Letter Sequence RAI |
---|
|
Results
Other: ML12125A181, ML12125A332, ML12131A451, ML12131A473, ML12139A058, ML12180A023, ML12244A571, ML12271A423, ML13029A016, ML14035A575, ML14045A284, ML14052A230, ML14083A617, ML14112A355, ML14112A450, ML14125A199, ML14169A441, ML14169A604, ML14169A637, ML14223A602, ML14281A365, ML14302A302, ULNRC-05886, Enclosure 1, Responses to the Individual Requests Contained in July 5, 2012 RAIs and Enclosure 2, Contains LRA Amendment 5 to Reflect Changes Made as a Result of the RAI Responses, ULNRC-05928, Enclosure 2 to ULNRC-05928, Amendment 15, LRA Updates, ULNRC-05957, Enclosure 2 to ULNRC-05957, Amendment 21, LRA Changes from RAI Responses, ULNRC-05979, Enclosure 2 to ULNRC-05979, Amendment 23, LRA Changes from RAI Responses and Commitment Updates Enclosure 2 Summary Table
|
MONTHYEARML12131A4732012-05-15015 May 2012 (Enclosure 4) Environmental Site Audit Regarding Callaway Plant, Unit 1, Project stage: Other ML12131A4512012-05-15015 May 2012 (Enclosure 2) Environmental Site Audit Regarding Callaway Plant, Unit 1 Project stage: Other ML12125A1812012-05-15015 May 2012 Environmental Site Audit Regarding Callaway Plant, Unit 1 Project stage: Other ML12125A3322012-05-15015 May 2012 (Enclosure 3) Environmental Site Audit Regarding Callaway Plant, Unit 1 Project stage: Other ML12139A0582012-05-31031 May 2012 Project Manager Change for the License Renewal Project (Safety) for Callaway Plant, Unit 1 Project stage: Other ML12144A0352012-06-11011 June 2012 Request for Additional Information for the Review of the Callaway Plant Unit 1 License Renewal Application Project stage: RAI ML12159A1542012-06-22022 June 2012 Summary of Site Audit Related to the Review of the License Renewal Application for Callaway Plant, Unit 1 (TAC Nos. ME7715 and ME7716) Project stage: Approval ML12157A0582012-06-22022 June 2012 Request for Additional Information for the Review of the Callaway Plant, Unit 1, License Renewal Application (TAC ME7708) 6 4 2012 Fmp Neutron Embrittlement and Rv Surveillance RAIs on Yee Chris Sydnor Project stage: RAI ML12164A9052012-07-0505 July 2012 Request for Additional Information for the Review of the Callaway Plant Unit 1, LRA Project stage: RAI ML12172A1112012-07-0909 July 2012 Request for Additional Information for the Review of the Callaway Plant, Unit 1, License Renewal Application, Set 4, Project stage: RAI ML12179A4002012-07-18018 July 2012 Request for Additional Information for the Review of the Callaway Plant Unit 1 License Renewal Application Project stage: RAI ML12206A2642012-08-0606 August 2012 Request for Additional Information for the Review of the Callaway Plant Unit 1 License Renewal Application, Set 6 Project stage: RAI ML12220A1602012-08-0606 August 2012 Responses to RAI Set #3 and Amendment 5 to the Callaway License Renewal Application (LRA) Project stage: Response to RAI ULNRC-05886, Enclosure 1, Responses to the Individual Requests Contained in July 5, 2012 RAIs and Enclosure 2, Contains LRA Amendment 5 to Reflect Changes Made as a Result of the RAI Responses2012-08-0606 August 2012 Enclosure 1, Responses to the Individual Requests Contained in July 5, 2012 RAIs and Enclosure 2, Contains LRA Amendment 5 to Reflect Changes Made as a Result of the RAI Responses Project stage: Other ML12180A0232012-08-0909 August 2012 Aging Management Programs Audit Report Regarding the Callaway Plant Unit 1 License Renewal Application Project stage: Other ML12271A4232012-08-13013 August 2012 Responses to Environmental RAI Set #1 to the Callaway LRA Project stage: Other ML12216A3382012-08-16016 August 2012 Request for Additional Information for the Review of the Callaway Plant Unit 1 License Renewal Application, Set 7 Project stage: RAI ML12233A6132012-08-23023 August 2012 Request for Additional Information for the Review of the Callaway Plant, Unit 1, License Renewal Application, Set 8, Electrical Project stage: RAI ML12244A5712012-08-30030 August 2012 Responses to E-RAI Set 2 to the License Renewal Application Project stage: Other ML12233A5702012-09-0606 September 2012 Request for Additional Information for the Review of the Callaway Plant Unit 1 License Renewal Application, Set 9 Project stage: RAI ML12284A4542012-09-12012 September 2012 Request for Additional Information for the Review of the Callaway Plant Unit 1 License Renewal Application, Set 10, Public Version Project stage: RAI ML12240A1742012-09-18018 September 2012 Review of the 2011 Refueling Outage Steam Generator Tube Inservice Inspection Reports Project stage: Approval ML12244A4292012-09-18018 September 2012 Summary of Telephone Conference Call Held on August 29, 2012, Between the U.S. Nuclear Regulatory Commission and Union Electric Company, Concerning the Request for Additional Information Pertaining to the Callaway Plant, Unit 1, License Ren Project stage: RAI ML12250A7702012-09-20020 September 2012 Request for Additional Information for the Review of the Callaway Plant Unit 1 License Renewal Application, Set 11 Project stage: RAI ML12256A8952012-09-25025 September 2012 RAI for the Review of the Callaway Plant, Unit 1, LRA, Set 12 Project stage: RAI ML12255A2872012-10-0101 October 2012 Request for Additional Information for the Review of the Callaway Plant Unit 1, License Renewal