Responds to Generic Ltr 89-08, Erosion/Corrosion Induced Pipe Wall Thinning. Review of NUMARC Guidelines Contained in App a of NUREG-1344,performed.Plant Intends to Implement Erosion/Corrosion Monitoring Program
ML20247A616
Person / Time
Site: Big Rock Point File:Consumers Energy icon.png
Issue date: 07/18/1989
From: Berry K
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
RTR-NUREG-1344 GL-89-08, GL-89-8, IEB-87-001, IEB-87-1, NUDOCS 8907210275
Download: ML20247A616 (2)


Text

e- ..

>, N-

-r

+

Consumers Power Kenneth W Berry.

M MlNG Director Nuclear bcensing MMM M General Offices: 1945 West Parnell Road, Jackson. MI 49201 e (517) 7881636 July 18, 1989 l

Nuclear Regulatory Commission-Document Control Desk Washington, DC 20555 DOCKET 50-155 - LICENSE DPR BIG ROCK POINT PLANT -

RESPONSE TO GENERIC LETTER 89 EROSION / CORROSION -

INDUCED PIPE WALL THINNING Nuclear Regulatory Commission Generic Letter 89-08 Erosion / Corrosion Induced Pipe. Wall Thinning, dated May 2, 1989, requires Consumers Power Company to provide assurances that a program, consisting of systematic measures to ensure that erosion /corrosiot. does not lead to degradation of single phase and two phase high-energy carbon ste:1 systems, has been implemented. Our response is to include information on whether or not we have implemented or intend to implement a long term erosion / corrosion monitoring program that provides assu'rances that procedures or administrative controls are in place to assure the NUMARC program or another effective program'is implemented and the structural integrity of all high-energy (two phase as well as single phase) carbon steel systems is maintained. Consumers Power Company's response for our Big Rock Point Plant is provided herein.

Pursuant to Generic ' Letter 89-08, a review of the NUMARC guidelines contained in Appendix A.af NUREG-1344, which was transmitted with the Generic Letter, has been performed. As stated in our response to NRC Bulletin 87-01 dated September 14, 1987, Big Rock Point has been examining single and two-phase lines since 1970; piping has been replaced when it was found to be necessary.

Big Rock Point will continue the ongoing examinations and in addition, intends to implement an Erosion / Corrosion Monitoring Program which will meet the requirements of NUREG-1344, Appendix A. This program will be in place by the 1990 Big Rock Point Refueling Outage so that additional erosion / corrosion examinations can take place at that time. The program will be an ongoing program controlled and implemented by plant procedures.

Kenneth W Berry Director, Nuclear Licensing CC Administrator, Region III, USNRC NRC Resident Inspector - Big Rock Point

^'*"*""*"'

jg72jggg gggggs, j7gof FDC OC0789-0154-NLO4 8U1

-,Pr CONSUMERS POWER COMPANY Big Rock Point Plant Docket 50-155 License DPR-6 Response to Generic Letter 89-08 dated May 2, 1989 At the request of the Commission and pursuant to the Atomic Energy Act of 1954 and the Energy Reorganfration Act of 1974, as amended, and the Commission's Rules and Regulations thereunder, Consumers Power Company submits our response to NRC letter dated May 2, 1989, entitled, " Erosion / Corrosion - Induced Pipe Wall Thinning". Consumers Power Company's response is dated July 18, 1989, i

CONSUMERS POWER COMPANY To the best of my knowledge, information and belief, the contents of this submittal are truthful and complete.

By W Robeft J %Echolson, Vice President Energy Supply Services Sworn and subscribed to before me this 18th day of July 1989.