MONTHYEARULNRC-06853, Submittal of 2023 Fitness for Duty Performance Data Per Per 10 CFR 26.7172024-01-29029 January 2024 Submittal of 2023 Fitness for Duty Performance Data Per Per 10 CFR 26.717 IR 05000483/20230042024-01-19019 January 2024 Integrated Inspection Report 05000483/2023004 ML24008A0552024-01-19019 January 2024 Acceptance of Requested Licensing Action - Proposed Alternative to the Requirements of the ASME Code (EPID L-2023-LLR- 0061) ML23353A1712024-01-18018 January 2024 Issuance of Amendment No. 237 to Clarify Support System Requirements for the Residual Heat Removal System and Control Room Air Conditioning System Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 ML23317A0012024-01-12012 January 2024 Audit Summary Regarding LAR to Clarify Support System Requirements for the Residual Heat Removal and Control Room Air Conditioning System Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 ML23347A1212024-01-11011 January 2024 Issuance of Amendment No. 236 to Adopt TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube Volume Values to Licensee Control EPID L-2023-LLA-0046) ML24011A1492024-01-11011 January 2024 Notification of Post-Approval Site Inspection for License Renewal and Request for Information (05000483/2024011) ULNRC-06847, Supplement to Relief Request from Requirements of ASME BPV Code, Section XI, Subsection Iwl Regarding Examination and Testing of the Unbonded Post-Tensioning System (Relief Request C3R-01)2023-12-21021 December 2023 Supplement to Relief Request from Requirements of ASME BPV Code, Section XI, Subsection Iwl Regarding Examination and Testing of the Unbonded Post-Tensioning System (Relief Request C3R-01) ULNRC-06849, License Renewal Resolution for Commitments 34 and 35 Perform Evaluation of Crack Initiation and Propagation in Steam Generator Divider Plate and Tube-To-Tubesheet Welds2023-12-20020 December 2023 License Renewal Resolution for Commitments 34 and 35 Perform Evaluation of Crack Initiation and Propagation in Steam Generator Divider Plate and Tube-To-Tubesheet Welds ML23346A0392023-12-14014 December 2023 Supplemental Information Needed for Acceptance of Requested Licensing Action Request for Relief from Requirements of ASME Code, Section Xl, Examination and Testing Unbonded Post-Tensioning System ULNRC-06844, Request for Exemption from Specific Requirements in 2023 Security Rule, Enhanced Weapons, Firearms Background Checks, and Security Event Notification2023-12-0707 December 2023 Request for Exemption from Specific Requirements in 2023 Security Rule, Enhanced Weapons, Firearms Background Checks, and Security Event Notification 05000483/LER-2023-001, Submittal of LER 2023-001-00 for Callaway, Unit 1, Inoperable Instrument Tunnel Sump Level Indication Resulted in Condition Prohibited by Technical Specifications2023-11-29029 November 2023 Submittal of LER 2023-001-00 for Callaway, Unit 1, Inoperable Instrument Tunnel Sump Level Indication Resulted in Condition Prohibited by Technical Specifications ULNRC-06827, Supplement to License Amendment Request Regarding Support System Requirements for Residual Heat Removal and Control Room Air Conditioning Systems Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 (LDCN 22-0029)2023-11-20020 November 2023 Supplement to License Amendment Request Regarding Support System Requirements for Residual Heat Removal and Control Room Air Conditioning Systems Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 (LDCN 22-0029) IR 05000483/20230102023-11-15015 November 2023 NRC License Renewal Phase 1 Inspection Report 05000483 2023010 IR 05000483/20233012023-11-0909 November 2023 NRC Examination Report 05000483-2023301 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV ML23297A2502023-11-0606 November 2023 Individual Notice of Consideration of Issuance of Amendment to Renewed Facility Operating License, Proposed No Significant Hazards Consideration Determination and Opportunity for a Hearing (EPID L-2022-LLA-0176) - Letter IR 05000483/20240122023-10-24024 October 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection (05000483/2024012) ML23293A2652023-10-24024 October 2023 3rd Quarter 2023 Integrated Inspection Report ML23240A3692023-10-0505 October 2023 Issuance of Amendment No. 235 to Revise Technical Specifications to Use of Framatome