Application, Set 13 Project stage: RAI ML12262A3112012-10-0202 October 2012 Summary of Telephone Conference Call Held on September 14, 2012, Between NRC and Union Electric Company, Concerning the SAMA RAI for the Callaway Plant, Unit 1, LRA Project stage: RAI ML12270A1472012-10-0303 October 2012 Request for Additional Information for the Review of the Callaway Plant Unit 1 License Renewal Application, Set 14 Project stage: RAI ML12276A3732012-10-12012 October 2012 RAI for the Review of the Callaway Plant Unit 1, LRA Set 15 Project stage: RAI ML12299A2482012-10-24024 October 2012 Responses to RAI Set #11 & #12 and Amendment 13 to the Callaway LRA Project stage: Response to RAI ULNRC-05928, Enclosure 2 to ULNRC-05928, Amendment 15, LRA Updates2012-11-0808 November 2012 Enclosure 2 to ULNRC-05928, Amendment 15, LRA Updates Project stage: Other ML12314A1412012-11-0808 November 2012 Responses to RAI Set #15 and Amendment 15 to the Callaway LRA Project stage: Response to RAI ULNRC-05929, Responses to RAI Set 16 and Amendment 16 to the LRA2012-11-20020 November 2012 Responses to RAI Set #16 and Amendment 16 to the LRA Project stage: Response to RAI ML12321A1992012-11-29029 November 2012 9/27/12 - Summary of Telephone Conference Call Held Between the NRC and Union Electric Company (Ameren Missouri), Concerning RAIs Pertaining to the Callaway Plant, Unit 1, License Renewal Application Project stage: RAI ML12326A9152012-12-0707 December 2012 RAI for the Review of the Callaway Plant Unit 1, LRA, Set 18 Project stage: RAI ML12342A1722012-12-27027 December 2012 Request for Additional Information for the Review of the Callaway Plant Unit 1 License Renewal Application Project stage: RAI ML13009A2112013-01-14014 January 2013 Request for Additional Information for the Review of the Callaway Plant 1 License Renewal Application Project stage: RAI ULNRC-05950, Responses to RAI Set 19 & Set 20 and Amendment 20 to the Callaway LRA2013-01-24024 January 2013 Responses to RAI Set 19 & Set 20 and Amendment 20 to the Callaway LRA Project stage: Response to RAI ML13025A0312013-01-30030 January 2013 Request for Additional Information for the Review of the Callaway Plant, Unit 1, License Renewal Application, Set 21 Project stage: RAI ML13029A0162013-02-12012 February 2013 Summary of Telephone Conference Call Held on January 22, 2013, Between the U.S. Nuclear Regulatory Commission Project stage: Other ML13029A6592013-02-12012 February 2013 Summary of Telephone Conference Call Held on December 6, 2012, Between the NRC and Union Electric Company, Concerning Request for Additional Information Pertaining to the Callaway Plant Unit 1, LRA Project stage: RAI ML13046A3072013-02-14014 February 2013 Enclosure 1 to ULNRC-05957, License Renewal Application, Request for Additional Information (RAI) Set #21 Responses Project stage: Request ML13046A3062013-02-14014 February 2013 Response to RAI Set #21 and Amendment 21 to the Callaway LRA Project stage: Response to RAI ULNRC-05957, Enclosure 2 to ULNRC-05957, Amendment 21, LRA Changes from RAI Responses2013-02-14014 February 2013 Enclosure 2 to ULNRC-05957, Amendment 21, LRA Changes from RAI Responses Project stage: Other ML13038A3082013-02-21021 February 2013 RAI for the Review of the Callaway Plant Unit 1, LRA, Set 22 Project stage: RAI ML12307A3912013-02-26026 February 2013 Schedule Revision for the Environmental Review of the Callaway Plant, Unit 1 License Renewal Application (TAC Nos. ME7715 and ME7716) Project stage: Approval ML13063A4762013-02-28028 February 2013 Response to RAI Set #22 and Amendment 22 to the Callaway LRA Project stage: Response to RAI ML13059A8002013-03-11011 March 2013 Summary of Telephone Call Held on 11/5/12, Between NRC and Union Electric Company, Regarding Request for Clarification of Responses to the SAMA RAI Concerning Callaway Plant, Unit 1, LRA Project stage: RAI ML13042A0422013-03-26026 March 2013 Request for Additional Information for the Review of the Callaway Plant Unit 1 License Renewal Application, Set 23 Project stage: RAI ML13058A1242013-03-29029 March 2013 Request for Additional Information for the Review of the Callaway Plant, Unit 1, License Renewal Application, Set 24 Project stage: RAI 2012-08-23
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000483/20240032024-10-23023 October 2024 Integrated Inspection Report 05000483/2024003 IR 05000483/20240132024-10-21021 October 2024 Design Basis Assurance Inspection (Programs) Inspection Report 05000483/2024013 IR 05000483/20244012024-10-0909 October 2024 Material Control and Accounting Program Inspection Report 05000483/2024401 Public ULNRC-06901, Concurrent Inoperability of Control Room Air Conditioning System Train and Opposite Train Emergency Diesel Generator Results in Condition Prohibited by Technical Specifications Limiting (Letter)2024-10-0101 October 2024 Concurrent Inoperability of Control Room Air Conditioning System Train and Opposite Train Emergency Diesel Generator Results in Condition Prohibited by Technical Specifications Limiting (Letter) ML24247A3042024-09-11011 September 2024 Regulatory Audit Questions for License Renewal Commitments 34 and 35 (EPID L-2024-LRO-0009) - Non-Proprietary IR 05000483/20244032024-08-28028 August 2024 Security Baseline Inspection 