Forwards Amends 224 & 228 to Licenses DPR-44 & DPR-56, Respectively & Safety Evaluation.Amends Revise TSs to Delete Requirements for Functional Testing of SRVs During Each Unit Startup
ML20154J185
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 10/05/1998
From: Thadani M
NRC (Affiliation Not Assigned)
To: Geoffrey Edwards
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
Shared Package
ML20154J189 List:
References
TAC-MA1741, TAC-MA1742, NUDOCS 9810150186
Download: ML20154J185 (11)


Text

. _ _ _ - _ _ _ _ _ _ _ _ _ _.

October 5, 1998 Mr. Garrett D. Edwards Director-Licensing, MC 62A-1 PECO Energy Company -

Nuclear Group Headquarters Correspondence Control Desk P.O. Box No.195 Wayne, PA 19087-0195

SUBJECT:

PEACH BOTTOM ATOMIC POWER STATION, UNIT NOS. 2 AND 3, TECHNICAL SPECIFICATIONS REVISION RELATING TO THE SURVEILLANCE OF THE SAFETY RELIEF VALVES (TAC NOS. MA1741 AND MA1742)

Dear Mr. Edwards:

The Commission has issued the enclosed Amendments Nos. 224 and 228 to Facility Operating License Nos. DPR-44 and DPR-56 for the Peach Bottom Atomic Power Station, Unit Nos. 2 and 3. These amendments consist of changes to the Technical Specifications (TSs) in response to PECO Energy Company's (the licensee) application dated May 1,1998, as supplemented by letter dated September 11,1998. In that letter the licensee also requested a relief from the American Society of Mechanical Engineers (ASME) Operation and Maintenance (OM) Code inservice testing (IST) requirements related to testing of the plant Automatic Depressurization System (ADS) SRVs. That relief request will be addressed as a separate action.

These amendments revise the TSs to delete the requirements for functional testing of SRVs during each unit startup.

A copy of the safety evaluation is also enclosed. Notice of issuance will be included in the Commission's Biweekly F ederal Realster Notice.

Sincerely,

/S/

Mohan C. Thadani, Senior Project Manager Project Directorate 1-2 kft Divis n of Reactor Projects - 1/II DO O

77 P

PDR Office of Nuclear Reactor Regulation Docket Nos. 50-277/278

Enclosures:

1. Amendment No. 224 to DPR-44
2. Amendment No. 228 to DPR-56
y. % p g f,' ' g,a u e s,..qp.pG}
3. Safety Evaluation g.g G J w

- ' ~.

cc w/encis: See next page DISTRIBUTION:

Docket File MO'Brien GHammer RCapra

[

PUBLIC ACRS W Beckner PDI-2 Reading [

MThadani OGC CAnderson, RGN-l DTermo BBoger GHill(4)

THarris (E-Mail SE) y hbPM PINN)

EMEB OGCa \\f PDl-2/D OFFICE NAME Whadani:mw Mbkn'erk SE dated RCapra F DATE'

/1/98 h /2 /98 08/28/98

/#///98 l' / /98 OFFICIAL RECORD COPY L " ' DOCUMENT NAME: a:\\pbma1741.amd 1E3001 1

m

'pS"%q k

UNITED STATES p

s NUCLEA"4 REGULATORY COMMISSION WASHINGTON, D.C. ensam mant October 5, 1998 Mr. Garrett D. Edwards Director-Licensing, MC 62A-1 PECO Energy Company Nuclear Group Headquarters Correspondence Control Desk P.O. Box No.195 Wayne, PA 19087-0195

SUBJECT:

PEACH BOTTOM ATOMIC POWER STATION, UNIT NOS. 2 AND 3, TECHNICAL SPECIFICATIONS REVISION RELATING TO THE SURVEILLANCE OF THE SAFETY RELIEF VALVES (TAC NOS. MA1741 AND MA1742) l

Dear Mr. Edwards:

- The Commission has issued the enclosed Amendments Nos. 224 and 228 to Facility Operating License Nos. DPR-44 and DPR-56 for the Peach Bottom Atomic Power Station, Unit Nos. 2 and 3. These amendments consist of changes to tiv Technical Specifications (TSs)in j

l response to PECO Energy Company's (the licensee) application dated May 1,1998, as 1

supplemented by letter dated September 11,1998. In that letter the licensee also requested a relief from the American Society of Mechanical Engineers (ASME) Operation and Maintenance j

(OM) Code inservice testing (IST) requirements related to testing of the plant Automatic l

Depressurization System (ADS) SRVs. That relief request will be addressed as a separate action.

l l

These amendments revise the TOs to delete the requirements for functional tasting of SRVs during each unit startup.

A copy of the safety evaluation is also enclosed. Notice of issuance will be included in the Comrr,ission's Biweekly Federal Reaister Notice.

l Sincerely, l

l M

M l

Mohan C. T eni, Senior Project Manager l

Project Directorate 1-2 l

Division of Reactor Projects-1/11 l

Office of Nuclear Reactor Regulation t

Docket Nos. 50-277/278

Enclosures:

1. Amendment No. 224 to DPR-44
2. Amendment No. 228 to DPR 56
3. Safety Evaluation cc w/encls: See next page i

__-.~

Mr. Garrett D. Edwards Peach Bottom Atomic Power Station, PECO Energy Company Units 2 and 3 1

i-d cc:

J. W. Durham, Sr., Esq'uire Chief Division of Nuclear Safety Sr. V.P. & General Counsel PA Dept. of PECO Energy Company.

Environmental Resources 2301 Market Street, S26-1 P.O. Box 8469 Philadelphia, PA 19101 Harrisburg, PA 17105-8469 PECO Energy Company

. ATTN: Mr. J. Doering, Vice President Board of Supervisors Peach Bottom Atomic Power Station Peach Bottom Township 1848 Lay Road R.D.#1 Delta, PA 17314 Delta, PA 17314 d

8 PECO Energy Company Public Service Commission of Maryland ATTN: Regulatory Engineer, A4-SS Engineering Division Peach Bottom Atomic Power Station Chief Engineer 1848 Lay Road 6 St. Paul Centre Delta, PA 17314 Baltimore, MD 21202-6806 Resident inspector Mr. Richard McLean U.S. Nuclear Regulatory Commission Power Plant and Environmental Peach Bottom Atomic Power Station Review Division P.O. Box 399 Department of Natural Resources Delta, PA 17314 B-3, Tawes State Office Building Annapolis, MD 21401 Regional Administrator, Region i U.S. Nuclear Regulatory Commission Dr. Judith Johnsrud 475 Allendale Road National Energy Committee King of Prussia, PA 19406 Sierra Club ~

433 Orlando Avenue Mr. Roland Fletcher State College, PA 16803 Department of Environment 201 West Preston Street Manager-Financial Control & Co-Owner Baltimore, MD 21201 Affairs Public Service Electric and Gas A. F. Kirby,111 Company Extemal Operations - Nuclear P.O. Box 236 Delmarva Power & Light Company Hancocks Bridge, NJ 08038-0236 P.O. Box 231 Wilmington, DE 19899 Manager-Peach Bottom Licensing PECO Energy Company PECO Energy Company Nuclear Group Headquarters Plant Manager Correspondence Control Desk Peach Bottom Atomic Power Station P.O. Box No.195 1848 Lay Road Wayne, PA 19087-0195 Delta, PA 17314