Gaia Fuel (EPID L-2022-LLA-0150) (Non-Proprietary) ML23234A1522023-10-0505 October 2023 Exemption from the Requirements of 10 CFR Part 50, Section 50.46, and Appendix K Regarding Use of M5 Cladding Material (EPID L-2022-LLE-0030) (Letter) ML23305A0942023-10-0202 October 2023 10-CW-2023-09 Post-Exam Submittal ML23270B9662023-09-27027 September 2023 10 CFR 50.55a(z)(I) Request for Relief from ASME OM Code Pump and Valve Testing Requirements for Fifth 120-Month Inservice Testing Interval ML23228A0252023-09-25025 September 2023 Issuance of Amendment No. 234 to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate Test Frequencies ML23261C3852023-09-25025 September 2023 Safety Evaluation for Operating Quality Assurance Manual Revision 36A ML23166B0882023-09-20020 September 2023 Issuance of Amendment No. 233 for Adoption of Alternative Source Term and Revision of Technical Specifications ML23206A1992023-09-15015 September 2023 Regulatory Audit Summary Regarding License Amendment and Regulatory Exemptions Request for Fuel Transition to Framatome Gaia Fuel (Epids L-2022-LLA-0150 and L-2022-LLE-0030) IR 05000483/20234012023-09-13013 September 2023 NRC Security Baseline Inspection Report 05000483/2023401 ML23240A7572023-08-31031 August 2023 NRC Initial Operator Licensing Examination Approval 05000483/2023301 IR 05000483/20230052023-08-23023 August 2023 Updated Inspection Plan for Callaway Nuclear Power Plant, Unit 1 (Report 05000483/2023005) - Mid Cycle Letter 2023 ULNRC-06824, Response to Request for Additional Information Regarding Operating Quality Assurance Manual (Oqam) Revision 36A2023-08-17017 August 2023 Response to Request for Additional Information Regarding Operating Quality Assurance Manual (Oqam) Revision 36A ML23219A1392023-08-15015 August 2023 Request for Withholding Information from Public Disclosure ULNRC-06830, Transmittal of Updated Technical Specification Markup and Clean Pages for License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak2023-08-15015 August 2023 Transmittal of Updated Technical Specification Markup and Clean Pages for License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak ML23215A1972023-08-0303 August 2023 Supplement to License Amendment and Exemption Request Regarding Use of Framatome Gaia Fuel (LDCN 22-0002) ULNRC-06223, Minor Correction to License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate Test Frequencies (LDCN 2020-0004)2023-07-25025 July 2023 Minor Correction to License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate Test Frequencies (LDCN 2020-0004) ULNRC-06799, Submittal of Licensee Event Report 2022-003-01, Class 1E Electrical Air Conditioning System Thermal Expansion Valve Failure Resulted in Condition Prohibited by Technical Specifications2023-07-13013 July 2023 Submittal of Licensee Event Report 2022-003-01, Class 1E Electrical Air Conditioning System Thermal Expansion Valve Failure Resulted in Condition Prohibited by Technical Specifications IR 05000483/20230022023-07-10010 July 2023 Integrated Inspection Report 05000483/2023002 ML23174A1272023-06-23023 June 2023 Cw FFD Document Request List 2023 ML23171A9942023-06-22022 June 2023 Acceptance of Request for Approval of Operating Quality Assurance Manual Revision 36a ULNRC-06821, Post-Audit Follow-Up Information in Support of Callaway'S License Amendment Request and Proposed Exemption to Allow Use of Framatome Gaia Fuel (LDCN 22-0002) (EPID L-2022-LLA-0150 and EPID L-2022-LLE-00301)2023-06-21021 June 2023 Post-Audit Follow-Up Information in Support of Callaway'S License Amendment Request and Proposed Exemption to Allow Use of Framatome Gaia Fuel (LDCN 22-0002) (EPID L-2022-LLA-0150 and EPID L-2022-LLE-00301) IR 05000483/20230112023-06-15015 June 2023 Comprehensive Engineering Team Inspection (CETI) Inspection Report 05000483/2023011 ULNRC-06822, Additional Information Regarding Request for NRC Approval of Operating Quality Assurance Manual (Oqam) Revision 36a2023-06-14014 June 2023 Additional Information Regarding Request for NRC Approval of Operating Quality Assurance Manual (Oqam) Revision 36a ML23158A1462023-06-13013 June 2023 Notification of Post-Approval Site Inspection for License Renewal and Request for Information Inspection (05000483/2023010) ULNRC-06815, Request for NRC Approval of Operating