05000483-2024-403 IR 05000483/20240052024-08-14014 August 2024 Updated Inspection Plan for Callaway Plant (Report 05000483/2024005) IR 05000483/20253012024-08-0505 August 2024 Notification of NRC Initial Operator Licensing Examination 05000483/2025301 ML24212A2822024-08-0202 August 2024 Regulatory Audit Summary Concerning Review of Request No. C3R-01 for Proposed Alternative to ASME Code, Section XI Requirements for Containment Building Inspections IR 05000483/20240022024-07-18018 July 2024 And Independent Spent Fuel Storage Installation Integrated Inspection Report 05000483/2024002 and 07201045/2024001 ML24185A1032024-07-16016 July 2024 2024 Biennial Problem Identification and Resolution Inspection Report ULNRC-06891, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00052024-06-26026 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0005 ULNRC-06892, Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC00062024-06-26026 June 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC0006 ULNRC-06884, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00022024-06-12012 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0002 ULNRC-06885, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00032024-06-12012 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0003 ULNRC-06886, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00042024-06-12012 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0004 ML24144A0492024-06-11011 June 2024 Requests for Relief from ASME OM Code Pump and Valve Testing Requirements for Fifth 120-Month Inservice Testing Interval ML24158A5222024-06-0606 June 2024 Application to Revise Technical Specifications to Adopt Tstf-569, Rev. 2, Revise Response Time Testing Definition (LDCN 24-0008) ML24178A1132024-06-0606 June 2024 Ameren Missouris Intent to Adopt Revision 1 to Amendment 0 of Certificate of Compliance No. 1040 as Applicable to the ISFSI at the Callaway Plant Site ML24143A1632024-05-23023 May 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Storage Canister HGMPC0001 ML24137A2342024-05-16016 May 2024 Independent Spent Fuel Storage Installation - Registration of Dry Spent Fuel Storage Canister HGMPC0011 ULNRC-06882, Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC00122024-05-16016 May 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC0012 ML24122A1502024-05-0707 May 2024 Audit Plan to Support Review of Steam Generator License Renewal Response to Commitment Nos 34 and 35 IR 05000483/20244022024-05-0606 May 2024 Security Baseline Inspection Report 05000483/2024402 (Full Report) ULNRC-06877, Final Safety Analysis Report Revision OL-27 and Technical Specification Bases Revision 252024-05-0606 May 2024 Final Safety Analysis Report Revision OL-27 and Technical Specification Bases Revision 25 ULNRC-06856, CFR 50.59 and 10 CFR 72.48 Summary Report2024-05-0101 May 2024 CFR 50.59 and 10 CFR 72.48 Summary Report IR 05000483/20240112024-05-0101 May 2024 NRC Post-Approval Site Inspection for License Renewal (Phase 2) Report 05000483/2024011 ULNRC-06869, Submittal of Callaway, Unit 1, 2023 Annual Radiological Environmental Operating Report2024-04-30030 April 2024 Submittal of Callaway, Unit 1, 2023 Annual Radiological Environmental Operating Report ML24122A1132024-04-30030 April 2024 Submittal of Callaway, Unit 1, 2023 Annual Radioactive Effluent Release Report ULNRC-06876, Registration of Dry Spent Fuel Storage Canister HGMPC00102024-04-25025 April 2024 Registration of Dry Spent Fuel Storage Canister HGMPC0010 ULNRC-06866, Submittal of Cycle 26 Commitment Change Summary Report2024-04-17017 April 2024 Submittal of Cycle 26 Commitment Change Summary Report ULNRC-06871, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00072024-04-17017 April 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0007 ULNRC-06872, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00082024-04-17017 April 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0008 ML24108A1082024-04-17017 April 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC0009 IR 05000483/20240012024-04-16016 April 2024 Integrated Inspection Report 05000483/2024001 IR 05000483/20244042024-04-0909 April 2024 Cyber Security Inspection Report 05000483/2024404 ML24088A3212024-04-0101 April 2024 Notification of Commercial Grade Dedication Inspection (05000483/2024013) and Request for Information ML24086A5132024-03-26026 March 2024 CFR 50.46 Annual Report Regarding ECCS Evaluation Model Revisions ULNRC-06863, Submittal of Annual Exposure Report for 20232024-03-20020 March 2024 Submittal of Annual Exposure Report for 2023 ML24079A1622024-03-19019 March 2024 Re Nuclear Property Insurance Reporting ML24066A1932024-03-0707 March 2024 2024 Callaway Plant Notification of Biennial Problem Identification and Resolution Inspection and Request for Information ULNRC-06852, Owners Activity Reports (OAR-1 Forms) for Cycle/Refuel 262024-03-0505 March 2024 Owners Activity Reports (OAR-1 Forms) for Cycle/Refuel 26 IR 05000483/20230062024-02-28028 February 2024 Annual Assessment Letter for Callaway Plant Report 05000483/2023006 ML24052A3662024-02-26026 February 2024 Regulatory Audit Plan in Support of Proposed Alternative to ASME Code, Section XI Requirements for Containment Building Inspections IR 05000483/20230022024-02-21021 