnel to assess licensee performance and compliance with Commission rules
and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
71111.01 - Adverse Weather Protection
Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)
(1)
The inspectors evaluated the adequacy of the overall preparations to protect
risk-significant systems from seasonal heavy rains and severe weather due to
potential for hurricane development on August 31, 2022.
71111.04 - Equipment Alignment
Partial Walkdown Sample (IP Section 03.01) (2 Samples)
The inspectors evaluated system configurations during partial walkdowns of the following
systems/trains:
(1)
emergency feedwater system trains A, B, and AB during and following maintenance
on emergency feedwater pump B on July 28, 2022
(2)
emergency diesel generator system train B while train A was inoperable during
surveillance testing on September 6, 2022
71111.05 - Fire Protection
Fire Area Walkdown and Inspection Sample (IP Section 03.01) (6 Samples)
The inspectors evaluated the implementation of the fire protection program by conducting a
walkdown and performing a review to verify program compliance, equipment functionality,
material condition, and operational readiness of the following fire areas:
4
(1)
fire area RAB 2-002, elevation +46.00' reactor auxiliary building main steam isolation
valve passage and fire area RAB 3A-003, elevation +21.00' reactor auxiliary building
vestibule on July 6, 2022
(2)
fire area RAB 32-001, elevation -35.00' auxiliary component cooling water room and
pipe penetration area on July 18, 2022
(3)
fire area RAB 8B-001, elevation +21.00' reactor auxiliary building switchgear room B
on August 12, 2022
(4)
fire area RAB 17-001, elevation +21.00' reactor auxiliary building component cooling
water pump B room, and fire area RAB 21-001, elevation +21.00' reactor auxiliary
building component cooling water heat exchanger B room, on September 1, 2022
(5)
fire area RAB 8A-001, elevation +21.00' reactor auxiliary building switchgear room A
on September 2, 2022
(6)
fire area RAB 25-001, elevation +21.00' reactor auxiliary building decon area on
September 27, 2022
71111.06 - Flood Protection Measures
Inspection Activities - Internal Flooding (IP Section 03.01) (1 Sample)
The inspectors evaluated internal flooding mitigation protections in the:
(1)
elevation +21.00' component cooling water pump and heat exchanger areas on
September 1, 2022
71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance
Requalification Examination Results (IP Section 03.03) (1 Sample)
(1)
The inspectors reviewed and evaluated the licensed operator examination failure
rates for the requalification annual operating exams administered on August 30,
2022.
71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance
Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)
(1)
The inspectors observed and evaluated licensed operator simulator training on
September 20, 2022.
71111.12 - Maintenance Effectiveness
Maintenance Effectiveness (IP Section 03.01) (2 Samples)
The inspectors evaluated the effectiveness of maintenance to ensure the following
structures, systems, and components (SSCs) remain capable of performing their intended
function:
(1)
engineered safety features actuation system train B following auxiliary component
cooling water pump B failure to start during testing on September 21, 2022
(2)
control room air handling system train B following failure of an electric relay on
September 30, 2022
5
71111.13 - Maintenance Risk Assessments and Emergent Work Control
Risk Assessment and Management Sample (IP Section 03.01) (3 Samples)
The inspectors evaluated the accuracy and completeness of risk assessments for the
following planned and emergent work activities to ensure configuration changes and
appropriate work controls were addressed:
(1)
elevated green risk for motor-driven emergency feedwater pump B outage during the