Quality Assurance Manual, Revision 36a2023-06-0505 June 2023 Request for NRC Approval of Operating Quality Assurance Manual, Revision 36a ULNRC-06818, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate .2023-06-0505 June 2023 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 5.5.16, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate . ML23093A0952023-05-10010 May 2023 Issuance of Amendment No. 232 Regarding Technical Specification Changes for Spent Fuel Storage ULNRC-06816, Withdrawal of Previously Submitted Enclosures Regarding License Amendment Request for Adoption of Alternative Source Term and Revision of Technical Specifications (LDCN 21-0015)2023-05-0909 May 2023 Withdrawal of Previously Submitted Enclosures Regarding License Amendment Request for Adoption of Alternative Source Term and Revision of Technical Specifications (LDCN 21-0015) ML23129A7942023-05-0909 May 2023 Post-Audit Supplement to License Amendment Request and Exemption to Allow Use of Framatome Gaia Fuel (LDCN 22-0002) (Iepid L-2022-LLA-0150 and EPID L-2022-LLE-0030) ML23122A3172023-05-0808 May 2023 Review of the Spring 2022 Steam Generator Tube Inservice Inspections ML23118A3492023-05-0808 May 2023 Request for Withholding Information from Public Disclosure 2024-01-29
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML23200A2982023-07-19019 July 2023 NRR E-mail Capture - Callaway Plant, Unit 1 - Final Request for Additional Information (RAI) - Request for Approval of Oqam, Revision 36a - EPID L-2023-LLQ-0000 ML23174A1272023-06-23023 June 2023 Cw FFD Document Request List 2023 ML23158A1462023-06-13013 June 2023 Notification of Post-Approval Site Inspection for License Renewal and Request for Information Inspection (05000483/2023010) ML23163A1572023-06-0606 June 2023 In-service Inspection Request for Information ML23096A0072023-04-0505 April 2023 NRR E-mail Capture - Final Request for Additional Information - Callaway Plant, Unit 1 - License Amendment Request to Revise TS 5.5.16 for Permanent Extension of Integrated Leak Rate Testing - EPID L-2022-LLA-0165 ML23080A1382023-03-21021 March 2023 Notification of Inspection (NRC Inspection Report 05000483/2023003) and Request for Information ML23073A0262023-03-13013 March 2023 NRR E-mail Capture - Final - Request for Additional Information - Callaway Plant, Unit 1 - SG Inspection Report Review - EPID L-2022-LRO-0143 ML23037A7092023-02-0606 February 2023 April 2023 Emergency Preparedness Exercise Inspection - Request for Information ML23026A0212023-01-24024 January 2023 NRR E-mail Capture - Final - Request for Additional Information - Callaway Plant, Unit 1 - LAR for Proposed Changes to TS for SFP - ML22287A0952022-10-14014 October 2022 NRR E-mail Capture - Final - Request for Additional Information - Callaway Plant, Unit 1 - License Amendment Request for Adoption of Alternate Source Term and Revision of Technical Specifications - EPID L-2021-LLA-0177 ML22269A4312022-09-26026 September 2022 November 2022 Emergency Preparedness Program Inspection - Request for Information ML22173A0562022-06-22022 June 2022 Information Request, Security IR 2022402 ML22167A0252022-06-15015 June 2022 NRR E-mail Capture - Final - Request for Additional Information - Callaway Plant, Unit 1 - LAR for Proposed Revision to Radiological Emergency Response Plan Regarding Response & Notification Goals - EPID L-2022-LLA-0024 ML22157A0572022-06-0606 June 2022 Notification of NRC Design Bases Assurance Inspection (Programs) (05000483/2022013) and Request for Information ML22154A0122022-06-0202 June 2022 NRR E-mail Capture - Final - Request for Additional Information - Callaway Plant, Unit 1 - License Amendment Request for Adoption of Alternate Source Term and Revision of Technical Specifications - EPID L-2021-LLA-0177 ML22151A0512022-05-27027 May 2022 NRR E-mail Capture - Final - Request for Additional Information - Columbia Generating Station - LAR to Change TS 3.4.11 - Reactor Coolant System Pressure and Temperature Limits - EPID L-2021-LLA-0191 ML22137A0292022-05-16016 May 2022 NRR E-mail Capture - Draft - Request for Additional Information - Callaway Plant, Unit 1 - License Amendment Request for Adoption of Alternate Source Term and Revision of Technical Specifications - EPID L-2021-LLA-0177 ML22096A0232022-04-0505 April 