February 2024 Amended Integrated Inspection Report 05000483/2023002 ULNRC-06858, Completion of License Renewal Activities Prior to Entering the Period of Extended Operation2024-02-21021 February 2024 Completion of License Renewal Activities Prior to Entering the Period of Extended Operation ML24036A1712024-02-20020 February 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0079 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ULNRC-06853, Submittal of 2023 Fitness for Duty Performance Data Per Per 10 CFR 26.7172024-01-29029 January 2024 Submittal of 2023 Fitness for Duty Performance Data Per Per 10 CFR 26.717 ML24008A0552024-01-19019 January 2024 Acceptance of Requested Licensing Action - Proposed Alternative to the Requirements of the ASME Code (EPID L-2023-LLR- 0061) IR 05000483/20230042024-01-19019 January 2024 – Integrated Inspection Report 05000483/2023004 2024-09-11
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24066A1932024-03-0707 March 2024 2024 Callaway Plant Notification of Biennial Problem Identification and Resolution Inspection and Request for Information ML23200A2982023-07-19019 July 2023 NRR E-mail Capture - Callaway Plant, Unit 1 - Final Request for Additional Information (RAI) - Request for Approval of Oqam, Revision 36a - EPID L-2023-LLQ-0000 ML23174A1272023-06-23023 June 2023 Cw FFD Document Request List 2023 ML23158A1462023-06-13013 June 2023 Notification of Post-Approval Site Inspection for License Renewal and Request for Information Inspection (05000483/2023010) ML23163A1572023-06-0606 June 2023 In-service Inspection Request for Information ML23096A0072023-04-0505 April 2023 NRR E-mail Capture - Final Request for Additional Information - Callaway Plant, Unit 1 - License Amendment Request to Revise TS 5.5.16 for Permanent Extension of Integrated Leak Rate Testing - EPID L-2022-LLA-0165 ML23080A1382023-03-21021 March 2023 Notification of Inspection (NRC Inspection Report 05000483/2023003) and Request for Information ML23073A0262023-03-13013 March 2023 NRR E-mail Capture - Final - Request for Additional Information - Callaway Plant, Unit 1 - SG Inspection Report Review - EPID L-2022-LRO-0143 ML23037A7092023-02-0606 February 2023 April 2023 Emergency Preparedness Exercise Inspection - Request for Information ML23026A0212023-01-24024 January 2023 NRR E-mail Capture - Final - Request for Additional Information - Callaway Plant, Unit 1 - LAR for Proposed Changes to TS for SFP - ML22287A0952022-10-14014 October 2022 NRR E-mail Capture - Final - Request for Additional Information - Callaway Plant, Unit 1 - License Amendment Request for Adoption of Alternate Source Term and Revision of Technical Specifications - EPID L-2021-LLA-0177 ML22269A4312022-09-26026 September 2022 November 2022 Emergency Preparedness Program Inspection - Request for Information ML22173A0562022-06-22022 June 2022 Information Request, Security IR 2022402 ML22167A0252022-06-15015 June 2022 NRR E-mail Capture - Final - Request for Additional Information - Callaway Plant, Unit 1 - LAR for Proposed Revision to Radiological Emergency Response Plan Regarding Response & Notification Goals - EPID L-2022-LLA-0024 ML22157A0572022-06-0606 June 2022 Notification of NRC Design Bases Assurance Inspection (Programs) (05000483/2022013) and Request for Information ML22154A0122022-06-0202 June 2022 NRR E-mail Capture - Final - Request for Additional Information - Callaway Plant, Unit 1 - License Amendment Request for Adoption of Alternate Source Term and Revision of Technical Specifications - EPID L-2021-LLA-0177 ML22151A0512022-05-27027 May 2022 NRR E-mail Capture - Final - Request for Additional Information - Columbia Generating Station - LAR to Change TS 3.4.11 - Reactor Coolant System Pressure and Temperature Limits - EPID L-2021-LLA-0191 ML22137A0292022-05-16016 May 2022 NRR E-mail Capture - Draft - Request for Additional Information - Callaway Plant, Unit 1 - License Amendment Request for Adoption of Alternate Source Term and Revision of Technical Specifications - EPID L-2021-LLA-0177 ML22096A0232022-04-0505 April 2022 NRR E-mail Capture - Callaway Plant - Final RAIs - License Amendment and Regulatory Exemptions for a Risk-Informed Approach to Address Generic Safety Issue - 191 and Respond to GL 2004-02 (EPIDs L-2021-LLA-0059 and L-2021-LLE-0021) ML21336A6392021-12-0202 December 2021 .05 Sec Doc Request ML21319A0062021-11-30030 November 2021 Supplemental Information Needed for Acceptance of Requested Licensing Actions License Amendment Request for Adoption of Alternate Source Term and Revision of Technical Specifications ML21258A0382021-09-14014 September 2021 NRR E-mail Capture - Final - Request for Additional Information - Callaway, Unit 1 - LAR to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors- EPID L-2020-LLA-023 ML21159A2352021-06-17017 June 2021 Notification of NRC Triennial Heat Exchanger/Heat Sink Performance Inspection (05000483/2021003) and Request for Information ML21130A5882021-05-11011 May 2021 Supplemental Information Needed for Acceptance of Requested Licensing Actions to Adopt a Risk-Informed Approach to Address GSI-191 and Respond to Generic Letter 2004 02 ML21088A3872021-03-30030 March 2021 Notification of Evaluations of Changes, Tests, and Experiments