Forwards Rev 2 to Post Shutdown Decommissioning Activities Rept (Psdar). Rev Incorporating Revised,Detailed Schedule & Revised Cost Estimate,Will Be Submitted to Util
ML20217H452
Person / Time
Site: Big Rock Point File:Consumers Energy icon.png
Issue date: 03/26/1998
From: Powers K
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20217H456 List:
References
NUDOCS 9804030353
Download: ML20217H452 (1)


Text

  • ' '

.I.

A CMSEnergy Company Big Rock Point Nuclear Plant MMM 10269 US-31 North Site General Manager Charlevoix, MI 49720 March 26, 1998 Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 DOCKET 50-155 - LICENSE DPR BIG ROCK POINT PLANT - POST SHUTDOWN DECOMNISSIONING ACTIVITIES REPORT (PSDAR); REVISION 2.

Pursuant to 10 CFR 50.82(a)(7), Consumers Energy Company hereby submits Revision 2 to the Post Shutdown Decommissioning Activities Report (PSDAR) for the Big Rock Point Plant. This revision incorporates a revised, detailed schedule and a revised cost' estimate that will be submitted to the Michigan Public Service Commission. This revision also includes a revised description of the planned decommissioning activities and a discussion that provides the reasons for concluding that the environmental impacts associated with site-specific decommissioning activities will be in compliance with 10 CFR

)

50.82(a)(6)(ii).

I Respectfully i

Kenneth P Powers General Manager i