Forwards SE Authorizing 980501 Request for Relief 0IA-VPR-1 Re IST Automatic Depressurization Sys Safety Relief Valves at Plant,Units 2 & 3,per 10CFR50.55a(a)(3)(ii)
ML20154G675
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 10/01/1998
From: Capra R
NRC (Affiliation Not Assigned)
To: Geoffrey Edwards
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
Shared Package
ML20154G680 List:
References
TAC-MA1741, TAC-MA1742, NUDOCS 9810130273
Download: ML20154G675 (3)


Text

- - - . - --- - . . . . - .. -- - _ _..-.-_ - - - - - - .-_ - .

Mr.Ga .:dwards October 1, 1998

. Directoi  : sing, MC 62A-1 PECO En t9, Comp:ny Nuclear Group Heaoquarters Correspondence Control Desk l

P. O. Box No.195 Wayne, PA 19087-0195

SUBJECT:

REQUEST FOR RELIEF OIA-VRR-1 FROM INSERVICE TESTING OF AUTOMATIC DEPRESSURIZATION SYSTEM SAFETY RELIEF VALVES AT PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3 (TAC NOS.

MA1741 AND MA1742

Dear Mr. Edwards:

By a letter dated May 1,1998; PECO Energy Company (the licensee) requested amendments to change the Peach Bottom Atomic Power Station (PBAPS) Technical Specifications (TSs); and relief from American Society of Mechanical Engineers (ASME) Operational Maintenance (OM)

Code inservice Testing (IST) requirements of plant Automatic Depressurization System (ADS) safety relief valves (SRVs). The request for amendments to the TSs will be addressed as a separate action. This action addresses the request for relief from ASME OM Code IST requirements.

The U.S. Nuclear Regulatory Commission staff authorizes the proposed altamative to inservice testing of the ADS SRVs required by the ASME OM Code - 1990, paragraph ISTC 4.2 and paragraph I 3.4.1(d), Appendix I at PBAPS, Units 2 and 3.

The NRC staff has reviewed the licensee's request and has determined that the licensee has demonstrated that the proposed altcmative to Code requirements provides assurance of adequate valve performance, and compliance with the Code would result in hardship or unusual difficulty without a compensating increase in quality and safety. Therefore, the proposed altemative testing is authonzed pursuant to10 CFR 50.55a(a)(3)(ii). The staff's safety evaluation is enclosed.

If you have any questions regarding this matter, please contact Mohan C. Thadani at 301-415-1476.

Sincerely,

/s Rober/ t A. Capra, Director Project Directorate 1-2 Division of Reactor Projects - t/11 Office of Nuclear Reactor Regulation Docket Nos. 50-277 and 278

Enclosure:

Safety Evaluation

{

cc w/encis: See next page i DISTRIBUTION g Docket File RCapra ESullivan CAnderson, RI THarris (e-mail) / O\

PUBLIC MThadani PDI-2 Reading File A40'Brien RHermann GHill(2)

GHammer -

OGC M

/

JZwolinski NGHomseth BMcCabe ACRS *See previous concurrence OFFICE Pbi'2/ led OGC* PDl-2/D NAME badani:mw bKMn MYoung RCapra

  • DATE YIN /98 fdb 09/28/98 'o/ V98 bFFICIAL RECORD COPY k#

DOCUMENT NAME: a:\PBMA1741.LTR R O 27 gy(( h f khk J

.,- 3 Mr. Garrett D. Edwards Peach Bottom Atomic Power Station, PECO Energy Company - Units 2 and 3 4

cc:

J. W. Durtiam, Sr.,- Esquire Chief-Division of Nuclear Safety-Sr. V.P. & General Counsel PA Dept. of PECO Energy Company Environmental Resources 2301 Market Street, S26-1 P.O. Box 8469 Philadelphia, PA '19101 Harrisburg, PA 17105-8469 PECO Energy Company ATTN: Mr. J. Doering, Vice President Board of Supervisors

. Peach Bottom Atomic Power Station Peach Bottom Township 1848 Lay Road 1 R.D.#1 Delta, PA 17314' Delta, PA 17314 PECO Energy Company Public Service Commission of Maryland ATTN: Regulatory Engineer, A4-SS Engineering Division Peach Bottom Atomic Power Station Chief Engineer 1848 Lay Road 6 St. Paul Centre Delta, PA 17314 Baltimore, MD 21202-6806 Resident inspector Mr. Richard McLean U.S. Nuclear Regulatory Commission Power Plant and Environmental Peach Bottom Atomic Power Station Review Division P.O. Box 399 Department of Natural Resources Delta,'PA 17314 . B-3, Tawes State Offce Building Annapolis, MD 2140i Regional Administrator, Region i U.S. Nuclear Regulatory Commission Dr. Judith Johnsrud 475 Allendale Road National Energy Committee King of Prussia, PA 19406 Sierra Club 433 Orlando Avenue Mr. Roland Fletcher State College, PA 16803-Department of Environment

- 201 West Preston Street Nianager-Financial Control & Co-Owner Baltimore, MD 21201 Affairs pun.: Service Electric and Gas A. F. Kirby, lll Company Extemal Operations - Nuclear P.O. Box 236 Delmarva Power & Light Company Hancocks Bridge, NJ 08038-0236 P.O. Box 231 Wilmington, DE 19899 Manager-Peach Bottom Licensing PECO Energy Company PECO Energy Company Nuclear Group Headquarters Plant Manager Correspondence Control Desk

- Peach Bottom Atomic Power Station P.O. Box No.195 1848 Lay Road Wayne, PA 19087-0195 Delta, PA 17314 -

)