Inspection (Inspection Report 05000483/2021002) and Request for Information ML21007A1622021-01-0606 January 2021 NRR E-mail Capture - Final - Request for Additional Information - (COVID-19) Callaway Plant, Unit 1 - Additional Request for Exemption from Specific Requirements of 10 CFR Part 26, Fitness for Duty Programs - EPID L-2021-LLE-0242 ML20203M3682020-07-21021 July 2020 NRR E-mail Capture - Draft Request for Additional Information - Callaway Plant, Unit 1 - License Amendment Request - Revision to Technical Specification (TS) 5.3.1 and Deletion of TS 5.3.1.1 and 5.3.1.2 - EPID L-2020-LLA-0046 ML20162A1882020-06-10010 June 2020 Request for Supporting Information for the Callaway SPRA Audit Review - Draft Supplement ML20280A5442020-03-25025 March 2020 Cwy 2020 PIR Request for Information ML20064B6582020-02-27027 February 2020 Second, Third, and Fourth Request for Information for Callaway Dba Teams Inspection 2020011 ML19317E6332019-11-13013 November 2019 Request for Supporting Information for the Callaway SPRA Audit Review ML19107A5152019-04-11011 April 2019 Cwy 2019410 RFI Cyber Security Gap ML19078A2932019-03-18018 March 2019 Notification of an NRC Triennial Fire Protection Baseline Inspection (NRC Inspection Report 05000483/2019010) and Request for Information ML19023A2032019-01-22022 January 2019 Notification of NRC Triennial Heat Sink Performance Inspection (05000483/2019001) and Request for Information ML19009A3442019-01-0909 January 2019 NRR E-mail Capture - Formal Release of RAIs Ref: Callaway Plant Class 1E LAR, L-2018-LLA-0062 ML18355A4882018-12-20020 December 2018 NRR E-mail Capture - Formal Release of RAI Ref: Callaway Plant EAL Changes, L-2018-LLA-0239 ML18331A2052018-11-27027 November 2018 NRR E-mail Capture - Formal Release of RAIs Ref: Callaway Relief Request EPID L-2018-LLR-0051 ML18025B4672018-01-24024 January 2018 NRR E-mail Capture - Request for Extension of Due Date for RAI Response ML17304B1912017-10-31031 October 2017 NRR E-mail Capture - Requests for Additional Information Concerning Callaway License Amendment - Thermal Overload Protection ML17142A1352017-05-19019 May 2017 Notification of NRC Design Bases Assurance Inspection (05000483/2017007) and Initial Request for Information ML17115A0622017-04-25025 April 2017 NRR E-mail Capture - Requests for Additional Information -- Callaway Plant, Unit 1, Technical Specification 5.6.5, Core Operating Limits Report CAC MF8463 ML17038A2292017-02-0707 February 2017 NRR E-mail Capture - RAI Formal Release for Callaway SG Tube Inspection Report, MF8474 ML16111B3222016-04-20020 April 2016 Notification of Evaluations of Changes, Tests, and Experiments, and Permanent Plant Modifications Inspection (05000483/2016007) and Request for Information ML15316A1532015-11-12012 November 2015 Request for Additional Information Email, Relief Request 13R-11 (Pressurizer Welds) from Code Case N-460 Requirements, Third 10-Year Inservice Inspection Interval ML15096A0942015-04-0606 April 2015 Notification of Inspection (NRC Inspection Report 05000483/2015003) and Request for Information ML14353A1172014-12-22022 December 2014 Request for Additional Information, Round 3, License Amendment Request to Revise Final Safety Analysis Report Standard Plant Section 3.6 for High Density Polyethylene (Hdpe) Crack Exclusion ML14294A7752014-10-28028 October 2014 Request for Additional Information, Round 2, License Amendment Request to Revise Final Safety Analysis Report Standard Plant Section 3.6 for High Density Polyethylene (Hdpe) Crack Exclusion ML14203A0632014-07-25025 July 2014 Request for Additional Information, Relief Request I3R-17, Proposed Alternative to ASME Code, Section XI Requirements, Which Extends Rv ISI Frequency from 10 to 20 Years, Third 10-Year ISI Interval ML14178A8232014-07-0101 July 2014 Request for Additional Information, License Amendment Request to Revise Final Safety Analysis Report- Standard Plant Section 3.6 for High Density Polyethylene (Hdpe) Crack Exclusion ULNRC-06117, Callaway Plant, Unit 1, License Revewal Application, Request for Additional Information (RAI) Set 31 Responses2014-04-24024 April 2014 Callaway Plant, Unit 1, License Revewal Application, Request for Additional Information (RAI) Set 31 Responses 2024-03-07
[Table view] |
Text
June 11, 2012
Mr. Adam C. Heflin Senior Vice President and Chief Nuclear Officer Union Electric Company P.O. Box 620 Fulton, MO 65251
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE CALLAWAY PLANT, UNIT 1 LICENSE RENEWAL APPLICATION (TAC NO. ME7708)
Dear Mr. Heflin:
By letter dated December 15, 2011, Union Electric Company submitted an application pursuant to Title 10 of the Code of Federal Regulations Part 54 for renewal of Operating License NPF-30 for the Callaway Plant, Unit 1. The staff of the U.S. Nuclear Regulatory Commission (NRC or the staff) is reviewing this application in accordance with the guidance in NUREG-1800, "Standard Review Plan for Review of License Renewal Applications for Nuclear Power Plants." During its review, the staff has identified areas where additional information is needed to complete the review. The staff's requests for additional information are included in the enclosure. Further requests for additional information may be issued in the future.
