Schedule Correction for the Review of the Turkey Point Nuclear Generating Unit Nos. 3 and 4 Subsequent License Renewal Application (EPID Nos. L-2018-LNE-0001/L-2018-RNW-0002)
ML19127A070
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 05/09/2019
From: Eric Oesterle
NRC/NRR/DMLR/MRPB
To: Nazar M
Florida Power & Light Co
James L, NRR-DMLR 415-3306
References
EPID L-2018-LNE-0001, EPID L-2018-RNW-0002
Download: ML19127A070 (5)


Text

May 9, 2019 Mr. Mano Nazar President and Chief Nuclear Officer Nuclear Division Florida Power & Light Company Mail Stop EX/JB 700 Universe Blvd Juno Beach, FL 33408

SUBJECT:

SCHEDULE CORRECTION FOR THE REVIEW OF THE TURKEY POINT NUCLEAR GENERATING UNIT NOS. 3 AND 4 SUBSEQUENT LICENSE RENEWAL APPLICATION (EPID NOS. L-2018-LNE-0001/L-2018-RNW-0002)

Dear Mr. Nazar:

Enclosed is a corrected schedule for the review of the Turkey Point Nuclear Generating Unit Nos. 3 and 4, subsequent license renewal application. This schedule has been revised to reflect the issuance of the draft Supplemental Environmental Impact Statement (SEIS) on March 29, 2019. In addition, the milestone date for the public meeting on the draft SEIS has been changed from April 2019 to May 2019. These schedules have been revised to reflect a minor delay that resulted from the Federal government partial shutdown. The partial shutdown delayed the National Park Service (a cooperating agency on this review) from performing a review of those portions of the draft SEIS for which they possess special expertise for environmental issues pertaining to the areas in and around Biscayne National Park. At this time, it is not clear if there will be an impact to the schedule for issuance of the final SEIS as this is highly dependent on the comments received on the draft SEIS. We will keep you apprised of any future impacts to the review schedule.

Additionally, the staff has determined that initial issuance of the safety evaluation report (SER) will contain open items. Specifically, the areas identified as open items are associated with aging management during the subsequent period of extended operation (i.e., from 60 to 80 years of operation) of: irradiated structural steel reactor pressure vessel supports, concrete containment prestressed tendons, and buried and underground piping and tanks. Additional interactions with your staff have been necessary to achieve resolution for these three review topics. These additional interactions have contributed to the need to revise the SER issuance date from April 2019 to May 2019 and, correspondingly, revise the Advisory Committee on Reactor Safeguards (ACRS) Subcommittee on Plant License Renewal meeting date from May 2019 to June 2019. At this time, the staff expects to present the results of its review to close these open items at the ACRS Subcommittee meeting in June 2019 and provide an updated SER following this ACRS meeting. In addition, as a result of this change, the ACRS Full Committee meeting schedule and issuance of the SER has been moved to September 2019.

If you have any questions regarding this matter, please contact Ms. Lois James, Project Manager, for the safety review, by telephone at 301-415-3306 or by email at lois.james@nrc.gov or Mr. William Burton, Project Manager, for the environmental review of the Turkey Point license renewal application, by telephone at 301-415-6332 or by e-mail at william.burton@nrc.gov.

Sincerely,

/RA/

Eric R. Oesterle, Chief License Renewal Projects Branch Division of Materials and License Renewal Office of Nuclear Reactor Regulation Docket Nos: 50-250 and 50-251

Enclosure:

Revised review schedule cc w/encl: Listserv

ML19127A070 OFFICE PM:MRPB:DMLR LA:MRPB:DMLR PM:MRPB:DMLR (A) BC:MENB:DMLR NAME LJames YEdmonds*

WBurton KErwin DATE 5/8/2019 with comments in ADAMS attached 5/8/2019 5/8/2019 5/9/2019 OFFICE (A):D:DMLR BC:MRPB:DMLR NAME JDonoghue EOesterle DATE 5/9/2019 5/9/2019