2022 NRR E-mail Capture - Callaway Plant - Final RAIs - License Amendment and Regulatory Exemptions for a Risk-Informed Approach to Address Generic Safety Issue - 191 and Respond to GL 2004-02 (EPIDs L-2021-LLA-0059 and L-2021-LLE-0021) ML21336A6392021-12-0202 December 2021 .05 Sec Doc Request ML21319A0062021-11-30030 November 2021 Supplemental Information Needed for Acceptance of Requested Licensing Actions License Amendment Request for Adoption of Alternate Source Term and Revision of Technical Specifications ML21258A0382021-09-14014 September 2021 NRR E-mail Capture - Final - Request for Additional Information - Callaway, Unit 1 - LAR to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors- EPID L-2020-LLA-023 ML21159A2352021-06-17017 June 2021 Notification of NRC Triennial Heat Exchanger/Heat Sink Performance Inspection (05000483/2021003) and Request for Information ML21130A5882021-05-11011 May 2021 Supplemental Information Needed for Acceptance of Requested Licensing Actions to Adopt a Risk-Informed Approach to Address GSI-191 and Respond to Generic Letter 2004 02 ML21088A3872021-03-30030 March 2021 Notification of Evaluations of Changes, Tests, and Experiments Inspection (Inspection Report 05000483/2021002) and Request for Information ML21007A1622021-01-0606 January 2021 NRR E-mail Capture - Final - Request for Additional Information - (COVID-19) Callaway Plant, Unit 1 - Additional Request for Exemption from Specific Requirements of 10 CFR Part 26, Fitness for Duty Programs - EPID L-2021-LLE-0242 ML20203M3682020-07-21021 July 2020 NRR E-mail Capture - Draft Request for Additional Information - Callaway Plant, Unit 1 - License Amendment Request - Revision to Technical Specification (TS) 5.3.1 and Deletion of TS 5.3.1.1 and 5.3.1.2 - EPID L-2020-LLA-0046 ML20162A1882020-06-10010 June 2020 Request for Supporting Information for the Callaway SPRA Audit Review - Draft Supplement ML20280A5442020-03-25025 March 2020 Cwy 2020 PIR Request for Information ML20064B6582020-02-27027 February 2020 Second, Third, and Fourth Request for Information for Callaway Dba Teams Inspection 2020011 ML19317E6332019-11-13013 November 2019 Request for Supporting Information for the Callaway SPRA Audit Review ML19107A5152019-04-11011 April 2019 Cwy 2019410 RFI Cyber Security Gap ML19078A2932019-03-18018 March 2019 Notification of an NRC Triennial Fire Protection Baseline Inspection (NRC Inspection Report 05000483/2019010) and Request for Information ML19023A2032019-01-22022 January 2019 Notification of NRC Triennial Heat Sink Performance Inspection (05000483/2019001) and Request for Information ML19009A3442019-01-0909 January 2019 NRR E-mail Capture - Formal Release of RAIs Ref: Callaway Plant Class 1E LAR, L-2018-LLA-0062 ML18355A4882018-12-20020 December 2018 NRR E-mail Capture - Formal Release of RAI Ref: Callaway Plant EAL Changes, L-2018-LLA-0239 ML18331A2052018-11-27027 November 2018 NRR E-mail Capture - Formal Release of RAIs Ref: Callaway Relief Request EPID L-2018-LLR-0051 ML18025B4672018-01-24024 January 2018 NRR E-mail Capture - Request for Extension of Due Date for RAI Response ML17304B1912017-10-31031 October 2017 NRR E-mail Capture - Requests for Additional Information Concerning Callaway License Amendment - Thermal Overload Protection ML17142A1352017-05-19019 May 2017 Notification of NRC Design Bases Assurance Inspection (05000483/2017007) and Initial Request for Information ML17115A0622017-04-25025 April 2017 NRR E-mail Capture - Requests for Additional Information -- Callaway Plant, Unit 1, Technical Specification 5.6.5, Core Operating Limits Report CAC MF8463 ML17038A2292017-02-0707 February 2017 NRR E-mail Capture - RAI Formal Release for Callaway SG Tube Inspection Report, MF8474 ML16111B3222016-04-20020 April 2016 Notification of Evaluations of Changes, Tests, and Experiments, and Permanent Plant Modifications Inspection (05000483/2016007) and Request for Information ML15316A1532015-11-12012 November 2015 Request for Additional Information Email, Relief Request 13R-11 (Pressurizer Welds) from Code Case N-460 Requirements, Third 10-Year Inservice Inspection Interval ML15096A0942015-04-0606 April 2015 Notification of Inspection (NRC Inspection Report 05000483/2015003) and Request for Information ML14353A1172014-12-22022 