Items in the enclosure were discussed with Sarah G. Kovaleski, of your staff, and a mutually agreeable date for the response is within 30 days from the date of this letter. If you have any questions, please contact me by telephone at 301-415-2946 or by e-mail at Samuel.CuadradoDeJesus@nrc.gov. Sincerely,
/RA/ Samuel Cuadrado de Jesús, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-483
Enclosure:
As stated cc w/encl: Listserv
ML12144A035 OFFICE LA:DLR/RPB1 PM:DLR/RPB1 BC:DLR/RPB1 PM:DLR/RPB1 NAME YEdmonds SCuadrado DMorey SCuadrado DATE 06 / 07 /12 06 / 06 /12 06 / 07 /12 06 / 11 /12 Letter to A. Heflin from S. Cuadrado De Jesus dated June 11, 2012.
SUBJECT:
RECEIPT AND AVAILABILITY OF THE LICENSE RENEWAL APPLICATION FOR THE CALLAWAY PLANT, UNIT 1 DISTRIBUTION:
E-MAIL: PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRapb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDraAfpb Resources RidsNrrDeEeeb Resources RidsOgcMailCenter Resources ------------------------------------ M. Spencer (OGC)
T. Hartman DWrona DMorey MThadani DMcIntyer, OPA A. Hon G. Armstrong G. Pick (RIV) VDricks, RIV LUselding, RIV DDumbacher, RIV
CALLAWAY PLANT UNIT 1 LICENSE RENEWAL APPLICATION REQUEST FOR ADDITIONAL INFORMATION
2.2 Plant-Level Scoping Results RAI 2.2-1
The applicant's scoping criteria is described in Section 2.1 of the Callaway Plant, Unit 1 (Callaway) License Renewal Application (LRA). LRA Section 2.2, Table 2.2-1, "Scoping Results," provides the results of applying the license renewal scoping criteria to systems, structures, and components (SSCs). The following systems, as described in the Updated Final Safety Analysis Report (UFSAR), could not be located in LRA Table 2.2-1.
The staff requests that the applicant justify its exclusion of the above system from LRA Table 2.2-1.
2.3.3.5 Service Water System RAI 2.3.3.5-1 LRA Section 2.1 describes the applicant's scoping methodology, which specifies how systems or components were determined to be included in scope of license renewal. The staff confirms the inclusion of all components subject to aging management review (AMR) by reviewing the results of the screening of components within the license renewal boundary. For the drawing locations identified in the table below, the continuation of piping within the scope of license renewal could not be located.
License Renewal Boundary Drawing Number & Location Continuation IssueLR-CW-EA-M-22EA01, location E-8 A section of (a)(2) piping (from line 036"-HBD-8" downstream of valve V160) continues to M-22KB02, location B-8, which was not submitted as part of the application. LR-CW-EA-M-22EA01, locations C-6/7 A section of (a)(2) piping (from line 039"-HBD-8" upstream of valve V159) continues to M-22KB02, location B-8, which was not submitted as part of the application. UFSAR Section System 18.1.17 Plant Safety Parameter Display System Safety Parameter Display System The staff requests the applicant to provide sufficient information to locate the license renewal boundary. If the continuation cannot be shown on license renewal boundary drawings, then provide additional information describing the extent of the scoping boundary and verify whether or not there are additional AMR component types between the continuation and the termination of the scoping boundary. If the scoping classification of a section of the piping changes over the continuation, provide additional information to clarify the change in scoping classification.
2.3.3.8 Compressed Air System RAI 2.3.3.8-1 In LRA Section 2.1.2.2 the applicant indicates nonsafety-related SSCs attached to safety-related SSCs are in scope of license renewal for 10 CFR 54.4(a)(2) up to the first seismic anchor past the safety/nonsafety interface. On the following drawings the staff could not locate seismic anchors on the nonsafety related lines:
License Renewal Application Drawing Number & Location 10 CFR 54.4(a)(2) Pipe Line(s) or IdentifierLR-CW-KA-M-22KA01, location B-1 317-JDD-1" downstream of valve V277 (No license renewal boundary drawing M-22KA09 to confirm seismic endpoint) LR-CW-KA-M-22KA04, location F-4 495-JDD- 1/2" downstream of valve V474 LR-CW-KA-M-22KA04, location F-4 Upstream of valve V474 and connected to the 1/2" line with an endpoint shown as RB2 LR-CW-KA-M-22KA04, location F-4 Downstream of valve V483 and connected to the 1/2" line with an endpoint shown as RB17
Provide additional information to locate the seismic anchors or anchored components between the safety/non-safety interface and the end of the 10 CFR 54.4(a)(2) scoping boundary.