Additional Distribution Ms. Sarah Cody, Chief Office of Historic Preservation Stephen P. Clark Center 111 NW 1st St. - 12th Floor Miami, FL 33128 Mr. Jason Aldridge Deputy State Historic Preservation Officer Florida Department of State 500 South Bronough Street R.A. Gray Building Tallahassee, FL 32399-0250 Mr. Billy Cypress, Chairman Miccosukee Tribe of Indians of Florida Tamiami Station P.O. Box 440021 Miami, FL 33144 Mr. James Floyd, Principal Chief Muscogee (Creek) Nation Office of the Administration P.O. Box 580 Okmulgee, OK 74447 Ms. Stephanie A. Bryan, Tribal Chair Poarch Band of Creek Indians 5811 Jack Springs Road Atmore, AL 36502 Ms. Carolyn White Acting Tribal Historic Preservation Officer Poarch Band of Creek Indians 5811 Jack Springs Road Atmore, AL 36502 Mr. Greg Chilcoat, Principal Chief Seminole Nation of Oklahoma Mr. Theodore Isham Tribal Historic Preservation Officer Seminole Nation of Oklahoma P.O. Box 1498 Wewoka, OK 74884 Mr. Marcellus W. Osceola, Chairman Seminole Tribe of Florida 6300 Stirling Road Hollywood, FL 330241 Mr. Paul Backhouse Tribal Historic Preservation Officer Seminole Tribe of Florida Ah-Ta-Thi-Ki Museum 30290 Josie Billie Hwy, PMB 1004 Clewiston, FL 33440 Caroline McLaughun National Parks Conservation Association 450 N. Part Rd, Ste 301 Hollywood, FL 33021 Andrew Carter Miami Waterkeeper 2103 Coral Way, 2nd Floor Miami, FL 33145 Kelly Cox Miami Waterkeeper 2103 Coral Way, 2nd Floor Miami, FL 33145 Arnuni Kapur Duke Energy 410 S. Wilmington St.

Raleigh, NC 27602 Wewoka, OK 74884 P.O. Box 1498 Wendy Brainard, citizen John Marquardt, citizen Patricia Marin, citizen Felipe Marin, citizen Erik Gonzales, citizen Matt Schwartz, citizen George Cavros, citizen Yvonne Knowles, citizen

Enclosure TURKEY POINT NUCLEAR GENERATING UNIT NOS. 3 AND 4 SUBSEQUENT LICENSE RENEWAL APPLICATION REVISED REVIEW SCHEDULE Milestone Scheduled Actual Receive subsequent license renewal application (SLRA) 01/2018 01/30/2018 Publish Federal Register Notice (FRN) - LRA availability 04/2018 04/18/2018 Publish FRN - acceptance/rejection and opportunity for hearing 05/2018 05/02/2018 Publish FRN - Notice of Intent to Prepare an Environmental Impact Statement and Environmental Scoping meeting 05/2018 05/22/2018 Public Meeting - License Renewal Overview and Environmental Scoping meeting 05/2018 05/31/2018 Environmental scoping period ends 06/2018 06/21/2018 Deadline for filing hearing requests and petitions for intervention 07/2018 08/01/2018*

Issue draft supplemental environmental impact statement (SEIS) 03/2019 03/29/2019 Public Meeting - draft SEIS meeting 05/2019 05/01/2019 Issue safety evaluation report (SER) with open items 05/2019 End of draft SEIS comment period 05/2019 Advisory Committee on Reactor Safeguards (ACRS)

Subcommittee meeting 06/2019 Issue final SER 07/2019 Issue final SEIS 08/2019 U.S. Environmental Protection Agency FRN Published -

availability of final SEIS 08/2019 ACRS full committee meeting 09/2019 Decision - Director, NRR 10/2019 Commission decision, if hearing granted TBD