December 2014 Request for Additional Information, Round 3, License Amendment Request to Revise Final Safety Analysis Report Standard Plant Section 3.6 for High Density Polyethylene (Hdpe) Crack Exclusion ML14294A7752014-10-28028 October 2014 Request for Additional Information, Round 2, License Amendment Request to Revise Final Safety Analysis Report Standard Plant Section 3.6 for High Density Polyethylene (Hdpe) Crack Exclusion ML14203A0632014-07-25025 July 2014 Request for Additional Information, Relief Request I3R-17, Proposed Alternative to ASME Code, Section XI Requirements, Which Extends Rv ISI Frequency from 10 to 20 Years, Third 10-Year ISI Interval ML14178A8232014-07-0101 July 2014 Request for Additional Information, License Amendment Request to Revise Final Safety Analysis Report- Standard Plant Section 3.6 for High Density Polyethylene (Hdpe) Crack Exclusion ULNRC-06117, Callaway Plant, Unit 1, License Revewal Application, Request for Additional Information (RAI) Set 31 Responses2014-04-24024 April 2014 Callaway Plant, Unit 1, License Revewal Application, Request for Additional Information (RAI) Set 31 Responses ML14114A1102014-04-24024 April 2014 License Revewal Application, Request for Additional Information (RAI) Set 31 Responses 2023-07-19
[Table view] |
See also: IR 05000483/2021003
Text
June 17, 2021
Mr. Fadi Diya, Senior Vice President
and Chief Nuclear Officer
Ameren Missouri
Callaway Plant
8315 County Road 459
Steedman, MO 65077
SUBJECT: CALLAWAY PLANT - NOTIFICATION OF NRC TRIENNIAL HEAT
EXCHANGER/HEAT SINK PERFORMANCE INSPECTION (05000483/2021003)
AND REQUEST FOR INFORMATION
Dear Mr. Diya:
The purpose of this letter is to notify you that U.S. Nuclear Regulatory Commission (NRC) staff
will conduct the triennial portion of the heat exchanger/heat sink performance inspection at your
Callaway Plant from September 13 - 17, 2021. The onsite phase of the inspection will consist
of two reactor inspectors from the NRCs Region IV office for one week. The inspection will be
conducted in accordance with NRC Inspection Procedure (IP) 71111, Attachment 07, Heat
Exchanger/Sink Performance, dated October 21, 2020.
The objectives of the inspection are to verify that: 1) any potential heat exchanger deficiencies
which could mask degraded performance are identified, 2) any potential common-cause heat
sink performance problems that have the potential to increase risk are identified, and 3) the
licensee has adequately identified and resolved heat sink performance problems that could
result in initiating events or affect multiple heat exchangers in mitigating systems and thereby
increase risk.
To minimize the impact the inspection on the site and to ensure an efficient inspection, we have
enclosed a request for documents needed for the inspection. It is important that these requests
are fulfilled as completely and accurately as possible to minimize any additional requests during
the preparation week or during the onsite inspection. The documents have been divided into
three groups.
x The first group lists information necessary for our initial inspection scoping activities.
This information should be available to the lead inspector no later than August 9, 2021.
As soon as practicable, the lead inspector will communicate the initial selected set of 2-4
risk significant or safety-related heat exchangers and/or heat sinks.
F. Diya 2
x The second group of documents requested includes those items needed to support our
in-office preparation activities. This set of documents, including calculations associated
with the selected heat exchangers and/or heat sinks, should be available no later than
August 30, 2021. This information should be separated for each inspection sample,
especially if provided electronically. Note that the inspectors may identify additional
information needed to support the inspection during this week and will communicate
those requests as soon as practicable.
x The third group of documents requested includes the additional documentation identified
during in-office preparation activities as well as other resource requests necessary to
support our onsite inspection activities. The additional information or resources should
be available throughout the week of onsite inspection activities beginning on September
13, 2021.
