Forwards Insp Repts 50-010/97-04,50-237/97-04 & 50-249/97-04 on 970125-0307.No Violations Noted
ML20138K098
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 05/01/1997
From: Caldwell J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Jamila Perry
COMMONWEALTH EDISON CO.
Shared Package
ML20138K102 List:
References
50-010-97-04, 50-10-97-4, 50-237-97-04, 50-237-97-4, 50-249-97-04, 50-249-97-4, NUDOCS 9705120153
Download: ML20138K098 (3)


See also: IR 05000010/1997004

Text

__ _ ._ _ _ . _ _ ._ _ __.

._.__g - _

Pubuc

s May 1, 1997

g

  • Mr. J. S. Perry

Site Vice President

Dresden Station

i Commonwealth Edison Company

6500 North Dresden Road

j Morris, IL 60450

SUBJECT: NRC RESIDENT INSPECTION REPORT 50-010:237:249/97004(DRP)

Dear Mr. Perry:

This refers to the inspection conducted from January 25 through March 7,1997, at the l

Dresden Nuclear facility. The purpose of the inspection was to determine whether 3

activities authorized by the license were conducted safely and in accordance with NRC j

requirements. During this period, routine resident inspections, augmented with regional l

personnel and with residents from other sites, were performed. At the conclusion of the  ;

inspection, the findings were discussed with those members of your staff identified in the i

enclosed report.

During this inspection period your staff, concurrent with the NRC, identified several

performance issues in operations. Your staff's recognition of these issues and the steps

taken to reinforce operational standards were indicative of a sound self-assessment

process. The effectiveness of your staff's corrective actions will be assessed by the NRC

in future inspections.

In accordance with 10 CFR 2.790 of the NRC's " Rules of Practice," a copy of this letter

and its enclosures will be placed in the NRC Public Document Room (PDR). i

Sincerely,

/s/ Jams L. Caldwell

James L. Caldwell, Director

Division of Reactor Projects

Docket Nos. 50-10; 50-237; 50-249

License Nos. DPR-2; DPR-19; DPR-25

Enclosure: Inspection Report 50-010:237:249/97004(DRP) g

PLEASE SEE ATTACHED CONCURRENCES

DOCUENT NAW: fWNSF9FTSPOWERSORESCRE97004.DFP

To ,eceive a copy of thes document. wecate in the hos *C" = Copy wthout ettech/enal "E" = Copy with attach /enci "N" = No copy

0FHCE fun fun fun

NAaAE Lerch/co K, opp Caldwed

DATE 5/ 19 7 5/ 19 7 5/ /97

vrrmeAL PEGDFID LOPY

120030 lllll

...

ll!I llllll

. . . .

lllll

.

9705120153 970501 '

PDR ADOCK 05000010 l

0 PDR l

1

s

)

May 1, 1997

Mr. J. S. Perry ,

Site Vice President l

Dresden Station i

Commonwealth Edison Company {

6500 North Dresden Road i

Morris, IL 60450 l

l

SUBJECT: NRC RESIDENT INSPECTION REPORT 50-010:237:249/97004(DRP) AND

NOTICE OF VIOLATION

l

Dear Mr. Perry:

This refers to the inspection conducted from January 25 through March 7,1997, at the j

Dresden Nuclear facility. The purpose of the inspection was to determine whether '

activities authorized by the license were corducted safely and in accordance with NRC

requirements. During this period, routine resident inspections, augmented with regional

personnel and with residents from other sites, were performed. At the conclusion of the

inspection, the findings were discussed with those members of your staff identified in the

enclosed report.

During this inspection your staff, concurrent with the NRC, identified events and issues

that were indicators of a change from the previously observed performance. Your staff's

recognition of this declining performance and the steps taken to reinforce operational

standards was indicative of a sound self assessment process. The effectiveness of your

staff's corrective actions to reverse this declining trend will be assessed by the NRC in

future inspections.

In accordance with 10 CFR 2.790 of the NRC's " Rules of Practice," a copy of this letter

and its enclosures will be placed in the NRC Public Document Room (PDR).

Sincerely,

/s/ J. A. Grobe

James L. Caldwell, Director

Division of Reactor Projects >

Docket Nos. 50-10; 50-237; 50-249

License Nos. DPR-2: DPR-19; DPR-25

.

Enclosures: Wtice of ViolatiW

2. Inspection Report 50-010:237:249/97004(DRP)

DOCUWWT NAM: fuNOMPTSPOWEM5WRESWRE97004.0fr

To recove a copy of the document irdcate in the bos *C" = Copy wethout attach /enal T - Capy unth setach/enci *N" = No copy

OPP G fun M kg M M

M. te,eh,- eut x,e., & J cens P

DATE h /97 dl l /97  ! /97 _

._. _ _ - . _ .- . _ _ . _ , _ _ _ ~ . . . . _ . ___ ___ _ _ , _ . . _ _

- - . . . - - - . . - - - . - . - ~ - - - - . - - - .~.- ----.-. - - . . -

!

r

=

!

i

' >

J. S. Perry -2-

.

4

cc w/ encl: T. J. Maiman, Senior Vice President ~ j

i Nuclear Operations Division

i D. A. Sager, Vice President,

! Generation Support

H. W. Keiser, Chief Nuclear

j. Operating Officer i

'

T. Nauman, Station Manager Unit 1 1

M. Heffley, Station Manager Units 2 and 3 I

F. Spangenberg, Regulatory Assurance l

Manager

1. Johnson, Acting Nuclear 1

Regulatory Services Manager 3

Richard Hubbard

Nathan Schloss, Economist

Office of the Attorney General

State Liaison Officer

Chairman, Illinois Commerce Commission i

Document Control Desk-Licensing ,

Distribution

Docket File w/enct Project Manager, NRR w/enci ,

PUBLIC IE-01 w/enci DRP w/ encl )

OC/LFDCB w/ encl Rlli PRR w/enci l

SRI LaSalle, Dresden, CAA1 w/enci(E-Mail) l

Quad Cities w/enci A B. Beach, w/ encl 1

RAC1 (E-Mail) Rlli Enf. Coordinator, w/enci (

Deputy RA, w/ encl DRS (2) w/enci l

TSS w/enci M. Webb, Project Manager, NRR w/enci j

)

i

I

i