Line 14: Line 14:
| document type = CORRESPONDENCE-LETTERS, OUTGOING CORRESPONDENCE
| document type = CORRESPONDENCE-LETTERS, OUTGOING CORRESPONDENCE
| page count = 4
| page count = 4
| project =  
| project = TAC:M91338
| stage = Withdrawal
| stage = Withdrawal
}}
}}
Line 34: Line 34:
==Dear Mr. Hunger:==
==Dear Mr. Hunger:==


By letter dated January 13, 1995, as. supplemented by letters dated March 14, 1995 and April 12, 1995, PECO Energy Company submitted License Change Request 94-08 which was an application for an amendment to the Peach Bottom Atomic                l Power Station, Units 2 and 3, Operating License Nos. DPR-44 and DPR-56. The proposed changes modified Tables 3.7.1 and 3.7.4 of the TS to reflect a change in the number of primary containment penetrations and isolation valves                    l l            associated with the traversing in-core probe (TIP) system. The change in l            primary containment penetrations was the result of planned modifications to the TIP system for both Unit 2 and Unit 3.                                                '
By {{letter dated|date=January 13, 1995|text=letter dated January 13, 1995}}, as. supplemented by letters dated March 14, 1995 and April 12, 1995, PECO Energy Company submitted License Change Request 94-08 which was an application for an amendment to the Peach Bottom Atomic                l Power Station, Units 2 and 3, Operating License Nos. DPR-44 and DPR-56. The proposed changes modified Tables 3.7.1 and 3.7.4 of the TS to reflect a change in the number of primary containment penetrations and isolation valves                    l l            associated with the traversing in-core probe (TIP) system. The change in l            primary containment penetrations was the result of planned modifications to the TIP system for both Unit 2 and Unit 3.                                                '
l            On April 24, 1995, the staff issued license amendment 203 to the Unit 3 license which revised the TSs in accordance with PEC0's application, in issuing the amendment to the Unit 3 license, the staff stated:
l            On April 24, 1995, the staff issued license amendment 203 to the Unit 3 license which revised the TSs in accordance with PEC0's application, in issuing the amendment to the Unit 3 license, the staff stated:
In your January 13, 1995 application, you requested that the amendments be issued for both Peach Bottom Unit 2 and Unit 3. The staff has issued the requested license amendment for Unit 3 only.
In your January 13, 1995 application, you requested that the amendments be issued for both Peach Bottom Unit 2 and Unit 3. The staff has issued the requested license amendment for Unit 3 only.
Line 46: Line 46:


4 G. Hunger, Jr.                                      determine that you no longer require an amendment to the current l            Unit 2 TS to support the TIP modification, you are requested to withdraw the amendment request for Unit 2.
4 G. Hunger, Jr.                                      determine that you no longer require an amendment to the current l            Unit 2 TS to support the TIP modification, you are requested to withdraw the amendment request for Unit 2.
PECO implemented the ITS at Peach Bottom in January 1996 for both Unit 2 and Unit 3. Subsequently, in a letter dated March 15, 1996, PEC0 requested that License Chan9e Request 94-08 be withdrawn for Unit 2.
PECO implemented the ITS at Peach Bottom in January 1996 for both Unit 2 and Unit 3. Subsequently, in a {{letter dated|date=March 15, 1996|text=letter dated March 15, 1996}}, PEC0 requested that License Chan9e Request 94-08 be withdrawn for Unit 2.
1
1
,      The Commission has filed the enclosed Notice of Withdrawal of Application for        !
,      The Commission has filed the enclosed Notice of Withdrawal of Application for        !
Line 62: Line 62:
G. Hunger, Jr.                                          January 10, 1997            )
G. Hunger, Jr.                                          January 10, 1997            )
l determine that you no longer require an amendment to the current Unit 2 TS to support the TIP modification, you are requested to withdraw the' amendment request for Unit'2.
l determine that you no longer require an amendment to the current Unit 2 TS to support the TIP modification, you are requested to withdraw the' amendment request for Unit'2.
PECO implemented the ITS at Peach Bottom in January 1996 for both Unit 2 and            l Unit 3. Subsequently, in a letter dated March 15,1996, PECO requested that              l License Change Request 94-08 be withdrawn for Unit 2.                                ,
PECO implemented the ITS at Peach Bottom in January 1996 for both Unit 2 and            l Unit 3. Subsequently, in a {{letter dated|date=March 15, 1996|text=letter dated March 15,1996}}, PECO requested that              l License Change Request 94-08 be withdrawn for Unit 2.                                ,
l l
l l
The Commission has filed the enclosed Notice,of With'drawal of' Application for Amendment to Facility Operating License with the Office of the' Federal Register for publication.
The Commission has filed the enclosed Notice,of With'drawal of' Application for Amendment to Facility Operating License with the Office of the' Federal Register for publication.

