Forwards Insp Repts 50-277/99-05 & 50-278/99-05 on 990518- 0628.NRC Determined That Two Severity Level IV Violations of NRC Requirements Occurred & Being Treated as non-cited Violations Consistent with App C of Enforcement Policy
ML20210H534
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 07/27/1999
From: Cowgill C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Rainey G
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
Shared Package
ML20210H537 List:
References
50-277-99-05, 50-278-99-05, EA-99-192, NUDOCS 9908040032
Download: ML20210H534 (3)


See also: IR 05000277/1999005

Text

-

,

t

w

l

July 27,1999

EA 99-192

Mr. G. Rainey, President

PECO Nuclear

Nuclear Group Headquarters

,

l

Correspondence Control Desk

'

P.O. Box 195

Wayne, Pennsylvania 19087-0195

SUBJECT:

NRC INTEGRATED INSPECTION REPORT 50-277/99-05, 50-278/99-05

l

Dear Mr. Rainey:

On June 28,1999, the NRC completed an inspection at the Peach Bottom Atomic Power

Station. The enclosed report presents the results of that inspection. We concluded that your

staff continued to operate both units safely.

Our review of radioactive waste activities concluded that the Peach Bottom radioactive waste

processing, handling, storage and transportation programs were effective. The clean-up

activities of the spent fuel pools and shipment of irradiated metals for disposal were notable. In

,

particular, we observed that your staff conducted thorough preparations for and very good

execution of diving operations in the spent fuel pools that resulted in the low overall dose

,

received by the divers.

'

!

<

Based on the results of this inspection, the NRC has determined that two Severity Level IV

violations of NRC requirements occurred. These violations are being treated as Non-Cited

Violations (NCVs), consistent with Appendix C of the NRC Enforcement Policy. These NCVs

are described in the subject inspection report. The first NCV involved the inadvertent loss of the -

i

Unit 3 Emergency Auxiliary Transformer and associated fast transfer of four 4KV emergency

busses due to inadequate equipment configuration control management by your operating staff.

The second NOV involved non-conformances to the Peach Bottom Fire Protection Plan which

were self-identified by PECO engineering personnel during comprehensive reviews of the Fire

Protection Plan.

,

If you contest the violations or the severity level of the NCVs, you should provide a response

within 30 days of the date of this inspection report, with the basis for your denial, to the Nuclear

Regulatory Commission, ATTN: Document Control Desk, Washington DC 20555-0001 with

copies to the Regional Administrator, Region I, the Director, Office of Enforcement, United

i.

States Nuclear Regulatory Commission, Washington DC 20555-0001 and the NRC Resident

inspector at the Peach Bottom Atomic Power Station.

[

Y

"

9900040032 990727

i

l

PDR

ADOCK 05000277

l

G

PDR

I

L

-

'

t

i

G. Rainey

2

in accordance with 10 CFR 2.790 of the NRC's " Rules of Practice," a copy of this letter and its

enclosures will be placed in the NRC Public Document Room (PDR).

We appreciate your cooperation.

Sincerely,

Original Signed by:

Curtis J. Cowgill, Chief

Projects Branch 4

Division of Reactor Projects

Docket Nos.: 50-277,50-278

License Nos.: DPR-44, DPR-56

Enclosure: NRC Inspection Report No. 50-277/99-05,50-278/99-05

cc w/encis:

J. Hagan, Senior Vice President, Nuclear Operations

J. Doering, Vice President, Peach Bottom Atomic Power Station

_

M. Warner, Plant Manager, Peach Bottom Atomic Power Station

G. D. Edwards, Chairman, Nuclear Review Board

R. Boyce, Director, Nuclear Quality Assurance

A. F. Kirby, Ill, Extemal Operations - Delmarva Power & Light Co.

A. A. Winter, Manager, Experience Assessment

J. W. Durham, Sr., Senior Vice President and General Counsel

H. C. Kresge, Manager, External. Operations, Connectiv

N. J. Sproul, Manager, Financial Control & Co-owner Affairs, Connectiv

R. McLean, Power Plant Siting, Nuclear Evaluations

D. Levin, Acting Secretary of Harford County Council

R. Ochs, Maryland Safe Energy Coalition

J. H. Walter, Chief Engineer, Public Service Commission of Maryland

Mr. & Mrs. Dennis Hiebert, Peach Bottom Alliance

Mr. & Mrs. Kip Adams

Commonwealth of Pennsylvania

State of Maryland

TMl- Alert (TMIA)

.

.__

i

i

G. Rainey

3

Distribution w/encis:

Region i Docket Room (with concurrences)

Nuclear Safety Information Center (NSIC)

NRC Resident inspector

PUBLIC

H. Miller, RA/J. Wiggins, DRA

C. Cowgill, DRP

D. Florek, DRP

D. Cullison, DRP

C. O'Daniell, DRP

Distribution w/enels: (Via E-Mail)

M. Tschilitz, RI EDO Coordinator

E. Adensam, PDI, NRR

J. Clifford, NRR

M. Thadani, NRR

B. Buckley, NRR

R. Correia, NRR

inspection Program Branch, NRR (IPAS)

DOCDESK

1

DOCUMENT NAME: R:\\lNSPECT\\PB\\PB990505.wpd

.

i

Ta receive a copy of this document, indicate in the box: "C" = Coq without attachment / enclosure "E" = Copy with attachment / enclosure

"N" = No copy

)

OFFICE

Rl!DRP ,A

l

/

l

[

NAME

CCowgilillb

DATE

07/27/99' Y

OFFICIAL RECORD COPY