License Renewal Pre-Application Coordination Meeting #1 River Bend Nuclear Generating Station, Unit 1 (RBNGS 1)

April 25, 2017 Emmanuel Sayoc, Safety Review Project Manager 1

Agenda

  • Introductions
  • Review process overview
  • Application requirements overview
  • Staff recommendations overview
  • Logistical considerations
  • Application
  • Site Information
  • Application of lessons learned
  • Review schedule overview
  • Second Pre-application coordination meeting overview 2

Contact Information Safety Project Manager Emmanuel Sayoc (301) 415-4084 emmanuel.sayoc@nrc.gov Environmental Project Manager TBD 3

License Renewal Process Environmental Consultation Review & Comment License Renewal NRC Renewal Application Hearings*

Decision Submitted to NRC Safety Review by Review ACRS

  • If a Request for Hearing is Granted 4

Safety Review Application Safety Evaluation Onsite Accepted and Audits Inspections by NRC Safety Evaluation ACRS Meeting NRC Decision Report Issued Hearings 5

Environmental Review Application Public Scoping Prepare Draft Accepted Meeting EIS by NRC Public Comment Issue Draft Address Public Meeting on EIS for Comments Draft EIS Public Comment Prepare and Issue Hearings Record of Decision Final EIS 6

The Application &

Supporting Documents

  • Letter to the Document Control Desk with a CD application
  • The Application and Appendices o 3 hard copies o 50 CDs with Application and Appendices w/

active links, FSAR, Drawings

  • Drawings o 1 CD o 4 hard copy 18x22 w/ no SGI
  • AMR table 2 items in MS Excel file 7

Logistical Considerations

  • NRC requests recommendations and contact info for the following:

o Public Meeting Venue o Public Libraries o Local Publications and News Papers o Hotel and Lodging

Application Overview NRC requests a brief on the application:

  • Application main sections
  • Break Down o New or existing o Consistent o Exceptions o Enhancements o Plant specific
  • Site unique programs
  • Time Limited Aging Analysis (TLAA) 9

Site Information

  • Major plant modifications that could affect the safety or environmental review
  • Identify the 15 most risk significant systems/components 10

Lessons Learned NRC requests that Entergy incorporate procedural and logistical lessons learned

  • Document portal
  • Communication with corporate and site organizations
  • Audit Support
  • RAI content and logistics 11

Lessons Learned Review safety technical issues from previous applications, apply lessons learned:

  • Fluence levels and modeling
  • Concrete alkali-silica reaction
  • Selective leaching of aluminum bronze
  • Condition of reactor vessel head closure studs 12

Lessons Learned Review safety technical areas of interest in previous applications, apply lessons learned (as applicable):

  • Electrical cables water submerged in underground manholes
  • Boraflex degradation in spent fuel pool storage
  • Containment liner degradation
  • Insufficient small bore weld inspection sample sizes
  • Insufficient environmentally-assisted fatigue methodology
  • Insufficient description, Reactor Vessel Surveillance AMP
  • Insufficient TLAAs on RPV materials not in beltline
  • Insufficient description, EQ of electrical cables AMP
  • Insufficient description, bolting integrity (air filled sys.) AMP 13

Review Schedule

  • Provide regular updates on application submission
  • Nominal review schedule - 22 months (no hearings)
  • Staff is working on optimization initiatives in schedule and safety evaluation report development
  • Safety and Environmental PMs will provide a schedule 14

Next Meeting Coordination Meeting #2 (May 2017)

  • Public meeting o HQ PM and technical staff o Licensee o Regional and Resident Staff
  • Licensee to provide overview of application and items from this meeting 15

Questions?

16