Latest revision as of 01:48, 10 August 2022

Forwards Notice of Withdrawal of Change Request 94-08,which Was Application for Amend to Plant Operating Licenses DPR-44 & DPR-56
ML20133G118
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 01/10/1997
From: James Shea
NRC (Affiliation Not Assigned)
To: Hunger G
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
Shared Package
ML20133G122 List:
References
TAC-M91338, NUDOCS 9701150165
Download: ML20133G118 (4)


Text

'  ;

. . So' - 2 7 7

. g# M4 4 1

m  % UNITED STATES f'

I l . j t

NUCLEAR REGULATORY COMMISSION l WASHINGTON. D.C. 20666 4001 January 10, 1997 k ..... / ,

l Mr. Georga A. Hunger, Jr.  !

Director-Licensing, MC 62A-1 l PECO Energy Company i l Nuclear Group Headquarters

! Correspondence Control Desk l P.O. Box No. 195 I Wayne, PA 19087-0195 l

SUBJECT:

WITHDRAWAL 0F TECHNICAL SPECIFICATION (TS) CHANGE REQUEST 94-08, PEACH BOTTOM ATOMIC POWER STATION, UNIT 2 (TAC N0.91338)

Dear Mr. Hunger:

By letter dated January 13, 1995, as. supplemented by letters dated March 14, 1995 and April 12, 1995, PECO Energy Company submitted License Change Request 94-08 which was an application for an amendment to the Peach Bottom Atomic l Power Station, Units 2 and 3, Operating License Nos. DPR-44 and DPR-56. The proposed changes modified Tables 3.7.1 and 3.7.4 of the TS to reflect a change in the number of primary containment penetrations and isolation valves l l associated with the traversing in-core probe (TIP) system. The change in l primary containment penetrations was the result of planned modifications to the TIP system for both Unit 2 and Unit 3. '

l On April 24, 1995, the staff issued license amendment 203 to the Unit 3 license which revised the TSs in accordance with PEC0's application, in issuing the amendment to the Unit 3 license, the staff stated:

In your January 13, 1995 application, you requested that the amendments be issued for both Peach Bottom Unit 2 and Unit 3. The staff has issued the requested license amendment for Unit 3 only.

During a February 7, 1994 telephone conference, your staff indicated that the TIP modification will not be implemented on Unit 2 until September 1996. By that time, it is expected that l the NRC will have approved and you will have implemented the

! improved Technical Specifications (ITS) requested in your '

I submittal of September 29, 1994. ( )

l The proposed ITS do not contain tables equivalent to Tables 3.7.1 l and 3.7.4 in the current TS. Therefore, in order to prevent .

confusion, the staff will not issue the requested TIP license @

l amendment for Unit 2 because, in all likelihood, it would not be V implemented into the TS. The staff previously published a Notice of Consideration of Issuance to Facility Operating Licenses.

Proposed No Significant Hazards Consideration, and Opportunity for a Hearing in the Federal Reaister for the TIP amendment for Unit 3 only. You are requested to inform the staff if you desire to have the staff approve the TIP amendment for Unit 2 as the review process for your proposed ITS conversion progresses. If you 9701150165 970110 PDR ADOCK 05000277 P PDR 1500D4 97:0 HE CENTER COPY

4 G. Hunger, Jr. determine that you no longer require an amendment to the current l Unit 2 TS to support the TIP modification, you are requested to withdraw the amendment request for Unit 2.

PECO implemented the ITS at Peach Bottom in January 1996 for both Unit 2 and Unit 3. Subsequently, in a letter dated March 15, 1996, PEC0 requested that License Chan9e Request 94-08 be withdrawn for Unit 2.