All requested documents are to be for the time period from the onsite inspection period back to
the last triennial heat exchanger/heat sink performance inspection. If nothing addressing a
request was performed in that time period, then the request applies to the last applicable
document. If a request does not apply for any heat exchanger/heat sink sample, no response is
necessary. Include all attachments to the requests, especially corrective action program
documents.
We have discussed the schedule for this inspection with your staff and understand that our
regulatory contact for this inspection will be Randy Pohlman of your Regulatory Affairs
organization. If there are any questions about this inspection or the documents requested,
please contact the lead inspector, Jonathan Braisted, by telephone at 817-200-1469 or by e-
mail at Jonathan.Braisted@nrc.gov.
PAPERWORK REDUCTION ACT STATEMENT
This letter contains mandatory information collections that are subject to the Paperwork
Reduction Act of 1995 (44 U.S.C. 3501 et seq.). The Office of Management and Budget (OMB)
approved these information collections (approval number 3150-0011). Send comments
regarding this information collection to the Information Services Branch, Office of the Chief
Information Officer, Mail Stop: T6 A10M, U.S. Nuclear Regulatory Commission, Washington,
DC 20555-0001, or by e-mail to Infocollects.Resource@nrc.gov, and to the Desk Officer, Office
of Information and Regulatory Affairs, NEOB-10202, (3150-0011) Office of Management and
Budget, Washington, DC 20503.
PUBLIC PROTECTION NOTIFICATION
The NRC may not conduct nor sponsor, and a person is not required to respond to, a request
for information or an information collection requirement unless the requesting document
displays a currently valid OMB control number.
F. Diya 3
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its
enclosure will be available electronically for public inspection in the NRC Public Document
Room or from the Publicly Available Records (PARS) component of NRC's document system
(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-
rm/adams.html (the Public Electronic Reading Room).
Sincerely,
Digitally signed by
David L. David L. Proulx
Date: 2021.06.17
Proulx 10:36:59 -05'00'
David L. Proulx, Chief (Acting)
Engineering Branch 1
Division of Reactor Safety
Docket No.: 50-483
License No.: NPF-30
Enclosure: Triennial Heat Exchanger/Heat Sink
Performance Inspection Request
for Information
cc w/ encl: Distribution via LISTSERV
ML21159A235
SUNSI Review ADAMS: Non-Publicly Available Non-Sensitive Keyword:NRC-002
By: JDB Yes No Publicly Available Sensitive
OFFICE DRS/EB1 DRS/EB1
NAME JBraisted DProulx
SIGNATURE JDB DLP
DATE 6/14/2021 6/9/2021
Request for Information
Triennial Heat Exchanger/Heat Sink Performance Inspection
Callaway Plant
Inspection Report: 05000483/2021003
Inspection Dates: September 13 - 17, 2021
Inspection Procedure: IP 71111.07, Triennial Heat Exchanger/Sink Performance
Inspector(s): Jonathan Braisted, Reactor Inspector (Lead)
Dustin Reinert, Reactor Inspector
I. Information Requested by August 9, 2021:
1. Heat exchanger/heat sink program documents, including NRC Generic Letter (GL) 89-13
or aging management programs
2. Responses to GL 89-13
3. Different requirements and/or commitments related to GL 89-13 or aging management
programs
4. Heat exchanger/heat sink program self-assessments
5. Updated final safety analysis report (UFSAR), technical specifications (TSs), and TS
bases
6. List of heat exchangers in order of risk significance
7. List of corrective action program documents related to heat exchangers/heat sinks
II. Information Requested by August 30, 2021:
1. For the selected heat exchangers that are directly cooled by the service water system:
a. Performance testing (or equivalent method) documentation, including procedure
b. Periodic flow testing and/or balancing documentation, including procedure
c. Inspection (visual, eddy-current, etc.) and cleaning documentation, including
procedure
d. Tube plugging map
e. Biotic fouling and macrofouling treatment documentation, including procedure
f. Relevant design basis calculations
5
enclosure
g. Applicable system health report and design basis document
h. Relevant system piping and instrumentation diagrams
i. Heat exchanger design specification and heat exchanger data sheet
j. Heat exchanger preventative maintenance schedule
2. For the selected heat exchangers that are directly cooled by a closed loop cooling water
system:
a. Periodic flow testing and/or balancing documentation, including procedure
b. Inspection (visual, eddy-current, etc.) and cleaning documentation, including
procedure
c. Tube plugging map
d. Evaluation of potential for water hammer