2.3.3.20 Fire Protection System The staff has identified that the fire protection systems and components discussed in the following sections have been excluded from the scope of license renewal and an AMR. These systems and components that were not included in the license renewal boundaries appear to have fire protection intended functions required for compliance with 10 CFR 50.48, "Fire protection," as stated in 10 CFR 54.4. Therefore, in order to complete our review, the staff requires responses to the following RAIs: RAI 2.3.3.20-1
The following LRA boundary drawings shows the following fire water systems/components as out of scope (i.e., not colored in green):
LRA Drawing Systems/Components Location LR-CW-KC-M-22KC01 Turbine Generator Bearing A4 North Area Below Turbine (El. 2000'-0") C5 North Area Below Turbine (El. 2033'-0") C4 Unit 1 Auxiliary Transformers XMA02, XMA01B ø B, and XMA01C ø C, D2 Main Transformers (3) XMA01A ø A F2 Station Service Transformers, XPB03 and XPB04 H5 Condenser Pit A6 South Area Below Turbine (El. 2000'-0") D7 South Area Below Turbine (El. 2033'-0") A7 Hydrogen Seal Oil Unit D2 LR-CW-KC-M-22KC02 Auxiliary Boiler Room A2 The staff requests that the applicant verify whether the fire water systems/components listed above are in the scope of license renewal in accordance with 10 CFR 54.4(a) and whether they are subject to an AMR in accordance with 10 CFR 54.21(a)(1). If they are excluded from the scope of license renewal and are not subject to an AMR, the staff requests that the applicant provide justification for the exclusion.
RAI 2.3.3.20-2
Tables 2.3.3-20 and 3.3.2-20 of the LRA do not include the following fire protection systems and components:
- fire hose connections and hose racks
- diesel fire pump heat exchange (bonnet, shell, and tubes)
- floor drains and curbs for fire-fighting water
- dikes for oil spill confinement
- sprinkler system water curtain in the auxiliary building equipment hatchway
- diesel generator room roof heat vents The staff requests that the applicant verify whether the fire protection systems and components listed above are in the scope of license renewal in accordance with 10 CFR 54.4(a) and whether they are subject to an AMR in accordance with 10 CFR 54.21(a)(1). If they are excluded from the scope of license renewal and are not subject to an AMR, the staff requests that the applicant provide justification for the exclusion. RAI 2.3.3.20-3
By letter dated August 29, 2011, Union Electric Company submitted a license amendment to transition the Callaway, existing fire protection program to a risk-informed, performance-based program based on National Fire Protection Association Standard 805 (NFPA 805), "Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants," 2001 Edition, in accordance with 10 CFR 50.48(c).
The staff requests that the applicant provide a gap analysis of LRA Tables 2.3.3-20 and 3.3.2-20 identifying differences between the existing and NFPA 805 post-transition changes. Summarize the results and the impacts of these gaps on the fire protection program described in LRA Tables 2.3.3-20 and 3.3.2-20, as the basis for transitioning to the NFPA 805 nuclear safety capabilities. Also list the fire protection systems and components including structural fire barriers, (e.g., fire walls and slabs, fire doors, fire barrier penetration seals, fire dampers, fire barrier coatings/wraps, equipment/personnel hatchways and plugs, metal siding), that will be added or removed based on the NFPA 805 transition in the scope of license renewal in accordance with 10 CFR 54.4(a) and whether they are subject to an AMR in accordance with 10 CFR 54.21(a)(1).
2.3.3.22 Standby Diesel Generator Engine System
RAI 2.3.3.22-1 License renewal boundary drawings LR-CW-M-22KJ02 and LR-CW-M-22KJ05, locations F-8 and H-8, show turbocharger casings that are in scope for 10 CFR 54.4(a)(1) which are not listed in Table 2.3.3-22 as components subject to an AMR.
The staff requests that the applicant justify why the turbocharger casing component type was not included in LRA Table 2.3.3-22.
RAI 2.3.3.22-2
License renewal boundary drawings LR-CW-M-22KJ02 and LR-CW-M-22KJ05, location G-7, show an air pressure supply manifold housing that is in scope for 10 CFR 54.4(a)(1) which is not listed in Table 2.3.3-22 as a component subject to an AMR.
The staff requests that the applicant justify why the air supply manifold housing component type was not included in LRA Table 2.3.3-22.
RAI 2.3.3.22-3
License renewal boundary drawings LR-CW-M-22KJ02 and LR-CW-M-22KJ05, locations A-6 and C-6, show pulsation dampers that are in scope for 10 CFR 54.4(a)(2) which are not listed in LRA Table 2.3.3-22 as components subject to an AMR.
The staff requests that the applicant justify why the pulsation damper component type was not included in LRA Table 2.3.3-22. RAI 2.3.3.22-4
License renewal boundary drawings LR-CW-M-22KJ03 and LR-CW-M-22KJ06, location F-4, show lube oil ejector casings that are in scope for 10 CFR 54.4(a)(1) which are not listed in LRA Table 2.3.3-22 as component types subject to an AMR.
The staff requests that the applicant justify why the ejector casing component type was not included in LRA Table 2.3.3-22.
RAI 2.3.3.22-5 License renewal boundary drawings LR-CW-M-22KJ03 and LR-CW-M-22KJ06, location F-5, show oil separator casings that are in scope for 10 CFR 54.4 (a)(1) which are not listed in LRA Table 2.3.3-22 as components subject to an AMR.