1

, The Commission has filed the enclosed Notice of Withdrawal of Application for  !

Amendment to Facility Operating License with the Office of the Federal l Register for publication.

Sinc rAly,, ,

- c l, ~.

Jos eph /W. Shea, Project Manager

! Project Directorate I-2 2 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation l

Docket No. 50-277

Enclosure:

Notice of Withdrawal cc w/ encl: See next page i

J

G. Hunger, Jr. January 10, 1997 )

l determine that you no longer require an amendment to the current Unit 2 TS to support the TIP modification, you are requested to withdraw the' amendment request for Unit'2.

PECO implemented the ITS at Peach Bottom in January 1996 for both Unit 2 and l Unit 3. Subsequently, in a letter dated March 15,1996, PECO requested that l License Change Request 94-08 be withdrawn for Unit 2. ,

l l

The Commission has filed the enclosed Notice,of With'drawal of' Application for Amendment to Facility Operating License with the Office of the' Federal Register for publication.

I Sinc $ rely, l

/s/. '

s

  • Joseph W.,S'hea, Project Manage's r' Project Directorate I-2 Division of Reactor Projects - I/II' Office of'ffuclek Reactor Regulation Docket No. 50-277

Enclosure:

Notice of Withdrawal ,

cc w/ encl: See next page DISTRIBUTION:

Docket File M0'Brien WPasciak, RI PUBLIC JShea JStolz .

PDI-2 Reading OGC ACRS SVarga JZwolinski l l

0 l OFC  : )D - /PM : I A 7

I-2/D  :

l NAME  : JfH6k7 :y"B/ fan  : l

/g  :'J$polz DATE

/73/97: /' /97 : /p/97 :

OFFICI AW RECORD COPr' FILENAME: 9:\SHEA'\7EAMW9T3383lDF '-

+

- _ . . -~ - - - . . . .- . .- -- __ _ --

l j

Mr. George A. Hunger, Jr. Peach Bottom Atomic Power Station, I

. PECO Energy Company- Units 2 and 3 cc:

J. W. Durham, Sr., Esquire Mr. Rich R. Janati, Chief Sr. V.P. & General Counsel Division of Nuclear Safety PECO Energy Company Pennsylvania Department of 2301 Market Street, S26-1 Environmental Resources Philadelphia, Pennsylvania 19101 P. O. Box 8469 Harrisburg, Pennsylvania 17105-8469 PECO Energy Company ATTN: Mr. T. N. Mitchell, Vice President Board of Supervisors Peach Bottom Atomic Power Station Peach Bottom Township i 1848 Lay Road R. D. #1 l Delta, Pennsylvania 17314 Delta, Pennsylvania 17314 PECO Energy Company Public Service Commission of Maryland i ATTN: Regulatory Engineer, A4-SS Engineering Division )

Peach Bottom Atomic Power Station Chief Engineer Route 1, Box 208 6 St. Paul Centre Delta, Pennsylvania 17314 Baltimore, MD 21202-6806 )

Resident Inspector Mr. Richard McLean U.S. Nuclear Regulatory Commission Power Plant and Environmental Peach Bottom Atomic Power Station Review Division I

P.O. Box 399 Department of Natural Resources Delta, Pennsylvania 17314 B-3, Tawes State Office Building Annapolis, Maryland 21401 Regional Administrator, Region I ,

U.S. Nuclear Regulatory Commission Dr. Judith Johnsrud l 475 Allendale Road National Energy Committee l King of Prussia, Pennsylvania 19406 Sierra Club l 433 Orlando Avenue l Mr. Roland Fletcher State College, PA 16803 I Department of Environment 1 201 West Preston Street Bryan W. Gorman, Manager Baltimore, Maryland 21201 Joint Owners / External Affairs Interface Public Service Electric and Gas l Company I A. F. Kirt,y, III External Operations - Nuclear P.O. Box 236 Delmarva Power & Light Company Hancocks Bridge, NJ 08038-0236 P.O. Box 231 Wilmington, DE 19899 PECO Energy Company G. D. Edwards, Plant Manager Peach Bottom Atomic Power Station Route 1, Box 208 Delta, Pennsylvania 17314

!