e. Chemical treatment documentation, including procedure
f. Relevant design basis calculations
g. Applicable system health report and design basis document
h. Relevant system piping and instrumentation diagrams
i. Heat exchanger design specification and heat exchanger data sheet
j. Heat exchanger preventive maintenance schedule
3. For the selected ultimate heat sink (UHS):
a. Forced draft cooling tower or spray pond UHS:
i. Calculations demonstrating sufficient reservoir capacity
ii. Documentation of periodic monitoring and trending of sediment, including
procedures
iii. Performance monitoring documentation of heat transfer capability,
including procedures
iv. Performance monitoring documentation of UHS structural integrity,
including procedures
6
enclosure
b. Operation of the service water system (SWS) and UHS:
i. List of modifications to the SWS and UHS
ii. Procedures for a loss of SWS or UHS
iii. Biotic fouling and macrofouling treatment documentation, including
procedures
iv. Chemistry monitoring documentation, including procedures
v. Evaluation of strong-pump to weak-pump interactions
c. Performance testing of the SWS and UHS:
i. Inservice testing documentation of SWS/UHS pumps, valves, and fans,
including procedures
ii. Service water flow balance test documentation, including procedures
iii. Diagnostic testing documentation for valves that interface with safety-
related service water and nonsafety-related or nonseismic piping systems
iv. Performance testing documentation of risk-significant nonsafety-related
functions (or alignments), including procedures
d. Service water and/or closed cooling water system:
i. Inaccessible pipe testing, inspection (visual, ultrasonic, etc.), and/or
monitoring documentation, including procedure
ii. Evaluations of active thru wall pipe leaks
iii. Corrective action documents related to thru wall pipe leakage, including
trend evaluations
iv. For closed cooling water systems, trend data on make-up to the system
v. Protective coatings inspection documentation, including procedure
vi. For deep draft vertical pumps, diagnostic testing (or equivalent method)
documentation, including procedures
e. Service water intake structure (SWIS):
i. Preventive maintenance schedule for traveling screens and strainers
ii. Corrective action documents related to traveling screens, strainers, trash
racks, etc.
iii. SWS/UHS normal and abnormal operating procedures
7
enclosure
iv. SWIS inspection documentation regarding structural integrity and silting,
including procedure
v. Service water pump bay water level instrument documentation related to
setpoints and calibration, including procedures
vi. SWS/UHS water temperature instrumentation documentation related to
setpoints and calibration, including procedures
vii. Evaluations of potential for frazil ice formation
viii. For underwater weir walls, evaluations of potential silt introduction
4. UHS Containment Device or Dam
a. For an above-ground UHS encapsulated by embankments, weirs or excavated
side slopes:
i. Weir or embankment design documentation
ii. Licensee or third-party dam inspection documentation used to monitor the
integrity or performance of the heat sink
iii. Calculations for sufficient reservoir capacity
iv. Significant debris or sediment build-up monitoring documentation in the
UHS
v. Corrective action program documents related to debris, debris, structural
integrity, seepage, settlement, rip rap, etc.
b. For underwater UHS weirs, structures, or excavations:
i. Underwater weirs, structures, or excavations design documentation
ii. Settlement or movement related to structural integrity and/or capacity
monitoring documentation, including procedures
iii. Sediment intrusion monitoring documentation, including procedures
iv. Calculations for sufficient capacity
v. Corrective action program documents related to settlement, movement,
structural integrity, sediment, etc.
8
enclosure
III. Additional Requests During Onsite Inspection Activities
1. Supplemental requests identified during in-office preparation activities
2. Additional requests identified during onsite inspection activities
3. Discussions with relevant subject matter experts
4. Walkdowns of selected heat exchanger/heat sink samples
5. Corrective action program documents generated as a result of this inspection
If the information requested above will not be available, please contact Jonathan Braisted as
soon as possible.
Inspector Contact Information:
Jonathan Braisted (Lead) Dustin Reinert
Reactor Inspector Reactor Inspector
817-200-1469 817-200-1534
Jonathan.Braisted@nrc.gov Dustin.Reinert@nrc.gov
Mailing Address:
U.S. NRC, Region IV
Attn: Jonathan Braisted
1600 East Lamar Blvd.
Arlington, TX 76011-4511
9
enclosure