Notifies That Schedule for Completion of Integrated Plan Issue BN-025, Wind & Tornado Loading, Changed to 890228 Due to Delivery Delays Involving Several Items Needed to Complete Installation & Testing
ML20196A315
Person / Time
Site: Big Rock Point File:Consumers Energy icon.png
Issue date: 12/01/1988
From: Marbaugh K
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
NUDOCS 8812050316
Download: ML20196A315 (1)


Text

- _ _ - - - -

4 i

ee, -.. j Consumers l

@ cowsm=S AHUNSANT PASSAESS Power oenerei ofNee: 1646 West Parnall Mood. hck.on, MI 49201 * (517) 788 0550 l

t l

December 1, 1988 Nuclear Regulatory Commission [

Document Control Desk  :

Washington DC 20555 l i

DOCKET 50-155 - LICENSE DPR BIG ROCK POINT PLANT - I NOTIFICATION OF SCHEDULE CHANGE FOR BIG ROCK POINT INTEGRATED PLAN ISSUE j BN-025. WIND AND TORNADO LOADING l f

Pursuant to the provisions of the Big Rock Point Plant Integrated Plan.  !

Consumers Power Company is required to notify the NRC of any schedular changes i-in NRC initiated Category "BN" issues at least 30 days in advance of the l originally scheduled completion date. This letter provides such notice for  ;

Issue BN-025. Wind and Tornado Loading. Completion of this item was scheduled  !

for December 31, 1988 but due to the circumstances identified below, will i instead be completed by February 28, 1989. l Resolution of Issue of BN-025 involves procurement of a portabic nunp and installation of associated connecting bardware. While the design package for this work is complete and the pump has been received. Consumers Power Company has encountered delivery delays involving several items needed to complete installation and testing. All hardware is expected to be oneite early in [

1989, with installation and testing completed by February 28. 1989. l l

Progress on this irrue will bw reported in the next Integrated Plan Semi-Annual }

l'pdate (Number 10) . j i

t i

n W i

Kenneth E Marbauh i Plant Licensing Enginest CC Administrator. Region III. NRC NRC Resident Inspector - Big Rock Point

{

8812050314 831201 f PDR ADOCN 05000155 g t P FDC OC1188-0223-NLO2 , g i s