week of July 25, 2022
(2)
planned yellow risk due to low-pressure safety injection and containment spray
train B outages during the week of August 8, 2022
(3)
elevated green risk due to unexpected plant protection system power supply failure
during the week of September 6, 2022
71111.15 - Operability Determinations and Functionality Assessments
Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)
The inspectors evaluated the licensee's justifications and actions associated with the
following operability determinations and functionality assessments:
(1)
component cooling water system following identification of inleakage on July 28, 2022
(2)
reactor trip circuit breakers following surveillance failure on August 5, 2022
(3)
feedwater ultrasonic flow meter following erratic indication and repair difficulties on
September 8, 2022
(4)
containment fan cooler train B following loss of motor control center 317B on
September 22, 2022
(5)
offsite power following automatic isolation of west switchyard bus on
September 29, 2022
71111.19 - Post-Maintenance Testing
Post-Maintenance Test Sample (IP Section 03.01) (6 Samples)
The inspectors evaluated the following post-maintenance testing activities to verify system
operability and/or functionality:
(1)
emergency feedwater pump A after planned maintenance on the motor on
July 6, 2022
(2)
emergency feedwater pump B after planned maintenance on July 28, 2022
(3)
low-pressure safety injection train A header to reactor coolant loop 2A flow control
valve SI-139A following planned maintenance on August 9, 2022
(4)
containment spray train A header isolation valve CS-125A following planned solenoid
replacements on August 11, 2022
(5)
component cooling water pump B following corrective maintenance on
August 18, 2022
(6)
plant stack wide range radiation monitors following identification of incorrect reference
values on September 9, 2022
6
71111.22 - Surveillance Testing
The inspectors evaluated the following surveillance testing activities to verify system operability
and/or functionality:
Surveillance Tests (other) (IP Section 03.01) (2 Samples)
(1)
dry cooling tower A diesel driven sump pump surveillance testing on August 31, 2022
(2)
containment spray pump surveillance testing on September 29, 2022
Inservice Testing (IP Section 03.01) (1 Sample)
(1)
steam generator 2 atmospheric dump valve inservice testing on July 21, 2022
71114.06 - Drill Evaluation
Drill/Training Evolution Observation (IP Section 03.02) (1 Sample)
The inspectors evaluated:
(1)
a full site integrated drill for a simulated site area emergency on September 13, 2022
OTHER ACTIVITIES - BASELINE
71151 - Performance Indicator Verification
The inspectors verified licensee performance indicators submittals listed below:
MS08: Heat Removal Systems (IP Section 02.07) (1 Sample)
(1)
Unit 3 (July 1, 2021, through June 30, 2022)
MS09: Residual Heat Removal Systems (IP Section 02.08) (1 Sample)
(1)
Unit 3 (July 1, 2021, through June 30, 2022)
MS10: Cooling Water Support Systems (IP Section 02.09) (1 Sample)
(1)
Unit 3 (July 1, 2021, through June 30, 2022)
71152S - Semiannual Trend Problem Identification and Resolution
Semiannual Trend Review (Section 03.02) (1 Sample)
(1)
The inspectors reviewed the licensees corrective action program and maintenance
rule tracking program for potential adverse trends in radiation monitor equipment
performance and corrective actions that might be indicative of a more significant
safety issue.
7
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
On August 30, 2022, the inspectors presented the annual requalification exam
inspection results to Van Ford, Superintendent, Operations Training, and other members
of the licensee staff.
On October 18, 2022, the inspectors presented the integrated inspection results to
John Ferrick and other members of the licensee staff.