The staff requests that the applicant justify why the oil separator casing component type was not included in LRA Table 2.3.3-22.
RAI 2.3.3.22-6
License renewal boundary drawings LR-CW-M-22KJ02 and LR-CW-M-22KJ05, location G-3, show four "XJ" components that are in scope for 10 CFR 54.4(a)(1) that cannot be identified and reviewed. It is uncertain what these components are, what function(s) they perform, and if they are listed in LRA Table 2.3.3-22 as component types subject to an AMR.
The staff requests that the applicant clarify what the components are and their functions, and justify why the component type was not included in LRA Table 2.3.3-22.
2.3.3.27 Floor and Equipment Drainage System
RAI 2.3.3.27-1
License renewal boundary drawing LR-CW-LF-M-22LF01, location H-4, shows A10-XND-4" piping within the scope of license renewal for 10 CFR 54.4(a)(2). However, the continuation from license renewal boundary drawing LR-CW-LF-M-22LF02, location A-4, depicts the piping within the scope of license renewal for 10 CFR 54.4(a)(3).
The staff requests the applicant to provide additional information to clarify the scoping classification of pipe section A10-XND-4".
2.3.4 Steam and Power Conversion Systems
RAI 2.3.4-1 LRA Section 2.1 describes the applicant's scoping methodology, which specifies how systems or components were determined to be included in scope of license renewal. The staff confirms the inclusion of all components subject to AMR by reviewing the results of the screening of components within the license renewal boundary. For the drawing locations identified in the table below, the continuation of piping in scope for license renewal could not be located.
License Renewal Boundary Drawing Number & Location Continuation IssueSection 2.3.4.2 Main Steam Supply System LR-CW-AB-M-22AB02, location B-6 "F"-HBD-2 & I"-HBD-2, a continuation is not provided Section 2.3.4.4 Steam Generator Blowdown System LR-CW-BM-M-22BM01, locations B-5, C-5, E-5 & G-5 Downstream continuation of valves V039, V028, V017 & V006 continued to drawing M- 22RM01. Drawing M- 22RM01 was not provided for review.
Section 2.3.4.5, Auxiliary Feedwater System LR-CW-AL-M-22FC02, location D-4 Downstream of valve V998 a continuation was not provided.
The staff requests the applicant to provide sufficient information to locate the license renewal boundary. If the continuation cannot be shown on license renewal boundary drawings, then provide additional information describing the extent of the scoping boundary and verify whether or not there are additional AMR component types between the continuation and the termination of the scoping boundary. If the scoping classification of a section of the piping changes over the continuation, provide additional information to clarify the change in scoping classification.
2.3.4.2 Main Steam Supply System
RAI 2.3.4.2-1
License renewal boundary drawing LR-CW-AE-M-22AB02 depicts main steam piping in the auxiliary building highlighted in green, which indicates that the piping is within scope of license renewal for 10 CFR 54.4(a)(1). However, at locations C-2, D-2, F-2, and G-2, four sections of main steam piping exit the auxiliary building and continue into the turbine building. As described by Note 1 on license renewal boundary drawing LR-CW-AE-M-22AB02, the scoping classification change and seismic portion of the main steam piping occurs at the first weld within the turbine building wall. Nonsafety-related components were not identified within scope of license renewal for 10 CFR 54.4(a)(2) inside the turbine building on the license renewal boundary drawing, as required by the applicant's scoping methodology described in LRA Section 2.1.2.2.
The staff requests the applicant to provide justification for excluding the nonsafety-related components in the turbine building, which may be in proximity of the (a)(1) main steam piping, from scope of license renewal for 10 CFR 54.4(a)(2). 2.3.4.3 Main Feedwater System RAI 2.3.4.3-1
License renewal boundary drawing LR-CW-AE-M-22AE01 depicts solenoid valves, which are highlighted in green, at locations A-7, B-7, C-7, D-7, E-7, F-7, G-7, and H-7. These solenoid valves are accompanied on the license renewal boundary drawing with license renewal Note 1, which indicates that these valves are within scope of license renewal under 10 CFR 54.4(a)(1). However, there were not any nonsafety-related components, either directly attached or within spatial proximity of the solenoid valves, identified on license renewal boundary drawing LR-CW-AE-M-22AE01. The exclusion of these nonsafety-related components from scope of license renewal appears to be inconsistent with the scoping methodology described in LRA Section 2.1.2.2. The staff requests the applicant to provide justification for excluding the nonsafety-related components near the solenoid valves from scope of license renewal for 10 CFR 54.4(a)(2) on license renewal boundary drawing LR-CW-AE-M-22AE01. 2.5 Scoping and Screening Results: Electrical and Instrumentation and Control Systems RAI 2.5-1 In the license renewal application, the applicant described the station blackout recovery paths for license renewal. As the licensee did not specifically exclude the associated control circuits and structures for the switchyard circuit breakers, it is assumed that these components are included in the scope of license renewal. In accordance with Title 10 of the Code of Federal Regulations (10 CFR) Section 54.4(a)(3) and License Renewal Sections 2.1.3.1.3 and 2.5.2.1.1 of the Standard Review Plan, the control circuits and structures associated with the circuit breaker should be in the scope of license renewal. Please confirm that these components are within the scope of license renewal.