Schedule Revision for the Review of the Turkey Point Nuclear Generating Unit Nos. 3 and 4 Subsequent License Renewal Application (EPID Nos. L-2018-LNE-0001/L-2018-RNW-0002
ML19123A220
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 05/03/2019
From: Eric Oesterle
NRC/NRR/DMLR/MRPB
To: Nazar M
Florida Power & Light Co
James L, NRR-DMLR 415-3306
References
EPID: L-2018-LNE-0001, EPID: L-2018-RNW-0002
Download: ML19123A220 (5)


Text

May 3, 2019 Mr. Mano Nazar President and Chief Nuclear Officer Nuclear Division Florida Power & Light Company Mail Stop EX/JB 700 Universe Blvd Juno Beach, FL 33408

SUBJECT:

SCHEDULE REVISION FOR THE REVIEW OF THE TURKEY POINT NUCLEAR GENERATING UNIT NOS. 3 AND 4 SUBSEQUENT LICENSE RENEWAL APPLICATION (EPID NOS. L-2018-LNE-0001/L-2018-RNW-0002)

Dear Mr. Nazar:

Enclosed is a revised schedule for the review of the Turkey Point Nuclear Generating Unit Nos. 3 and 4, subsequent license renewal application. This schedule has been revised to reflect the issuance of the draft Supplemental Environmental Impact statement (SEIS) on March 29, 2019. In addition, the milestone date for the public meeting on the draft SEIS has been changed from April 2019 to May 2019. These schedules have been revised to reflect a minor delay that resulted from the Federal government partial shutdown. The partial shutdown delayed the National Park Service (a cooperating agency on this review) from performing a review of those portions of the draft SEIS for which they possess special expertise for environmental issues pertaining to the areas in and around Biscayne National Park. At this time, it is not clear if there will be an impact to the schedule for issuance of the final SEIS as this is highly dependent on the comments received on the draft SEIS. We will keep you apprised of any future impacts to the review schedule.

Additionally, the staff has determined that initial issuance of the safety evaluation report (SER) will contain open items. Specifically, the areas identified as open items are associated with aging management during the subsequent period of extended operation (i.e., from 60 to 80 years of operation) of: irradiated structural steel reactor pressure vessel supports, concrete containment prestressed tendons, and buried and underground piping and tanks. Additional interactions with your staff have been necessary to achieve resolution for these three review topics. These additional interactions have contributed to the need to revise the SER issuance date from April 2019 to May 2019 and, correspondingly, revise the Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting date from May 2019 to June 2019. At this time, the staff expects to present the results of its review to close these open items at the ACRS Subcommittee meeting in June 2019 and provide an updated SER this ACRS meeting.

M. Nazar If you have any questions regarding this matter, please contact Ms. Lois James, Project Manager, for the safety review, by telephone at 301-415-3306 or by email at lois.james@nrc.gov or Mr. William Burton, Project Manager, for the environmental review of the Turkey Point license renewal application, by telephone at 301-415-6332 or by e-mail at william.burton@nrc.gov.

Sincerely,

/RA Bennett Brady for/

Eric R. Oesterle, Chief License Renewal Projects Branch Division of Materials and License Renewal Office of Nuclear Reactor Regulation Docket Nos: 50-250 and 50-251

Enclosure:

Revised review schedule cc w/encl: Listserv

ML19123A220 OFFICE LA:MRPB:DMLR BC:MENB:DMLR D:DMLR BC:MRPB:DMLR NAME SLent KErwin (A) JDonoghue (A) EOesterle (BBrady) for DATE 5/3/2019 5/3/2019 5/3/2019 5/3/2019

M. Nazar Additional Distribution Ms. Sarah Cody, Chief P.O. Box 1498 Office of Historic Preservation Mr. Theodore Isham Stephen P. Clark Center Tribal Historic Preservation Officer 111 NW 1st St. - 12th Floor Seminole Nation of Oklahoma Miami, FL 33128 P.O. Box 1498 Wewoka, OK 74884 Mr. Jason Aldridge Deputy State Historic Preservation Officer Mr. Marcellus W. Osceola, Chairman Florida Department of State Seminole Tribe of Florida 500 South Bronough Street 6300 Stirling Road R.A. Gray Building Hollywood, FL 330241 Tallahassee, FL 32399-0250 Mr. Paul Backhouse Mr. Billy Cypress, Chairman Tribal Historic Preservation Officer Miccosukee Tribe of Indians of Florida Seminole Tribe of Florida Tamiami Station Ah-Ta-Thi-Ki Museum P.O. Box 440021 30290 Josie Billie Hwy, PMB 1004 Miami, FL 33144 Clewiston, FL 33440 Mr. James Floyd, Principal Chief Caroline McLaughun Muscogee (Creek) Nation National Parks Conservation Association Office of the Administration 450 N. Part Rd, Ste 301 P.O. Box 580 Hollywood, FL 33021 Okmulgee, OK 74447 Andrew Carter Ms. Stephanie A. Bryan, Tribal Chair Miami Waterkeeper Poarch Band of Creek Indians 2103 Coral Way, 2nd Floor 5811 Jack Springs Road Miami, FL 33145 Atmore, AL 36502 Kelly Cox Ms. Carolyn White Miami Waterkeeper Acting Tribal Historic Preservation Officer 2103 Coral Way, 2nd Floor Poarch Band of Creek Indians Miami, FL 33145 5811 Jack Springs Road Atmore, AL 36502 Arnuni Kapur Duke Energy Mr. Greg Chilcoat, Principal Chief 410 S. Wilmington St.

Seminole Nation of Oklahoma Raleigh, NC 27602 Wewoka, OK 74884 Wendy Brainard, citizen John Marquardt, citizen Patricia Marin, citizen Felipe Marin, citizen Erik Gonzales, citizen Matt Schwartz, citizen George Cavros, citizen Yvonne Knowles, citizen

TURKEY POINT NUCLEAR GENERATING UNIT NOS. 3 AND 4 SUBSEQUENT LICENSE RENEWAL APPLICATION REVISED REVIEW SCHEDULE Milestone Scheduled Actual Receive subsequent license renewal application (SLRA) 01/2018 01/30/2018 Publish Federal Register Notice (FRN) - LRA availability 04/2018 04/18/2018 Publish FRN - acceptance/rejection and opportunity for hearing 05/2018 05/02/2018 Publish FRN - Notice of Intent to Prepare an Environmental 05/2018 05/22/2018 Impact Statement and Environmental Scoping meeting Public Meeting - License Renewal Overview and Environmental 05/2018 05/31/2018 Scoping meeting Environmental scoping period ends 06/2018 06/21/2018 Deadline for filing hearing requests and petitions for intervention 07/2018 08/01/2018*

Issue draft supplemental environmental impact statement (SEIS) 03/2019 03/29/2019 Public Meeting - draft SEIS meeting 05/2019 Issue safety evaluation report (SER) with open items 05/2019 End of draft SEIS comment period 05/2019 Advisory Committee on Reactor Safeguards (ACRS) 06/2019 Subcommittee meeting ACRS full committee meeting 07/2019 Issue SER 07/2019 Issue final SEIS 08/2019 U.S. Environmental Protection Agency FRN Published - 08/2019 availability of final SEIS Decision - Director, NRR 10/2019