8
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Engineering
Evaluations
Flood Hazard Reevaluation Report
07/21/2015
Procedures
OP-901-521
Severe Weather and Flooding
340
Procedures
OP-009-002
360
Procedures
OP-009-003
Emergency Feedwater
312
Calculations
ECF91-010
Combustible Loading Calculation for Fire Area RAB 8
4
Corrective Action
Documents
CR-WF3-YYYY-
NNNN
2022-05705
Fire Plans
RAB 17-001
Component Cooling Water Heat Exchanger B Fire Plan
9
Fire Plans
RAB 2-002
Main Steam Isolation Valve Passage
7
Fire Plans
RAB 21-001
Component Cooling Water Pump B Fire Plan
9
Fire Plans
RAB 25-001
RAB +21 Decon Area
9
Fire Plans
RAB 32-001
Auxiliary Component Cooling Water Room & Pipe
Penetration Area
11
Fire Plans
Vestibule
4
Fire Plans
Switchgear Room A
13
Fire Plans
Reactor Auxiliary Building +21.00' elevation
14
Miscellaneous
TCP 22-110
Transient Combustible Permit for Fire Area RAB 8
04/11/2022
Miscellaneous
TCP 22-116
Transient Combustible Permit for Fire Zone RAB 8A
04/18/2022
Procedures
Control of Combustibles
24
Procedures
Control of Combustibles
25
Procedures
MM-006-106
Plant Door Maintenance
335
Work Orders
52969317
Calculations
MNQ3-5
Flooding Analysis Outside Containment
6
Miscellaneous
N/A
2022 Annual NRC Operating Test Results
08/29/2022
Procedures
Operations Training Program Description
3
Procedures
OP-902-000
Standard Post Trip Actions
17
Procedures
OP-902-003
Loss of Offsite Power / Loss of Forced Circulation
11
Corrective Action
Documents
CR-WF3-YYYY-
NNNN
2022-1562, 2022-3627, 2022-04666
Miscellaneous
SD-CC
Component Cooling Water
25
9
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Miscellaneous
SD-PPS
Plant Protection System
22
Miscellaneous
W3-DBD-38
Safety Related HVAC - Control Room
302
Procedures
EN-FAP-LI-001
Performance Improvement Review Group (PRG) Process
19
Procedures
Corrective Action Program
47
Procedures
Causal Evaluation Process
35
Procedures
OP-903-068
Emergency Diesel Generator and Subgroup Relay
Operability Verification
326
Corrective Action
Documents
CR-WF3-YYYY-
XXXXX
2022-06304
09/06/2022
Miscellaneous
Tagout : 2022-0106-LPSI Pump A
08/09/2022
Miscellaneous
Tagout: 2022-0107-CS Train A
08/09/2022
Miscellaneous
Tagout: 2022-0108-
0809/2022
Procedures
Protected Equipment Postings
16
Work Orders
52980548, 52988875
Work Orders
53000802
09/06/2022
Corrective Action
Documents
CR-WF3-YYYY-
XXXXX
2022-5674
08/05/2022
Engineering
Changes
ER-W3-2002-
0519-000
Install Software to Improve Path Reliability on LEFM
10/31/2002
Miscellaneous
DES-I-018
Feedwater Flow Measurement Instrumentation Specification
for Main Feedwater System
0
Miscellaneous
DES-I-018
Feedwater Flow Measurement Instrumentation Specification
for Main Feedwater System
0
Miscellaneous
Technical
Requirements
Manual 0
Technical Requirements Manual - Amendment 17
177
Procedures
ME-004-330
4kV Induction Motor Maintenance
304
Procedures
ME-007-008
Motor Operated Valves
20
Procedures
MI-004-644
Testing of Solenoid Valves
1
Procedures
OP-903-050
Component Cooling Water and Auxiliary Component Cooling
Water Pump and Valve Operability Test
44
Procedures
OP-903-121
Safety Systems Quarterly IST Valve Tests
35
Work Orders
52988875, 52952762, 52980548, 52946634, 52953000,
10
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
52946634, 53006370
Corrective Action
Documents
CR-WF3-YYYY-
NNNN
2019-3025, 2019-3164, 2020-5920, 2020-6021, 2020-7200,
2021-0344, 2022-1819, 2022-4487
Engineering
Changes
Operability Input to CR-WF3-2020-6021
10/25/2020
Engineering
Changes
Rebaseline MS-116B
01/25/2021
Engineering
Changes
ECM97-059
Design Basis Review for Atmospheric Dump Valves MS-
116A and MS-116B
001
Procedures
CEP-IST-4
Standard on Inservice Testing
311
Procedures
ECS09-005
Air Operated Valves - Design Basis Accident Times
001
Procedures
OP-100-014
Technical Specification and Technical Requirements
Compliance
364
Procedures
OP-903-035
Containment Spray Pump Operability Check
34
Procedures
OP-903-120
Containment and Miscellaneous Systems Quarterly IST
Valve Tests
035
Procedures
SEP-WF3-IST-1
WF3 Inservice Testing Bases Document
010
Procedures
SEP-WF3-IST-2
WF3 Inservice Testing Plan
011
Procedures
W4-DBD-6
Main Steam System - design basis document
302
Work Orders
52894192, 52955201, 52860841, 53002488, 552605,
52715847